Don't Forget The 150-Day Rule In Virginia

more+
less-

On the first day of 2009, I wrote a post about the "150-day rule" in Virginia: Virginia's Interesting 150 Day Rule. Therein I offered a pithy explanation of the rule:

"From the last day of work, the claimant must count backwards 150 days. Generally speaking, a contractor is not allowed to include any labor or materials supplied outside this window in its mechanics lien."


LOADING PDF: If there are any problems, click here to download the file.

Published In: Construction Law Updates

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Zlien | Attorney Advertising

×