FERC Alters Mystic’s Cost-of-Service Agreement; Commissioner Glick Dissents Again

Troutman Pepper
Contact

Troutman Pepper

On December 21, 2020, FERC either set aside in part or modified its previous cost-of-service compensation decision allowing Constellation Mystic Power, LLC (“Mystic”) to continue operating two gas-fired generation facilities (“Mystic 8 and 9”) fueled exclusively by an affiliate, Everett Marine Terminal (“Everett”), which, like Mystic, is owned by Exelon Generation Company, LLC (“Exelon”).  Commissioner Richard Glick dissented, reiterating his belief that FERC has exceeded its jurisdiction to “bail out” the liquified natural gas (“LNG”) import terminal.

Originally, Mystic proposed to retire its generation units in 2018, but ISO New England Inc. (“ISO-NE”) determined Mystic’s capacity was required to avoid reliability risks during its 2022-2023 and 2023-2024 capacity commitment periods.  ISO-NE also determined the retirements threatened the financial viability of the Everett LNG station, which created an unacceptable fuel security risk for the region.  As such, ISO-NE, Mystic and Everett entered into a cost-of-service agreement (“Mystic Agreement”) to provide for the continued operation of Mystic 8 and 9 through May 31, 2024.  FERC accepted the Mystic Agreement in contentious proceedings that led to various rehearing requests of previously-issued rehearing orders (see July 30, 2020 edition of the WER).  In the December 21 order, however, FERC addressed the limited issues of tank congestion charges associated with Everett’s non-jurisdictional service, as well as a clawback mechanism for certain capital expenditures to protect ratepayers should Mystic decide to participate in the ISO-NE market after the termination of the Mystic Agreement.

Upon reconsideration, FERC changed its position and set aside its prior orders on two issues.  First, FERC found that a methodology for calculating tank congestion charges and costs could be necessary to demonstrate that ISO-NE ratepayers pay only the costs of tank congestion attributable to serving Mystic under the Mystic Agreement.  Rather than require Mystic to file any such methodology, however, FERC determined that the costs could be reviewed during Mystic’s cost-of-service true-up process.  FERC also directed Mystic to remove the phrase “that were expensed” from the clawback provision to ensure that it would apply to costs “that are incurred” rather than those “that were expensed,” thus avoiding a potential accounting loophole that could be used to circumvent the return capital expenditures to New England ratepayers in the event Mystic decided to participate in the ISO-NE market after the termination of the Mystic Agreement.

As with the previous orders in this proceeding, Commissioner Glick wrote separately in dissent.  Glick explained his view that the retention of Mystic was really aimed at bailing out a non-jurisdictional LNG facility and that by doing so, FERC has exceeded its jurisdiction.  According to Glick, the December 21 order underscores the extent to which many of the issues that are nominally related to Mystic pertain first and foremost to the operation of the non-jurisdictional Everett facility.

Recently sworn-in Commissioner Allison Clements did not participate in the order.

A copy of the order is available here.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Troutman Pepper | Attorney Advertising

Written by:

Troutman Pepper
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Troutman Pepper on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide