Today, Xcel Energy filed its 2016 – 2030 Integrated Resource Plan.  Xcel Energy’s proposal is fairly significant in scope – it proposes to cut CO2 emissions by 40% by 2030, add new renewable and natural gas generating resources, and lay the stage for reforming the resource planning process conistent with its framework filing and proposals from the e21 Initiative.  Specifically, Xcel Energy’s preferred plan contains the following elements:

  • Add approximately 1,800 MW of wind resources;
  • Add approximately 1,700 MW of utility-scale solar resources;
  • Add approximately 1,750 MW of natural gas peaking resources;
  • Operate the carbon-free, baseload nuclear plants through at least 2030;
  • Operate Sherco Units 1 and 2 at reduced levels through 2030;
  • Extend the life of Blue Lake Units 1-4 an additional four years through 2023; and
  • Modify the procedural review process by inviting stakeholder participation in modeling discussions prior to the traditional discovery and comment processes. 

The assumptions underlying this proposal, as well as other parties’ proposed alternatives, will be debated over the next year.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Stoel Rives LLP | Attorney Advertising

Written by:

Stoel Rives LLP
Contact
more
less

Stoel Rives LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide