[co-author: Giulio Catalani]
On February 20, 2026, the Italian Council of Ministers adopted Law Decree No. 21/2026 (LD 21/26), which entered into force on February 21, 2026, and must be converted into law by the Italian Parliament (with potential amendments) by April 21, 2026. Article 8 of LD 21/26 introduces a single authorization process for the development and expansion of data centers located in Italy, as well as related grid connection activities (the Single Authorization).
New Authorization Process
LD 21/26 introduces the following key rules:
Open Points and Next Steps
LD 21/26 represents an important first step toward streamlining and accelerating the administrative procedure applicable to developing data centers. In particular, the introduction of a maximum timeline of 10–13 months and the consolidation of different authorization procedures is expected to significantly shorten the environmental permitting phases, which, to date, have represented a bottleneck for such projects.
However, as currently drafted, the Single Authorization process does not expressly address the urban planning phase or the issuance of the required building permit. Further clarifications can still be provided either through Parliament’s conversion of LD 21/26 or through the adoption of future national guidelines addressing how these aspects are to be integrated into, or coordinated with, the Single Authorization process.