D.C. Circuit Rejects Challenges to FERC’s Order No. 1000

by Morgan Lewis
Contact

The court turned back all challenges to FERC’s order, which imposed major regional transmission planning requirements, concluding that FERC has adequately justified the order and acted within its statutory authority.

On August 15, the U.S. Court of Appeals for the District of Columbia Circuit rejected the challenges filed by various utilities, industry groups, and state commissions that claimed that the Federal Energy Regulatory Commission (FERC or the Commission) overstepped its authority when promulgating Order No. 1000.[1] The court’s decision in South Carolina Public Service Authority v. FERC,[2] which FERC Chairman Cheryl LaFleur hailed as “critical to the Commission’s efforts to support efficient, competitive, and cost-effective transmission,”[3] substantially strengthens FERC’s ability to establish the structures necessary to encourage and facilitate competitive transmission planning and development.

FERC Had the Authority to Promulgate the Rule

Certain petitioners had challenged FERC’s authority to regulate transmission planning under section 206 of the Federal Power Act. These petitioners claimed that FERC’s authority is limited to regulating voluntary planning arrangements and does not extend to requiring the new regional planning arrangements mandated by Order No. 1000.

The court rejected this argument, finding that the transmission planning practices regulated by Order No. 1000 are practices that affect rates. The court noted that what constitutes a “practice” is broad and that failing to engage in regional planning is itself a practice. The court viewed Order No. 1000 as “simply the next step” in the transmission planning reforms that began in Order No. 890, and which themselves grew out of Order No. 888.

The court also rejected claims that section 202(a) of the Federal Power Act prevents FERC from mandating transmission planning. Section 202(a) authorizes the Commission to divide the United States into districts and to promote the “voluntary interconnection and coordination of facilities” in those districts. According to the court, the Commission’s interpretation that applied section 202(a) only to coordinated operations, as distinguished from pre-operational planning, was permissible.

Finally, the court rejected claims that Order No. 1000 impermissibly intrudes on states’ authority to regulate the siting and construction of transmission, particularly because section 201(a) limits the Commission’s authority to “only those matters which are not subject to regulation by the States.” The court found that FERC “possesses greater authority over electricity transmission than it does over sales,” and that, although FERC’s authority over sales is limited to wholesale sales, there is no textual limit in the statute that indicates that FERC lacks jurisdiction over retail transmission. With this background, the court concluded that Order No. 1000 did not intrude on states’ authority because Order No. 1000 relates only to electric transmission and therefore falls within FERC’s broad authority in that area, particularly because Order No. 1000 is aimed at the interconnected grid that spans state lines. The court used this to distinguish its decision from its recent decision in Electric Power Supply Ass’n v. FERC,[4] which had rejected an attempt by FERC to regulate retail electricity sales.

FERC Provided Substantial Evidence to Support Its Conclusions

Petitioners had also challenged FERC’s conclusion that structural shortcomings in current planning efforts and cost allocation practices justified the remedies imposed in Order No. 1000. According to those petitioners, FERC’s claim of a theoretical threat is an insufficient evidentiary basis for the rule.

The court rejected this argument, explaining that FERC need not provide empirical evidence of the problem it seeks to solve. The court noted that the problem was well supported by comments and other evidence in the record, including industry studies that demonstrate the need for transmission investment. The court also rejected challenges to the Commission’s degree of certainty regarding its proposed improvements to regional planning, noting that, when predicting the future effect of a rule, FERC can rely on generally accepted principles, such as the benefits of competition.

FERC Has the Authority to Require the Removal of Rights of First Refusal

One of the reforms introduced by Order No. 1000 was the requirement that any rights of first refusal be removed from all FERC-jurisdictional tariffs and agreements. These rights grant the incumbent utility the right to construct any new transmission facilities in its footprint, even if a project is proposed by a competitor.

The court held that it was within the Commission’s authority over practices that affect rates to require the removal of rights of first refusal because “a generally accepted principle of economics directly connects rights of first refusal to rates.” The court noted that potential competitors are not likely to propose projects because they would not likely be able to build the projects they propose. This reduces competition and, therefore, likely increases rates.

The court also rejected claims that removing rights of first refusal would undermine the benefits of vertical integration, including by replacing project development by experienced and knowledgeable utilities with projects by new and untested developers. Although there are reliability risks presented by bringing in nonincumbent developers, the court concluded that FERC reasonably addressed those concerns through mechanisms such as the use of minimum developer qualifications, processes for monitoring project development, the right of incumbents to develop upgrades and local facilities, and the obligation to comply with reliability standards.

The court went on to reject the other reliability concerns that the petitioners presented, including concerns under section 215 of the Federal Power Act. According to the court, Order No. 1000 did not violate section 215’s requirements for reliability standard development when the Commission imposed a new North American Electric Reliability Corporation (NERC) mitigation plan process because in doing so no reliability standards were modified. The court also found that Order No. 1000 did not violate the prohibition on FERC ordering the construction of new transmission capacity because utilities mitigating violations could use methods other than construction of new facilities. Finally, the court concluded that utilities would be completely protected from reliability sanctions caused by nonincumbent developer failures because, even if NERC imposed such a sanction, FERC has committed not to penalize utilities in those circumstances and could free incumbent transmission providers from any such penalties. 

The court refused to address claims that FERC violated the Mobile-Sierra doctrine by directing modifications to FERC tariffs and agreements to remove the right of first refusal. The court explained that the Commission had promised to address individual contracts on compliance and noted that it would review those decisions as they arose.

FERC May Require the Ex Ante Allocation of Facility Costs Among Beneficiaries

In Order No. 1000, the Commission concluded that it is necessary to require a method for ex ante allocation of the costs of new transmission facilities to ensure that those who benefit from the facilities pay for them. Certain petitioners challenged that decision, claiming that FERC lacked the authority to require such allocation. Others claimed FERC did not go far enough.

The court rejected those challenges, explaining that mandating the allocation of costs using a beneficiary-pays protocol is within the scope of FERC’s authority over practices that affect rates. The court also concluded that a beneficiary-based cost allocation methodology would appropriately address the potential for free riders. Finally, the court concluded that limiting mandatory cost allocation to within regions was an appropriate balance between using a beneficiary-pays methodology and imposing a workable scope to identify beneficiaries.

FERC Reasonably Concluded That Regional Planning Should Consider Public Policy Requirements

The court rejected each challenge to the Commission’s requirement that regional planning account for federal, state, and local laws and regulations, such as renewable portfolio requirements. The court explained that FERC was not attempting to generically promote the public welfare, as some petitioners contended, but rather was recognizing that transmission planning needs to account for a variety of factors, including laws and governmental policies. The court also concluded that planning for these public policy requirements is consistent with FERC’s obligations to load-serving entities. Finally, the court rejected claims that the public policy requirements were too vague to be workable, explaining that the requirement is for regions to develop processes and that affording the regions broad discretion to develop their own processes does not make the obligation unworkably vague.

FERC Reasonably Relied on Reciprocity to Encourage Nonpublic Utility Participation

The court concluded by rejecting claims that the Commission should not have used its reciprocity policy to encourage nonpublic utilities to participate in Order No. 1000 regional planning. Under reciprocity, a nonpublic utility’s ability to take transmission service from public utilities is tied to the nonpublic utility’s willingness to accommodate FERC’s transmission policies, including the regional planning requirements in Order No. 1000.

The court explained that FERC used reciprocity in Order No. 1000 in the same way it used reciprocity in prior orders and that it explained why it was changing the scope of the reciprocity condition to accommodate regional planning. Nonpublic utilities need not take any action unless they choose to do so.

Finally, the court rejected claims that FERC should have used its authority under section 211A of the Federal Power Act to mandate participation in Order No. 1000 regional planning by nonpublic utilities. The court held that the use of section 211A is discretionary and that FERC adequately explained why it chose to rely on voluntary participation. The court did not find the evidence in the record sufficient to contravene FERC’s judgment that nonpublic utilities are likely to participate. The court noted that the petitioners raised concerns about possible free-riding by nonpublic utilities, but it deferred to FERC’s decision to leave the use of section 211A in that context for another day.

Other Legal Issues Related to Order No. 1000 Remain Unresolved

Although the D.C. Circuit’s decision upheld Order No. 1000 against all of the broad challenges brought against it, several key issues created by Order No. 1000 may result in future legal challenges on narrower topics that are more fact-specific. These include the following:

  • Whether the Mobile-Sierra language in certain regional transmission organization tariffs will protect the existing rights of first refusal in those tariffs
  • How NERC will implement the mitigation plan structure for reliability standard violations that result from nonincumbent project failures
  • How disputes over project and project developer selections will be resolved by FERC
  • Whether there will be disputes over the cost allocations that result from regional planning processes, and, if so, how FERC will resolve them
  • How FERC will provide for the billing of costs from transmission project developers to entities with which the developer has no contractual or tariff relationship

[1]. View the order here

[2]. No. 12-1232 (D.C. Cir. Aug. 15, 2014), available here

[3]. Statement of Chairman Cheryl A. LaFleur, FERC (Aug. 15, 2014), available here

[4]. 753 F.3d 216 (D.C. Cir. 2014).

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Morgan Lewis | Attorney Advertising

Written by:

Morgan Lewis
Contact
more
less

Morgan Lewis on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.