Court of Appeal Issues Decision Clarifying the Applicability of Prevailing Wage Law to Offsite Fabrication of Materials

Best Best & Krieger LLP
Contact

Decision Impacts Public Works Projects in California

The California Court of Appeal has ruled that fabrication of materials for a public works project is not subject to California’s prevailing wage law if it occurs at a “permanent, offsite manufacturing facility, the location and existence of which is determined wholly without regard to the particular public works project.” In Sheet Metal Workers’ International Assn., Local 104 v. Duncan, published Aug. 27, Russ Will Mechanical, Inc. was the heating, ventilation, and air conditioning subcontractor contracted to perform the HVAC component for a community college district project.

As part of the public works project, Russ Will fabricated sheet metal for various HVAC components at a permanent offsite facility it had operated for more than a decade. An employee of Russ Will filed a complaint with the Department of Industrial Relations claiming he should have received prevailing wages for his work fabricating sheet metal at the offsite facility. Following the DIR’s administrative review of the matter, DIR’s final coverage determination concluded that Russ Will was not required to pay prevailing wages. Local 104, which had participated in the DIR proceedings, then filed a petition for a writ of mandate in court challenging the final DIR coverage determination. Local 104’s petition was granted, and the court returned the matter to the DIR. Russ Will then appealed.

The Court of Appeal’s decision clarifies and solidifies the rule consistently set forth in past DIR coverage determinations that prevailing wage requirements do not apply when the offsite fabrication takes place at a permanent, offsite manufacturing facility, where the location and existence of the facility has no relationship to the public works project in question. While this decision could be appealed to the California Supreme Court, for now, the Sheet Metal Workers’ International decision provides certainty that the payment of prevailing wages is not required in relation to a public agency’s direct purchase of materials for a public works project from a permanent offsite manufacturing facility, so long as the facility’s existence is not reliant on, or otherwise related to, the public works project.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Best Best & Krieger LLP | Attorney Advertising

Written by:

Best Best & Krieger LLP
Contact
more
less

Best Best & Krieger LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide