NAESB to Seek Industry Comments on Proposed Modified Standards Prepared in Response to FERC Gas-Electric Coordination NOPR

by Moore & Van Allen PLLC
Contact

The Notice of Proposed Rule Making re: Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines and Public Utilities (Docket No. RM14-2-000) (“NOPR”) issued by the Federal Energy Regulatory Commission (“FERC”) on March 20, 2014 has spawned an extraordinary effort by the North American Energy Standards Board (“NAESB”) and natural gas and electric industry participants to develop a consensus on standards for coordinating the scheduling processes of the natural gas and electricity markets. In a previous post, we discussed the ongoing efforts of the NAESB Gas-Electric Harmonization Forum (“GEH Forum”), which provided industry stakeholders, regulators, consumer advocacy groups, and others an avenue to work towards a consensus proposal to submit to the NAESB Board of Directors for consideration, and ultimately to FERC in response to the NOPR. Nearly 470 people reportedly participated in the four GEH Forum meetings held in Houston, TX and nearly 700 people monitored the effort through distribution lists. Throughout the course of the meetings, more than 13,000 individual votes were cast on 56 ballots. After presentations of several alternative proposals, the GEH Forum narrowed the proposals down to four for consideration in a vote in early June. None of the four proposals garnered the requisite level of support from the GEH Forum participants to constitute a consensus. However, the NAESB Board of Directors noted that “there appeared to be broad support from interested parties in both the gas and electric industries for changes to the intraday scheduling cycles and the day-ahead nomination cycles.” Accordingly, the NAESB Board voted to modify the Wholesale Gas Quadrant (“WGQ”) Annual Plan to assign standards development work to several WGQ Subcommittees in order to implement changes to these cycles consistent with the timelines presented in the final proposal considered by the GEH Forum.

On June 18, 2014, NAESB submitted a status report to FERC which detailed its efforts thus far and provides a timeline for continued efforts prior to the submission of NAESB’s response to FERC in September 2014. The NAESB report states that it is merely a status report and “NAESB does not advocate that the Commission take a particular position on any of the issues presented.” NAESB’s efforts to modify its standards have continued through the WGQ Subcommittees, with the most recent meeting on July 8. NAESB’s timeline calls for the posting of proposed modified standards for industry comment by July 18, 2014. We describe in more detail below the outcomes of the GEH Forum and NAESB Board votes on alternative proposals, and highlight the WGQ Subcommittee’s work and timeline for presenting a response to the FERC NOPR. 

Outcome from GEH Forum June 2-3, 2014 Meeting & Vote on Alternatives to FERC NOPR Proposal:

The final binding votes on the four alternative proposals were taken on June 2-3, with one alternative being eliminated through each successive vote. A table in Appendix A of the GEH Forum Comparison of FERC Proposal to Existing NAESB Standards outlines the four alternatives considered by the GEH Forum, as well as an alternative that does not include the specification of a gas day start time and a comparison of the proposal outlined in the NOPR and current existing NAESB standards.

The NAESB Board of Directors had determined in April 2014 that to reach a consensus of the GEH Forum there must be a super majority affirmative balanced vote of 67% of each of the WEQ and WGQ participants and at least 40% affirmative balanced vote of each of the segments. The GEH Forum did not achieve a consensus vote on any of the four proposals. The proposal with a 9 am CCT gas start day received the most votes on a balanced basis. However, the 9 am CCT gas start day still failed to meet the required super majority and balanced votes, and it failed to garner a simple majority balanced vote of one of the quadrants. The ISO Group, which includes ISO-NE, NYISO, PJM, MISO, SPP and ERCOT, had supported the 4 a.m. CCT start to the gas operating day and submitted IRC Comments on 4AM Gas Day. A table reflecting each vote can be found in Appendix B of the GEH Forum Comparison of FERC Proposal to Existing NAESB Standards.

Outcome of NAESB Board of Directors Meeting on June 4, 2014:

Despite the lack of consensus from the GEH Forum, the NAESB Board reported that the analysis and work that the GEH Forum completed was helpful. The Board of Directors met June 4, 2014 and voted on the following motion:

Although consensus was not reached on a complete alternative to the proposed changes in the NOPR there appeared to be broad support from interested parties in both the gas and electric industries for changes to the intraday scheduling cycles and the day-ahead nomination cycles. Accordingly, the Board directs the WGQ Executive Committee (EC) to:

Add an item to the WGQ annual plan instructing the WGQ EC to write standards to reflect the timely and evening next day nomination cycles, and the 3 intraday nomination cycles as described in the last motions of the NAESB GEH Forum, remaining silent on the start of the Gas Day with the assumption the Commission will establish the gas day start best suited to achieve the objectives defined in the NOPR. Once an order is issued by the Commission in the NOPR proceeding, the WGQ EC will make the appropriate changes to the standards to reflect changes as ordered by the Commission.

This motion is for the purpose of initiating work on the revisions to the standards and does not limit or restrict in any way those voting in favor of the motion from taking whatever position they deem appropriate to their interests in the NOPR.

Based on a simple majority vote by each quadrant of the Board, it modified the WGQ Annual Plan to assign the following standards development work to the WGQ Business Practices Subcommittee (BPS) and to the WGQ Information Requirements and WGQ Technical Subcommittees in support of the timeline defined by the GEH Forum:

Develop new standards and modify existing standards to support the timelines for timely, evening, ID1, ID2 and ID3 nomination cycles as specified in Attachment A of this plan and make corresponding changes where necessary to other standards such as those that support capacity release programs. The standards should be neutral on gas day start times; meaning that all references to the 9 am CCT start of the gas day should be removed.

WGQ BPS Efforts & Timeline for Industry Comment

The WGQ subcommittees have initiated work on standards development with the goal of voting on a recommendation containing the modified or new standards by July 18, 2014. The BPS has worked to identify standards that require modification and has held several meetings to discuss potential modifications since June 5, 2014, with the most recent being on July 8, 2014. You can access minutes and information from several of the BPS meetings, which outline the standards discussed: June 5, Draft Minutes (redlined),June 12, Final Minutes, June 26, Final Minutes, July 8, Draft Minutes. A possible vote was on the WGQ BPS July 10, Meeting Agenda, but the meeting has since been cancelled.

The NAESB timeline outlines the following schedule for additional work on the standards development:

  • By July 18 – Subcommittee will vote on a recommendation containing the modified or new standards and post standards for a thirty-day industry wide comment period.
  • August 18 – Industry comment period ends.
  • August 22 – WGQ Executive Committee will consider the recommendation and comments submitted, and will vote on recommendation. If approved, the recommendation will be distributed for ratification by NAESB membership.
  • September 22 – Ratification Ballot Period ends. If ratified, the standards become NAESB final action.
  • September 29 – NAESB standards filed with FERC.

Upon issuance of a final rule by FERC, NAESB plans to respond by integrating FERC regulations into its standards within 90 days of the effective date of the final rule and will notify FERC when the standards have been approved.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Moore & Van Allen PLLC | Attorney Advertising

Written by:

Moore & Van Allen PLLC
Contact
more
less

Moore & Van Allen PLLC on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.