Post-Tender Resubmission: The Duty To Carry Subcontractors

more+
less-

In times of cost escalation, owners sometimes revise the scope of work and ask the lowest bidder to resubmit. What is a general contractor's duty to its subcontractors in this situation? In G&S Electric Ltd. v. Devlan Construction Ltd., the court held that the general contractor must only seek resubmissions from subcontractors it originally carried. This is so even if another subcontractor can offer a lower price.