Key Amendments to the San Francisco Administrative Code Governing CEQA Procedures, Appeals and Public Notice Requirements Go Into Effect

by Holland & Knight LLP
Contact

Project Sponsors Will Be Interested in Three Key Changes to the San Francisco CEQA Process

The San Francisco Board of Supervisors ("board") unanimously adopted Ordinance No. 161-13 ("ordinance"), substantially amending Chapter 31 of the San Francisco Administrative Code, which governs administration of the California Environmental Quality Act (CEQA) in the city and county of San Francisco ("city"). The ordinance, which was adopted on second reading on July 23, 2013, became fully operative on September 25, 2013 — five days after the secretary of the Planning Commission filed a memorandum with the clerk of the board documenting that required tasks, including updates to the Planning Department's website, had been completed.

Three components of the ordinance are particularly interesting to project sponsors:

  1. comprehensive revision of Administrative Code provisions governing appeals of CEQA decisions to the board
  2. expanded public notice requirements
  3. clarification of environmental review requirements for modification of CEQA-exempt projects

This alert provides an overview of these three key topics.

1. Clarification of Process for Appealing CEQA Decisions to the Board of Supervisors

The ordinance comprehensively revises Administrative Code provisions governing appeal of CEQA decisions to the board. These revisions provide welcome clarification to a previously uncertain CEQA appeals process in San Francisco. Prior to adoption of the ordinance, Administrative Code Chapter 31 included provisions governing environmental impact report (EIR) appeals to the board. However, although the CEQA statute was amended in 2003 to allow appeal to a lead agency's elected body approval of a negative declaration or exemption determination (Senate Bill 1393), the city had not yet updated Chapter 31 to outline appeals processes for negative declarations or exemption determinations. Without Administrative Code provisions governing appeals of negative declarations and exemption determinations, project sponsors relying on these categories of CEQA approvals faced uncertainty about potential CEQA appeals throughout the development process.

The following is a summary of key clarifications to the CEQA appeals process implemented by the ordinance.

  • Appealable Decisions: The ordinance provides that three types of CEQA decisions may be appealed to the board:
    1. Planning Commission certification of a final EIR
    2. adoption of a negative declaration by the first decision-making body
    3. Planning Department or other city department determination that a project is exempt from CEQA
  • Deadlines and Standing: The ordinance clarifies deadlines and standing to appeal city CEQA decisions as follows: 
  • EIR: An EIR appeal must be filed within 30 days after the Planning Commission's certification of the EIR. An EIR appeal may only be filed by a person or entity that submitted comments on a draft EIR during the public review period or at a public hearing on the EIR.
  • Negative Declaration: A negative declaration must be appealed within 30 days after the "approval action," defined for projects requiring preparation of a negative declaration as approval of the project by the first city decision-making body that adopts the negative declaration. A negative declaration appeal may be filed by any person or entity that filed an appeal of the preliminary negative declaration during the public comment period.
  • CEQA Exemption: A CEQA exemption determination must be appealed within 30 days after the "approval action," defined for private projects exempt from CEQA as the first approval of the project in reliance on the exemption by the Planning Commission following a noticed public hearing (including a discretionary review hearing as provided in Planning Code Section 311 or 312 for building permits and change of use in certain zoning districts). If no Planning Commission hearing is required, the "approval action" is either the first approval of the project in reliance on the exemption by another city commission, board, or official following a noticed public hearing granting an entitlement authorizing the project applicant to carry out the project, or the issuance of the building permit or other entitlement in reliance on the exemption, without a public hearing. If the exemption determination is not posted on the city's website or otherwise properly noticed, the CEQA decision may be appealed within 30 days after the appellant's discovery of the exemption determination. Any person or entity may appeal an exemption determination.

The ordinance also establishes general deadlines and procedures applicable to all CEQA appeals to the board. If an appeal is accepted, the clerk of the board must schedule a hearing on the appeal within 21 to 45 days after the expiration of the applicable appeal period. All stakeholders, including members of the public, the appellant, project sponsors or city agencies sponsoring the proposed project, must submit written materials no later than noon, 11 days prior to the scheduled public hearing on the appeal. The board must decide the CEQA appeal within 30 days after the hearing on the appeal.

Notably, under the ordinance, a CEQA appeal to the board may put a project on hold. For projects that require multiple city approvals, after the appeal is scheduled for hearing and until the CEQA decision is affirmed by the board, the ordinance provides that no further actions to approve the project may be taken by the board or other city agencies or departments, unless necessary to abate hazards to public health and safety.

  • Final Approval and CEQA Statute of Limitations for Judicial Appeal: Under the ordinance, a project is considered finally approved either when the appeal period expires, if no appeal is filed, or on the date the board affirms the CEQA decision if there is an appeal.

    After a project is considered finally approved, the ordinance authorizes that the environmental review officer may file a notice of determination (for an EIR or negative declaration) triggering the 30-day CEQA statute of limitations, or a notice of exemption (for CEQA-exempt projects) triggering the 35-day CEQA statute of limitations. In other words, project sponsors will know by the end of the Administrative Code appeal period whether the CEQA decision is being administratively appealed to the board. However, project sponsors must wait another 30 or 35 days after the end of the Administrative Code appeal period or resolution of the appeal until the CEQA statute of limitations runs before knowing definitively whether a CEQA decision will be challenged in court.

2. Expanded Public Notice Requirements

The ordinance includes several new requirements designed to expand public notice of CEQA decisions. The ordinance requires that the Planning Department implement an electronic notification system for CEQA notices, and authorizes electronic transmittal of official notices required by Chapter 31. Public hearing notices are generally required to inform the public of rights to appeal CEQA decisions to the board.

All exemption determinations must be posted on the Planning Department's website. For projects requiring multiple discretionary permits or other approvals, the online exemption notice must also describe and evaluate the whole of the project that will result from all discretionary approvals and identify any additional discretionary approvals known at the time of the exemption determination.

The ordinance requires that a notice of intent to adopt a negative declaration or notice of availability of an EIR must be posted at the project site in a manner that assures that posters are visible from the closest public street or other public space. For private projects, the ordinance also requires that notice be sent to property owners and, to the extent practicable, to residential occupants within the area that is the subject of the negative declaration or EIR and within 300 feet of all exterior boundaries of that area.

3. Environmental Review Requirements for Modification of Exempt Projects

The ordinance establishes standards for determining whether additional CEQA review is required for a proposed change to a project that was previously determined to be exempt from CEQA. With implementation of these standards, project sponsors will have greater certainty about whether changes during the development of an exempt project require further CEQA review. These standards are particularly salient in San Francisco because the city has adopted numerous area plans covering portions of the city where new development and redevelopment are planned or ongoing, and projects within those area plans often qualify for community plan exemptions under CEQA.

Specifically, re-evaluation is required for a change in an exempt project that involves an expansion or intensification of the project, including a change that would expand the building envelope or change the use that would require notice under Planning Code Sections 311 or 312 (discretionary review of building permits and change of use in certain zoning districts), or a change in the project that would constitute a demolition. Additionally, re-evaluation is required if new information or evidence of substantial importance is presented to the environmental review officer that was not known when the exemption determination was issued, and that shows that the project no longer qualifies for the CEQA exemption. If a proposed change is considered a substantial modification, the environmental review officer must determine that the modified project is exempt and make a new exemption determination, or must conduct an initial study to determine the appropriate level of CEQA review.

Ordinance Brings Greater Clarity to San Francisco CEQA Process

The ordinance is now fully operative, providing greater clarity about the San Francisco CEQA process, in particular with respect to CEQA appeals and procedures for modifying exempt projects during the development process.

Written by:

Holland & Knight LLP
Contact
more
less

Holland & Knight LLP on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.