Infrastructure Series: Agencies Establish One Federal Decision Framework for Project Reviews

by WilmerHale
Contact

This is the seventh issue of WilmerHale's 10-in-10 Infrastructure Series. In this series, our attorneys share insights on current and emerging issues affecting infrastructure project developers in the United States. Attorneys from various practice groups at the firm offer their take on issues ranging from permitting reform to financing to litigation, and share their insights from working with clients in a variety of infrastructure sectors, from water infrastructure to energy development to infrastructure development on tribal lands. Read all issues in this series and our other recent publications.

This week, a dozen federal agencies signed a Memorandum of Understanding (MOU) committing to “a more predictable, transparent, and timely Federal review and authorization process for delivering major infrastructure projects.”1 Under the MOU, federal agencies with responsibilities to review or authorize infrastructure projects commit to a number of policies intended to create a more coordinated and streamlined federal review process. This includes:

  • One Federal Decision. Developing a single Environmental Impact Statement (EIS) and Record of Decision (ROD) to document all required agency reviews for proposed infrastructure projects.
  • Target Deadlines. Issuing all project approvals within 90 days of the issuance of the ROD, with the goal of completing the permitting process within two years of publication of the Notice of Intent (NOI).
  • Permitting Timetable. Establishing—and complying with—a coordinated permitting timetable with target deadlines for intermediate and final milestones that facilitate meeting the two-year target deadline for permit approvals.
  • Concurrent Reviews. Completing all required federal reviews concurrently rather than sequentially.
  • Dispute Resolution. Elevating interagency disputes for quick resolution.

The MOU implements the targets and policy directives in Executive Order 13807 and builds on Congress's similar efforts to streamline federal environmental reviews through Title 41 of the Fixing America's Surface Transportation Act (FAST-41).

Which projects are covered under the MOU?

The MOU applies to all “major infrastructure projects,” as that term is defined in Executive Order 13807. This covers projects in a broad range of sectors—from energy generation to electricity transmission lines and pipelines to water resources projects. A project in any of these sectors would qualify as a major infrastructure project if it requires multiple federal authorizations and the preparation of an EIS.2 In addition, the project sponsor must show “reasonable availability” of funds to complete the project.3

Which types of reviews are included?

The MOU applies to all federal environmental reviews or authorizations required for the project, including review and consultation obligations under the National Environmental Policy Act (NEPA), National Historic Preservation Act and Endangered Species Act (ESA). In the MOU, agencies commit to review their internal regulations, including NEPA regulations, and make any necessary modifications to facilitate the implementation of a one federal decision framework. This could result in broader reforms to underlying environmental regulations. For example, the Department of the Interior (DOI) has indicated that as part of its implementation of the MOU, it would look to reform the ESA and “create regulations to better reflect the intent of the original legislation.”4

How does this relate to previous streamlining efforts?

The MOU builds upon previous efforts to better coordinate federal reviews and streamline the complex federal process. The MOU reaffirms many of the statutory requirements in FAST-41, including the requirement to designate a federal lead and develop a coordinated project schedule for each infrastructure project, the responsibilities of cooperating agencies, and the requirement to complete reviews concurrently where possible. The MOU builds upon these requirements with a number of significant new commitments, including:

  • A commitment to comply with the permitting timetable set by the lead agency;
  • A commitment to prepare one federal EIS and ROD in order to facilitate better coordination;
  • A commitment that agencies will come together to provide feedback at specific concurrence points to facilitate coordinated reviews and a single decision record;
  • For FERC-led projects, a commitment that each agency whose authorization is required will participate as a cooperating agency at FERC's invitation, to minimize duplicative reviews and the potential for delays.

What impact will this MOU have on project reviews?

The MOU includes a number of important principles that would improve permitting efficiency and coordination. The ultimate impact of the MOU on pending or newly proposed projects will depend to a large extent on its implementation. A number of important issues will have to be addressed as the first projects start going through this process, including:

  • Refining the Two-Year Target. Under the MOU, the two-year target permitting timeline begins with the publication of the NOI. The MOU further provides that the lead federal agency will publish the NOI only after it consults with cooperating agencies and determines that the project proposal is sufficiently developed. However, there are currently no clear or consistent standards regarding when data is sufficient to complete agency review. As agencies implement the MOU, it will be important to establish a process for coordinating agency decisions regarding the adequacy of the data presented, as well as the ability to quickly elevate and resolve disputes related to the adequacy of data or need for additional data.
  • Voluntary Nature of the Agreement. At the end of the day, the commitments in this MOU are not mandated by statute. In fact, in some cases, it would take careful analysis to reconcile the target dates and the single decision framework with existing statutes and regulations. For example, the Forest Service pre-decisional objection process requires the publication of a draft ROD to provide the public an opportunity to review it and file formal objections with the agency before the ROD is finalized. Lead agencies would have to carefully design the approach to a given project to address agency-specific processes such as this while preserving the one federal decision framework. In addition, because there's no statutory mandate to adhere to the permitting timetable, there will be a need for continued leadership engagement and effective communication and training of agency permitting staff.
  • Ensuring NEPA Adequacy. Because there have been no changes to the underlying statutory requirements, each agency will have to determine that the final EIS and ROD meet its respective statutory obligations, including the “hard look” standard under NEPA. This can be especially tricky where agencies like the Army Corps of Engineers have a different standard of analysis (i.e., the “least environmentally damaging practicable alternative”). The lead agency would have to carefully manage the process of coordinating input from all agencies to ensure that the final NEPA document and ROD meet each agency's respective statutory and regulatory requirements. The MOU itself recognizes this challenge and provides that the lead agency will be responsible for ensuring that “the final EIS (FEIS) includes an adequate level of detail to inform decisions by all agencies with review or authorization decision responsibilities for the proposed project.”
  • Addressing Limited Agency Resources. Successful implementation of the coordination process and ambitious timelines outlined in the MOU will require significant resources. This can be addressed in part by using available agency authorities to allow cost-sharing, retain third-party consultants or (in some cases) use applicant-prepared NEPA documentation. But much of the coordination and review responsibilities will remain with agency staff; therefore, it will be important to have dedicated agency staff.

What's next?

Over the coming months, agencies will work on developing appropriate internal policies and procedures to comply with the MOU. Each agency has committed to transmit an implementation plan to the Council on Environmental Quality and Office of Management and Budget within 90 days. Much of this work is already underway. For example, DOI has established a project permitting task force dedicated to streamlining its permitting process. The agency is also in the process of reviewing NEPA, ESA, and other environmental regulations and policies to identify necessary reforms. These implementation plans, along with the on-the-ground experience of the first projects that avail themselves of the new one federal decision approach will be illustrative of how the newly streamlined permitting process will work in practice going forward.


Memorandum of Understanding Implementing One Federal Decision Under Executive Order 13807 at A-1.
2 E.O. 13807 of August 15, 2017, “Establishing Discipline and Accountability in the Environmental Review and Permitting Process for Infrastructure Projects,” 82 Fed. Reg. 40,463, 40,464 (Aug. 24, 2017).
3 Id.
4 U.S. Department of the Interior Press Releases, “Secretary Zinke Committed to President Trump's Latest Infrastructure Initiative” (April 9, 2018).

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© WilmerHale | Attorney Advertising

Written by:

WilmerHale
Contact
more
less

WilmerHale on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.