The reforms are aimed to address natural gas and electric scheduling concerns resulting from the increase in gas-fired generation, to provide greater flexibility to industry participants, and to better ensure reliable and efficient operation of the electric and interstate gas pipeline systems.

On April 16, the Federal Energy Regulatory Commission (the Commission) issued Order No. 809, revising its regulations relating to scheduling transportation service on interstate natural gas pipelines.[1] Order No. 809 is the latest of the Commission’s efforts over the last three years to address certain coordination issues with the scheduling practices of the wholesale natural gas and electric industries that arise from electric generators’ increased reliance on natural gas.

The Final Rule adopts portions of the Commission’s March 20, 2014 Notice of Proposed Rulemaking (NOPR) in which the Commission proposed the following three changes to the nationwide natural gas scheduling practices: (1) moving the start of the natural gas operating day from 9:00 a.m. to 4:00 a.m. central time to better align with the electric operating day, (2) moving the start of the first gas nomination cycle for day-ahead pipeline scheduling from 11:30 a.m. to 1:00 p.m. central time (Timely Nomination Cycle), and (3) modifying the intraday nomination timeline to provide additional intraday nomination cycles. Following the NOPR’s issuance, the Commission provided the electric and natural gas industries with six months to reach consensus on the NOPR proposals through the North American Energy Standards Board (NAESB).

In the Final Rule, the Commission declined to adopt the modified start time to the gas operating day. Otherwise, the Final Rule largely reflects acceptance of the NOPR’s key scheduling proposals. The Commission noted that it is revising its regulations to incorporate by reference the modified NAESB’s Wholesale Gas Quadrant business practice standards, which set forth scheduling revisions (discussed in more detail below). Interstate natural gas pipelines must comply with the revised NAESB standards that the Final Rule incorporates beginning on April 1, 2016. Pipelines must also file tariff records in accordance with the Final Rule’s compliance filing requirements to reflect the changed standards by February 1, 2016. The Final Rule’s effective date is 75 days after its publication in the Federal Register.

Revisions to Day-Ahead and Intraday Natural Gas Nomination Cycles

The Final Rule adopts two proposals to revise the practices that interstate pipelines use to schedule natural gas transportation service. Currently, shippers have two nomination opportunities prior to the day of gas flow: the Timely Nomination Cycle and the Evening Nomination Cycle. In addition, shippers have two more opportunities to schedule nominations on the day of gas flow: Intraday 1 Nomination Cycle and Intraday 2 Nomination Cycle.

With regard to day-ahead nominations, Order No. 809 moves the deadline for submitting nominations in the Timely Nomination Cycle from 11:30 a.m. to 1:00 p.m. central time to provide sufficient time for electric utilities to understand their commitments in the day-ahead electric market before arranging for natural gas supply and pipeline transportation. Originally presented in the NOPR, the proposal to move the start of the Timely Nomination Cycle to 1:00 p.m. was incorporated by NAESB into its revised standards. Additionally, NAESB moved the deadline for pipelines to notify shippers of their scheduled quantities from 4:30 p.m. to 5:00 p.m central time. The Commission adopted both proposals in the revised NAESB standards and amended its regulations under 18 C.F.R. § 284 to reflect those changes.

The Commission also adopted NAESB’s revised standards with respect to intraday scheduling. Although the NOPR proposed four intraday nomination opportunities, the revised NAESB standards provide for only three such opportunities. In accepting the NAESB proposal, the Commission noted that the revised standards garnered broad support in both the electric and natural gas industries because the proposed three intraday nomination cycles will allow sufficient time for processing gas nominations, avoid overlapping nomination cycles, and allow for most scheduling work to be completed during regular business hours. The Commission also agreed that although the NAESB proposal deviates slightly from the NOPR, it still meets the NOPR’s goals because the additional nomination opportunity provides gas-fired generators and other pipeline shippers with additional flexibility. Although the Commission concluded that, on balance, adopting the NAESB proposal represents a step forward for ensuring scheduling flexibility, it urged the gas and electric industries to explore the potential for more efficient, computerized scheduling to provide even greater scheduling flexibility.

No Change to the Gas Day

In the NOPR, the Commission expressed concern about the potential effect of the natural gas and electric operating days’ differing start times for the operation of the electric transmission system and interstate natural gas pipelines. To address this issue, the NOPR proposed moving the start of the natural gas operating day from 9:00 a.m. to 4:00 a.m. central time to ensure that gas-fired generators are able to retain sufficient natural gas capacity during the morning electric ramp-up period. Ultimately, the Commission declined to adopt the NOPR’s proposal. After considering comments and concerns from industry participants, the Commission concluded that gas-fired generator derates due to fuel limitations appear to be a more isolated regional issue during winter months that do not warrant changing the start time of the nationwide natural gas operating day. The Commission also found compelling the arguments from some commenters who identified substantial costs and potential safety issues that would accompany the proposed 4:00 a.m. start time. In declining to adopt this proposal, the Commission noted ongoing regional efforts and tariff reforms that ISO New England and PJM Interconnection have undertaken to address generator performance and availability that may alleviate some of the electric industry’s fuel supply concerns underlying the gas day change proposal.

Changes to ISO and RTO Day-Ahead Scheduling Practices

Along with issuing the NOPR on March 20, 2014, the Commission instituted a proceeding under section 206 of the Federal Power Act (FPA) to ensure that Independent System Operators (ISOs) and Regional Transmission Organizations (RTOs) adjust their day-ahead scheduling practices to correlate with the revisions that were ultimately adopted by the Final Rule.[2] Specifically, the section 206 order requires each ISO and RTO to adjust the time that the results of its day-ahead energy market and reliability unit commitment process are posted to a time in advance of the Timely and Evening Nomination Cycles, respectively. This allows gas-fired generators to procure natural gas supply and pipeline transportation capacity. ISOs and RTOs must propose tariff revisions that reflect these changes within 90 days after the Final Rule is published in the Federal Register or otherwise show cause why existing scheduling practices need not be changed.

Multi-Party Transportation Contracts

The Final Rule also amends the Commission’s regulations to require interstate natural gas pipelines that offer firm transportation service under subpart B or G of Part 284 to allow multiple shippers associated with a designated agent or asset manager to be jointly and severally liable under a single firm transportation service agreement. The Commission explained that although multi-party firm transportation contracts will provide shippers with greater flexibility, the Commission would only require pipelines to offer such an option if a shipper requested it. If a shipper makes such a request, a pipeline must file tariff changes that facilitate the change within 60 days of the request.

Conclusion

Order No. 809 represents the Commission’s latest action to address certain natural gas and electric industry coordination challenges that result from the divergent utility scheduling practices. The Commission anticipates that the changes in the Final Rule will improve coordination among the industries while still allowing for ongoing regional efforts to address coordination needs that arise from the electric industry’s increased reliance on natural gas.


[1]. Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines and Public Utilities, Order No. 809, 151 FERC ¶ 61,049 (2015), available here (Order No. 809 or the Final Rule).

[2]. California Independent System Operator Corp., et al, order initiating investigation into ISO/RTO scheduling practices and establishing paper hearing procedures, 146 FERC ¶ 61,202 (2014).

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Morgan Lewis | Attorney Advertising

Written by:

Morgan Lewis
Contact
more
less

Morgan Lewis on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.