The Illinois Supreme Court has issued an opinion—in LaSalle Bank v. Cypress Creek 1, LP 1—clarifying the relative priorities of a lender and mechanics lien claimants to the proceeds of a foreclosure sale where the lender’s mortgage was recorded before the mechanics liens attached. The court held that a lender has priority up to the value of the property when the construction contract underlying the lien was entered, plus the value of the improvements that were paid for out of the construction loan secured by the mortgage. The court concluded a mechanics lien holder has priority only to the value of the improvements for which it has not been paid. This case overruled Mitchell v. Robinovitz, which allowed a lien claimant’s priority claim to include the value of all improvements, including those provided by others. Also, the dissenting opinion noted the majority opinion "does not apply the statute’s plain language."
This case does not address projects encumbered by a mortgage recorded after the construction contract is executed. However, the court left the door open for a mortgagee that records after the date of a construction contract to claim equitable subrogation rights arising from payments that it advances for the work of that contract, and thereby claim priority to that part of the value of the improvements. Despite stating that it avoided reaching the lender’s claim of equitable subrogation based on the amounts that it paid for construction, the court’s rationale is not at odds with an equitable subrogation claim.
Please see full alert below for more information.
Firefox recommends the PDF Plugin for Mac OS X for viewing PDF documents in your browser.
We can also show you Legal Updates using the Google Viewer; however, you will need to be logged into Google Docs to view them.
Please choose one of the above to proceed!
LOADING PDF: If there are any problems, click here to download the file.