Interconnections

News & Analysis as of

Federal Energy Regulatory Commission Issues Order to Eliminate Reactive Power Service Exemptions for Wind Generators

On June 16, 2016, the Federal Energy Regulatory Commission issued Order No. 827, a final rule that eliminates exemptions for wind generators from the requirement to provide reactive power services as a condition of taking...more

FERC’s Generator Interconnection Technical Conference Elicits Debate on Need for Interconnection Process Reforms

On May 13, 2016, the Federal Energy Regulatory Commission (FERC or the “Commission”) held a technical conference on generator interconnection issues in partial response to a June 2015 Petition filed by the American Wind...more

Maine examines interconnection standards

The Maine Public Utilities Commission has opened an inquiry into whether it should change its rule governing how small distributed generation resources may interconnect with the electric grid. This small generator...more

Can Solar Reboot Your Coal-Fired Plant Site?

The future of coal-fired plants is not bright. With regulations weighing on them, many plant operators are powering down and asking themselves what’s next for their sites. Solar offers viable options for reusing a plant site....more

Generator interconnection technical conference scheduled

The Federal Energy Regulatory Commission has scheduled a technical conference to generator interconnection issues, including interconnection of energy storage. The case has its origins in a 2015 petition to the...more

New York State Modifies Standardized Interconnection Requirements

Standardized Interconnection Requirements (SIR) Modified: On March 18, 2016, the New York State Public Service Commission (PSC) issued an Order Modifying Standardized Interconnection Requirements. The SIR, which has been...more

FERC Decision Signals that it Will Strictly Enforce Interconnection Procedures

On March 4, 2016, over the objections of the developer and a dissent from Commissioner Cheryl LaFleur, FERC issued an order authorizing the Midcontinent Independent System Operator, Inc. to terminate a generator...more

MISO Proposes Interconnection Queue Reform To Address Continuing Delays

Midcontinent Independent System Operator (MISO) is proposing another round of interconnection queue reform. On December 31, 2015, MISO filed proposed revisions to its Open Access Transmission, Energy and Operating Reserve...more

FERC Urged To Revise Generator Interconnection Procedures and Agreement

It has been over twelve years since the Federal Energy Regulatory Commission (FERC) issued the pro forma Large Generator Interconnection Procedures (LGIP) and pro forma Large Generator Interconnection Agreement (LGIA) for...more

7th Circuit Affirms FERC Finding That Wind Generators Are Responsible for Corrected Costs

On August 19, 2015, the United States Court of Appeals for the 7th Circuit denied two wind generators’ (“Generators”) petitions for review of various Federal Energy Regulatory Commission (FERC) orders assigning the corrected...more

Edge Provider Files First Interconnection Complaint

What appears to be the first complaint by an edge provider regarding interconnection has been submitted to the FCC. In the complaint, dated June 22, 2015, Commercial Network Services (CNS) identifies itself as an edge...more

American Wind Energy Association Seeks Revisions to Generator Interconnection Rules

On June 19, 2015, the American Wind Energy Association (“AWEA”) filed a petition with the Federal Energy Regulatory Commission (“FERC”) for a rulemaking to revise the FERC’s pro forma Large Generator Interconnection...more

Wind Power Trade Association Seeks Reforms to Generator Interconnection Process

On July 7, 2015, the Federal Energy Regulatory Commission (FERC) issued a notice seeking comments on a petition for rulemaking filed by the American Wind Energy Association (AWEA). The petition asks FERC to implement reforms...more

Summary of FERC Meeting Agenda - June 2015

In This Issue: - Administrative Items - Electric Items - Hydro Items - Certificate Items - Excerpt from Certificate Items: C-1: Natural Gas Pipeline Company of America, LLC (Docket No....more

FERC Issues Proposal to Ease Regulation of Gen-Tie Lines

FERC has issued a Notice of Proposed Rulemaking (NOPR) that would substantially reduce the regulatory burdens placed on energy project developers that construct generator lead lines (gen-tie lines) to interconnect their...more

FERC Rule Gives Gen-Tie Owners Safe Harbor From Third-Party Transmission Requests

On March 19, 2015, the Federal Energy Regulatory Commission (FERC) issued Order No. 807, a rule that makes it easier for developers of non-utility transmission lines that connect power projects to the grid to avoid having to...more

5th Circuit Denies Louisiana Public Service Commission’s Petition for Review of FERC’s Entergy Bandwidth Implementation Orders

On November 14, 2014, the U.S. Court of Appeals for the 5th Circuit denied the Louisiana Public Service Commission’s (LPSC) petition for review of various Federal Energy Regulatory Commission (FERC) orders on the...more

Interconnectivity And Information Sharing: Cause As Well As Cure for Cyber Attacks?

The modern day interconnected business creates a number of opportunities, but also brings with it massive issues relating to breach of privacy and data security in the form of cyber attacks, which cost companies and taxpayers...more

FERC Accepts CAISO’s Proposed Generator Interconnection Process Enhancements To Facilitate Project Downsizing

On July 31, 2014, the Federal Energy Regulatory Commission (FERC) accepted amendments to the California Independent System Operator Corporation (CAISO) tariff designed to improve the efficiency and flexibility of the CAISO’s...more

The Fourth Circuit Affirms District Court Decision Finding Maryland’s Contract for Differences Unconstitutional

As we reported (see link below), in October 2013, the United States District Court for the District of Maryland declared unconstitutional an order of the Maryland Public Service Commission (PSC) directing the state’s...more

FERC Amends Open-Access Requirements for Interconnection Facilities

New proposals aim to reduce regulatory burden on generation developers. On May 15, the Federal Energy Regulatory Commission (FERC or the Commission) issued a Notice of Proposed Rulemaking (NOPR) that proposes to...more

FERC Announces Plan To Change Open Access And Priority Rights Governing Generator Lead Lines - Interconnection Only Transmission...

On May 15, the Federal Energy Regulatory Commission proposed to modify its policy concerning open access and priority rights to capacity for interconnection only transmission facilities. This proposal, if implemented, will...more

Summary of the Implementing Regulations for Japan’s Feed-In Tariff Law for Renewable Electric Energy

This updates our September 13, 2011 Client Alert entitled “Outline of Japan’s Feed-In Tariff Law for Renewable Electric Energy,” which summarized “The Act on Special Measures Concerning the Procurement of Renewable Electric...more

Emerging Policy on NERC Compliance for Generator Interconnections

The ongoing struggle to determine how and when generator interconnection facilities should be subject to the North American Electric Reliability Corporation’s (NERC) rules governing transmission owners and transmission...more

FERC Proposes Reforms to Facilitate Small Generator Interconnections

On January 17, 2013, the Federal Energy Regulatory Commission (FERC) issued a notice of proposed rulemaking (NOPR) proposing reforms to the pro forma Small Generator Interconnection Procedures (SGIP) and the Small Generator...more

25 Results
|
View per page
Page: of 1
JD Supra Readers' Choice 2016 Awards

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:

Sign up to create your digest using LinkedIn*

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.

Already signed up? Log in here

*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.
×