The American Arbitration Association (AAA) has revised its Construction Industry Arbitration Rules and Mediation Procedures (Rules), effective July 1, 2015. Although some changes are relatively modest, others expand the powers of the arbitrator and may alter traditional assumptions underlying the selection of arbitration as a dispute resolution process for construction projects.

Introduction to the Revised Rules

The AAA’s recently revised Rules involve some changes that are relatively modest, while others may alter traditional assumptions underlying the selection of arbitration as a dispute resolution process for construction projects. For example, the Rules now provide a procedure for emergency relief that may result in more mid-project disputes being taken to arbitration or court, as the new Rule R-39 provides a party can seek emergency relief from either the AAA or a court, without violating the agreement to arbitrate. Also, the arbitrator is now expressly provided with the authority to sanction parties for violating his/her orders, and with specific authority to manage the discovery process and enforce compliance. Specific changes are discussed in detail below, and all parties to construction contracts with arbitration clauses are encouraged to review these changes carefully in conjunction with new and existing contracts, particularly because some contracts may require the use of the Rules in effect at the time of the dispute and not necessarily at the time of contracting.

Eight Specific Changes of Note

Rule R-7, Consolidation or Joinder, previously provided no guidance on timing concerning requests for joinder or consolidation, or any responses. The new Rule R-7 now provides that any requests for joinder or consolidation must be submitted prior to the selection of a Merits Arbitrator or within 90 days of AAA’s determination that all filing requirements have been satisfied, whichever is later. Although later requests may be considered on a showing of good cause, properly effectuated, this rule change should generally work to ensure that requests for joinder and consolidation are made early on in the arbitration, in turn minimizing the headaches associated with late joinder and consolidation.

The new Rule R-7 also provides for response times—written responses to requests for consolidation or joinder must be provided within 10 days or 14 days, respectively, of AAA’s notice of the request. If a party to an ongoing AAA arbitration fails to object to a request for joinder, that party waives any objection. Although the phrasing is less than clear,1 the intent appears to be that failure by a non-party to object to a request for it to join an arbitration is deemed a denial of the request.

Notably, the new Rule R-7 also gives AAA the power to stay arbitrations affected by a joinder or consolidation request while the Rule R-7 arbitrator (appointed to resolve joinder and/or consolidation issues in the absence of agreement by the parties) determines whether joinder and/or consolidation is proper.

Rule R-10, Mediation, has been completely rewritten. Whereas the prior Rule R-10 merely served as an acknowledgment that the parties to an arbitration could mediate their dispute if desired, and set some boundaries for participation by an arbitrator in a mediation, the new Rule R-10 purports to require mediation if a claim or counterclaim is greater than $100,000. However, there are no teeth to this purported requirement. Unless the underlying arbitration agreement mandates mediation, any party can unilaterally opt out on notice to AAA and the other parties.

Rule R-23, Preliminary Management Hearing, has been rewritten in its entirety. The old Rule R-23 mandated a preliminary hearing and provided a list of potential topics to be discussed. The new Rule R-23 provides that the timing of the preliminary hearing (and arguably even its occurrence2) is “[a]t the discretion of the arbitrator . . . depending on the size and complexity of the arbitration.” The new Rule R-23 provides a generic statement that at the hearing “the parties and arbitrator should be prepared to discuss and establish a procedure for the conduct of the arbitration that is appropriate to achieve a fair, efficient, and economical resolution of the dispute,” and points to new Rules P-1 and P-2 for the topics to be discussed. Rule P-1 focuses on the purpose of the hearing, noting that “[c]are must be taken to avoid importing procedures from court systems, as such procedures may not be appropriate to the conduct of arbitrations as an alternative form of dispute resolution that is designed to be simpler, less expensive and more expeditious.” Rule P-2 contains a more detailed laundry list of topics to be discussed than the old Rule R-23, including allocation of costs related to burdensome discovery and whether site visits will be required.

Rule R-24, Pre-Hearing Exchange and Production of Information, has been expanded. The old Rule R-24 provided that the arbitrator could “direct . . . production of documents and other information” and “resolve any disputes concerning the exchange of information.” The new Rule R-24 begins with a statement about “efficient and economical resolution of the dispute,” but then provides that the arbitrator can “on application of a party or on the arbitrator’s own initiative:”

    i.       require the parties to exchange documents in their possession or custody on which they intend to rely;

   ii.       require the parties to update their exchanges of the documents on which they intend to rely as such documents become known to them;

  iii.       require the parties, in response to reasonable document requests, to make available to the other party documents, in the responding party’s possession or custody, not otherwise readily available to the party seeking the documents, reasonably believed by the party seeking the documents to exist and to be relevant and material to the outcome of the disputed issues; and

  iv.       require the parties, when documents to be exchanged or produced are maintained in electronic form, to make such documents available in the form most convenient and economical for the party in possession of such documents, unless the arbitrator determines that there is good cause for requiring the documents to be produced in a different form. The parties should attempt to agree in advance upon, and the arbitrator may determine, reasonable search parameters to balance the need for production of electronically stored documents relevant and material to the outcome of disputed issues against the cost of locating and producing them.

This has the potential of equaling the document discovery burden in ordinary litigation, so parties anticipating a reduced burden in arbitration would do well to consider the ramifications of this rule.

A brand new rule, Rule R-25, Enforcement Powers of the Arbitrator, has been introduced to explicitly provide the arbitrator with the “authority to issue any orders necessary to enforce the provisions of Rules R-23 and R-24 and to otherwise achieve a fair, efficient and economical resolution of the case.” Examples provided include issuance of confidentiality orders to protect confidential information, imposition of electronic search parameters, and allocation of costs of document production. Most importantly, however, Rule R-25 provides that the arbitrator may draw adverse inferences, exclude evidence, and award costs in the event of a party’s “willful non-compliance” with an order of the arbitrator.

Rule R-34, Dispositive Motions, is also new—it allows the arbitrator to entertain motions disposing of “all or part of a claim, or narrow[ing] the issues in a case.”

Rule R-39, Emergency Measures of Protection, is one of the most intriguing of the new rules, affecting only arbitration agreements entered after July 1, 2015, unless otherwise agreed by the parties. Under Rule R-39, a party can petition the AAA for appointment of an emergency arbitrator to grant emergency relief. The AAA will appoint an arbitrator within one business day, and that arbitrator can “enter an interim order or award granting the relief and stating the reason therefore.” Parties relying on arbitration clauses to ensure that mid-project disputes are kept between the parties would do well to consider the ramifications of this rule, as it further provides that “[a] request for interim measures addressed by a party to a judicial authority shall not be deemed incompatible with this rule, the agreement to arbitrate or a waiver of the right to arbitrate.”3

Rule R-60, Sanctions, is new and provides the arbitrator with the authority to “order appropriate sanctions” when a party does not comply with the arbitrator’s orders or the party’s obligations under the rules. Although the rule expressly prohibits entering a default award as a sanction, it allows for sanctions “limit[ing a] party’s participation in the arbitration” and adversely determining issues, provided the order is explained in writing and evidence and argument were submitted.

Other changes include failure to timely object to a potential conflict with the arbitrator as possible waiver of that conflict (Rule R-19, subdivision (a)); clarification of evidence required in the absence of participation by a party (Rule R-32, formerly Rule R-31); express authorization for the arbitrator to disregard a written witness statement or expert report if the witness or expert fails to appear for examination (Rule R-36, subdivision (b)); express authorization for the arbitrator to order a witness who is unable or refuses to testify at the hearing, to testify at some location where the witness is willing or can be legally compelled to testify; (Rule R-36, subdivision (c)); authorization for the chair of a three-arbitrator panel to delegate resolution of discovery disputes to a single member of the panel (Rule R-45); elevation of the ceiling for applicability of fast track procedures to $100,000 (Rule F-1); elevation of the ceiling for a presumed documents-only hearings to $25,000 (Rule F-1); provision for unilateral extension of timelines by the arbitrator (Rule F-12); and reorganization of Rule L-4, “Preliminary Management Hearing and Management of Proceedings,” and former Rule L-5 into a single rule referencing new Rules P-1 and P-2, discussed supra.

Conclusion

Although the recent changes to the Rules may well end up in more efficient resolution of disputes in arbitration under those Rules, these changes may not necessarily comport with traditional assumptions concerning arbitration as a construction dispute resolution method. All construction project participants whose contracts contain arbitration clauses are encouraged to review the Rules to ensure that they know exactly what they have bargained for.


1. “If the party sought to be joined is not a party to an ongoing arbitration administered by the AAA, the party seeking joinder shall comply with the provisions of Rule 4(a) as to that party. If no response to the joinder request is received by a party that is not a party to an ongoing arbitration, that party will be deemed to have denied the arbitration request.” Rule R-7(c) (emphasis added.). Presumably the underlined “by” was intended to be “from.” Also, the choice of “denied” instead of rejected as to the effect of a failure to object is curious.

2. “At the discretion of the arbitrator, and depending on the size and complexity of the arbitration, a preliminary hearing should be scheduled as soon as practicable after the arbitrator has been appointed.”

3. Note this last is consistent with California law. See California Code of Civil Procedure § 1281.8.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Pillsbury Winthrop Shaw Pittman LLP | Attorney Advertising

Written by:

Pillsbury Winthrop Shaw Pittman LLP
Contact
more
less

Pillsbury Winthrop Shaw Pittman LLP on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.