What Should Parties Do With Unusually Severe Weather on a Construction Project?

Burr & Forman
Contact

Rain. Snow. Sleet. Ice. The winter elements this year have been unusually severe throughout the country. While weather affects our everyday lives, it can be especially crippling to the delivery of materials, the schedule of activities, and the construction project as a whole.

In Daewoo Eng’g & Constr. Co. v. U.S., 557 F.3d 1332 (Fed. Cir. 2009), the contractor involved in building a 53-mile road around the island of Babeldaob submitted to the Corps a claim for delays and additional costs incurred because of high humidity, rainy weather and moist soils encountered on the project. The contractor sought $13 million in additional costs incurred and more than $50 million for future costs not yet incurred. The government filed a counter-claim alleging fraud and other violations.

Please see full publication below for more information.

LOADING PDF: If there are any problems, click here to download the file.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Burr & Forman | Attorney Advertising

Written by:

Burr & Forman
Contact
more
less

Burr & Forman on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide