Mexico's Ministry of Energy Issues Interconnection Manual for Small Capacity Plants

Holland & Knight LLP
Contact

Holland & Knight LLP

Mexico's Energy Reform of 2013 opened activities of the country's power market to private investors. Before the reform, large-scale power generation was reserved to the state-run Comisión Federal de Electricidad (CFE), or to private investors through government contracts under an independent power producer structure. Self-supply and co-generation was allowed if complying with certain regulations.

Under the Power Industry Law, power plants with capacity below 0.5 megawatts (MW), designated as small capacity plants, are not required to obtain a permit from the Energy Regulatory Commission, or Comisión Reguladora de Energía (CRE). However, they can generate only for self-use or trade through a basic power supplier.

In December 2016, Mexico's Ministry of Energy issued the manual for requesting and keeping interconnection to the public power network of small capacity plants.

The manual is an important step toward completing the Mexican government's efforts to make the power market and Mexican wholesale electricity market (MEM) functional, as well as to opening opportunities to all investors sector-wide.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Holland & Knight LLP | Attorney Advertising

Written by:

Holland & Knight LLP
Contact
more
less

Holland & Knight LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide