Current Developments in Eminent Domain and Oil and Gas Pipeline Construction (Under Construction - March 2014)

On February 19, 2014, a Nebraska state district court judge invalidated a portion of a Nebraska law that had, until the decision, permitted an alternate, streamlined method of obtaining eminent domain authority for the...more

3/20/2014 - Energy Keystone XL Pipeline Oil & Gas Pipelines TransCanada

Effective Use of CPM Scheduling

In a relatively recent case, Metcalf Construction Co. v. U.S., 107 Fed. Cl. 786 (2012), the U.S. Court of Federal Claims once again looked to the critical path method (CPM) in determining the allocation of damages in a...more

12/13/2013 - Calculation of Damages Construction Disputes Critical Path Method Damages Delay Claims

Under Construction - December 2013

Welcome to our final issue of Under Construction in 2013. We hope your year has been filled with health, happiness, peace and prosperity. We thank you for your readership, and we continue to appreciate the opportunities we...more

12/5/2013 - Anti-Indemnification Statutes Competitive Bidding Design-Bid-Build Foreclosure Mechanics Lien Mortgages

Under Construction - September 2013: Economic Loss in Colorado

The economic loss doctrine generally holds parties to the benefits, burdens and obligations set out in their contracts and bars tort claims such as negligence, misrepresentation and theft for purely economic loss when a...more

9/18/2013 - Construction Disputes Economic Loss Doctrine Misrepresentation Negligence Theft

Under Construction - September 2013

Welcome to the fall 2013 issue of Under Construction. In this issue, we focus on the economic loss doctrine and how the different courts in our firm’s footprint treat it similarly and differently. We hope you enjoy our review...more

9/17/2013 - Economic Loss Doctrine Indemnification Prompt Payment