Recent revisions to the Texas lien laws, Tex. Prop. Code Ann. § 53.001, et seq., mandate the use of statutory lien release forms. Because the statute voids, as a matter of public policy, agreements that “adversely affect” payment bond or lien claims, many standard release forms previously employed by general contractors may be unenforceable. As a result, a general contractor’s subcontract administration practices should be carefully tailored to the statute if it wishes to resolve outstanding subcontractor claims during the course of a construction project.
The New Statutory Scheme Invalidates Many Prior Contracting Practices -
The required statutory forms for the release of lien rights and payment bond rights raise significant contracting issues for Texas general contractors. The new Texas statute significantly impairs a general contractor’s freedom to contract insofar as it relates to a subcontractor’s release of lien or payment bond rights.
Tex. Prop. Code Ann. § 53.281(a) provides that “[a]ny waiver and release of a lien or payment bond claim under this chapter is unenforceable unless a waiver and release is executed and delivered in accordance with this subchapter.” Tex. Prop. Code Ann. § 53.282 provides that a “statement purporting to waive, release, or otherwise adversely affect a lien or payment bond claim is not enforceable” unless it complies with the statutory form prescribed by Section 53.284 (emphasis added.)
Please see full alert below for more information.
Firefox recommends the PDF Plugin for Mac OS X for viewing PDF documents in your browser.
We can also show you Legal Updates using the Google Viewer; however, you will need to be logged into Google Docs to view them.
Please choose one of the above to proceed!
LOADING PDF: If there are any problems, click here to download the file.