When Is A California Construction Project Substantially Complete?

more+
less-

Short Answer:  It's a legal determination ultimately left up to a court, but takes into account a variety of factors.  Typically, the most controlling or popular factor is when the property is ready for occupancy.

Long Answer: This is the hardest question to answer in California's mechanics lien law. Unlike the majority of states, a mechanics lien must be filed in California within a certain period of time from the completion of the entire project and not simply conclusion of the claimant's work.  Accordingly, a party that furnishes at the very beginning of a job (i.e. the foundation or site work folks) may have a ton of time to file their lien, while the finishing contractors may have a tiny window.


LOADING PDF: If there are any problems, click here to download the file.

Published In: Construction Law Updates

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.