Court Holds That CEQA Does Not Limit Agencies’ Authority to Impose Mitigation Pursuant to Other Laws

Perkins Coie
Contact

Perkins Coie

The First District Court of Appeal ruled that CEQA does not constrain an agency’s authority to administer and enforce any other laws, including those authorizing imposition of mitigation requirements. Thus, even after an EIR for a project has been certified, a regional water board, as a responsible agency, can impose additional mitigation on the project through waste discharge requirements (WDRs) issued under the Porter-Cologne Water Quality Control Act. Santa Clara Valley Water District v. San Francisco Bay Regional Water Quality Control Board, No. A157127, 2020 WL 7706795 (Cal. Ct. App. Dec. 29, 2020).

The Santa Clara Valley Water District brought this case to challenge the San Francisco Bay Regional Water Quality Control Board’s WDRs for a flood control project on Upper Berryessa Creek near Milpitas and San Jose. The Army Corps of Engineers was responsible for the design and construction of the flood control project, while the District was the project sponsor. In January 2016, the District issued a final EIR, which found that impacts on water resources would be less-than-significant with mitigation.

Pursuant to section 401 of the Clean Water Act, the Corps applied to the Regional Board for a certification that the project would not violate state water quality laws. Facing political pressure to issue the section 401 certification quickly (because the project was needed to protect a soon-to-open BART station and was at risk of losing federal funding if the certification was delayed), the Regional Board agreed to issue the certification in March 2016. The certification stated that the Regional Board, as a responsible agency under CEQA, found that environmental impacts during construction that were within its jurisdiction would be mitigated to less-than-significant levels. The Regional Board’s certification also stated that it would later issue WDRs to compensate for water quality impacts attributable to the project’s design, operation, and maintenance.

In April 2017, the Regional Board issued a WDR order requiring additional mitigation to compensate for the project’s impacts on water quality. The WDR order required enhancing 15,000 linear feet or 15 acres of waters of the state, which could be satisfied by one of the District’s other planned projects.

Waste Discharge Requirements. The court rejected the District’s claim that the Regional Board lacked authority to issue WDRs under the Porter-Cologne Act because the project would not cause a discharge of waste. The District argued that substances must be useless, unneeded, or discarded to constitute waste for purposes of the Porter-Cologne Act, and that the project’s sedimentation effects did not meet this test. The court ruled that even if the District’s interpretation of the law were correct, the project would result in a discharge of waste: The project’s widening of the creek bed would slow the flow of water and lead to increased sedimentation in the creek; this additional sediment would not be useful or necessary and would require periodic removal.

CEQA. The District also argued that the Regional Board’s failure to impose mitigation through the CEQA process barred it from later imposing mitigation through WDRs issued under the Porter-Cologne Act. The District claimed that if the Regional Board disagreed with the mitigation findings in the EIR, it should have availed itself of the remedies available to a responsible agency that believes an EIR is not adequate, as set forth in CEQA Guidelines section 15096(e):filing a lawsuit within 30 days, preparing a subsequent EIR if permissible, or assuming the lead agency role. According to the District, the Regional Board waived any objections to the adequacy of mitigation described in the EIR by failing to take any of these actions. The court ruled that the Regional Board had independent authority to impose mitigation through WDRs pursuant to the Porter-Cologne Act, citing Public Resources Code section 21174, which provides that CEQA does not limit an agency’s power to administer or enforce any other law.

[View source.]

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Perkins Coie | Attorney Advertising

Written by:

Perkins Coie
Contact
more
less

Perkins Coie on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide