New Jersey Delays Its Next Offshore Wind Solicitation for Transmission Planning

Mayer Brown
Contact

Mayer Brown - Energy Forward

The New Jersey Board of Public Utilities (NJBPU) announced that its third solicitation with a capacity target of 1,200 megawatts for New Jersey’s offshore wind (OSW) development will now be released by January 2023, instead of the previously announced September 2022 date, to account for its ongoing transmission-planning efforts.

NJBPU’s updated timeline takes into consideration New Jersey’s ongoing offshore “coordinated transmission solution” efforts. In January 2021, PJM Interconnection, L.L.C. (PJM) filed with the Federal Energy Regulatory Commission (FERC) for approval of a study agreement that would begin the implementation of a State Agreement Approach (SAA) to explore new collaborative frameworks to advance offshore wind energy and enable New Jersey’s offshore wind goals to be incorporated into the PJM transmission-planning process. Under the SAA, PJM and the NJBPU asked developers to “propose the optimal mix of onshore and offshore transmission facilities that provide the most economically efficient and reliable way of delivering power from offshore wind turbines to New Jersey customers.”1 Developers were asked to propose:

  1. upgrades to the existing grid to facilitate the offshore wind development;
  2. extensions of the onshore transmission grid closer to offshore wind locations;
  3. optimal landfall approaches to minimize/reduce environmental impacts and any necessary offshore substations; and
  4. interconnections between offshore substations (also known as a transmission “backbone”) to provide benefits of a networked offshore grid.

New Jersey is the first state within PJM to request that PJM initiate an SAA under the PJM Operating Agreement. On February 16, 2021, FERC accepted the SAA study approach.

Also in January 2022, PJM asked FERC (with the support of the NJBPU and other New Jersey state and environmental-sector stakeholders) to (1) accept and to allow PJM and the NJBPU to implement a proposed definitive SAA; (2) issue a favorable order on the SAA by April 15, 2022; and (3) permit the transmission planning that results from the SAA to be included in PJM’s regional transmission expansion plan. PJM will review the more than 80 different proposals that were submitted by transmission developers for consideration in its SAA process; will provide its recommendations to the state; and New Jersey will select the best transmission solutions, the costs of which will be assigned only to New Jersey ratepayers.

Even though PJM’s SAA process may result in more efficient and resilient transmission for OSW, FERC’s SAA proceeding has attracted dozens of interventions and comments. In answers to those filings, PJM and the NJBPU have stated that the FERC acceptance of the SAA would not establish a rate, or even a specific methodology for rate design, and that the costs of a project that is adopted under the SAA will not be cross-subsidized by out-of-state ratepayers of non-New Jersey utilities in PJM.

The NJBPU’s updated timeline for its next solicitation allows for the SAA process to be completed and the outcome to be incorporated into the third solicitation guidance documents.

SeeNew Jersey Advances Offshore Wind Transmission Proposal at Federal Energy Regulatory Commission” (nj.gov)

[View source.]

Written by:

Mayer Brown
Contact
more
less

Mayer Brown on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide