We Are Just Getting Started: EPA Issues Much Anticipated Cleanup Plan for the Lower 8.3 Miles of the Lower Passaic River

Cole Schotz
Contact

The United States Environmental Protection Agency (“EPA”) recently issued the Record of Decision (“ROD”) for the lower 8.3 miles of the Lower Passaic River, which sets forth EPA’s $1.38 billion remedy. Potentially Responsible Parties (“PRPs”) will be interested to know that the $1.38 billion price tag only addresses one of the operable units that comprise the Diamond Alkali Superfund Site, which includes the 17-mile tidal stretch of the Lower Passaic River.

Sediment Mega Sites

In recent years, EPA has increasingly shifted more of its focus towards contaminated waterways, as opposed to the traditional single site Superfund site.  Of all the Superfund sites throughout the United States, “sediment mega sites” like the Gowanus Canal, Fox River, Portland Harbor and the Hudson River (just to name a few) are among the most complex to investigate, the largest in areal extent, and the most challenging and expensive to remediate.

Remediating sediment mega sites is a massive undertaking because of the persistent nature of the contaminants, the hundreds of potential sources and the migration and mixing of the contamination from tidal influences. It comes as no surprise that the remediation costs for these sediment mega sites can exceed $1 billion.

As is common for these waterways, the sediments in the Passaic River consist of a chemical soup of hazardous substances, including dioxin, PCBs, mercury, pesticides (including DDT) and heavy metals, created from generations of industrial operations along the waterways.  According to EPA, the remedy released in this ROD is the final action for the sediments in the lower 8.3 miles and an interim action for the water column in this section of the river.  Meanwhile, EPA and some of the PRPs are still studying the sediments in the upper 9 miles, the water column of the entire 17 miles of the river and the entire Newark Bay Study Area. The scope and cost of those remedies are unknown. We have a long road ahead of us.

The Proposed Remedy

The scope of the proposed remedy is extensive.  It includes:

  • Bank to bank dredging of approximately 3.5 million cubic yards of sediments;
  • Installing an engineered cap over the river bottom for the entire 8.3 miles;
  • Transporting the dredged materials to be dewatered, treated and disposed;
  • Long-term monitoring and maintenance of the engineered cap; and
  • Long-term monitoring of fish, crabs and sediment.

What’s Next?

If EPA is following its Superfund playbook for traditional sites, its next move is to issue “Special Notice Letters” to some or all of the PRPs inviting them to perform or fund the proposed remedy. Given the complexity of sediment mega sites, however, EPA has reserved the right to depart from the playbook.  EPA may therefore take a different approach enforcing this ROD, which is certainly possible in light of the overwhelming number of PRPs involved.  The next step is to see if EPA issues any Special Notice Letters, or takes an alternative approach.

Also, keep in mind the $1.38 billion remedy does not address natural resource damages (“NRDs”). The Natural Resource Trustees (which have jurisdiction over NRDs) have yet to publish an NRD Assessment.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Cole Schotz | Attorney Advertising

Written by:

Cole Schotz
Contact
more
less

Cole Schotz on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide