Nevada enacted a Renewable Energy Tax Abatement program in 2009, which it operates under the Governor’s Office of Energy (“GOE”). For eligible renewable energy facilities, the program awards partial abatements for sales and use tax, and property tax. Application must be made to the Energy Office, whose staff reviews the abatement applications, conducts public hearings to determine eligibility, enters into abatement agreements, and then, reviews annual compliance audits.

Property and Sales Tax Abatement

The application for the property tax abatement may be made for real and personal property used to generate electricity from renewable energy resources, including solar, wind, biomass,1 fuel cells, geothermal or hydro. Generation facilities must have a capacity of at least 10 megawatts (MW), and plan to operate for at least 10 years. Facilities that use solar energy must generate at least 25,840,000 British thermal units of process heat per hour to qualify for the abatement.

Depending on the population of the county or city where the project is sought to be located, there are job creation, job quality requirements and minimum capital investments ($10 million or $3 million). In addition:

  • The average hourly wage for employees at the facility, excluding management and administrative employees, must be at least 110 percent of the average statewide hourly wage;
  • The average hourly wage for construction employees, excluding management and administrative employees, must be at least 175 percent of the average statewide hourly wage; and
  • The employees working on the construction of the facility must be provided a health insurance plan from a third-party administrator that includes coverage for dependents.

The GOE Director may approve partial abatements for property and sales taxes. The Property tax abatement can be for a duration of 20 fiscal years and equal to 55 percent of the taxes on real and personal property; but the abatement is not applicable for any period the facility receives another abatement or exemption from property taxes. As to the sales tax abatement, its duration is only 3 years and equal to that portion of the combined rate of all local sales and use taxes payable by the facility that exceeds 0.6 percent; but, such abatement is not applicable during any period the facility receives another abatement or exemption from local sales and use taxes.

Approval is encapsulated in an “Abatement Agreement”. The partial abatement of taxes approved by the GOE director is prospective only. It cannot be applied retroactively to any tax imposed before the execution of the Abatement Agreement.

Application Process

The Application must be filed electronically, attaching a PDF and Excel workbook of the confidential application, and a PDF of the redacted application with the GOE. The application fee must be sent either via wire or mail before an application can be considered filed.

As abatement applications are contested cases under Nevada’s Administrative Procedures Act, NRS Chapter 233B, the GOE must hold a public hearing on the abatement application. The Act prohibits members or employees assigned to render a decision or to make findings of fact and conclusions of law from communicating, directly or indirectly, with any person or party, or the party’s representative, except upon notice and opportunity to all parties to participate.

Upon receipt of an application:

  1. The Director reviews the application for timeliness and completeness. Timely filed application means that the Director received a completed application on or before the facility’s commercial operation date. If an application is not timely and filed in bad faith, or the timing frustrates the statutory purpose, the Director may reject the application. If an application is rejected, written notice is provided to the applicant.
  2. If the application is incomplete, written notice is provided to the applicant identifying the information necessary to complete the application. An applicant has 10 business days to provide the missing information; otherwise, Director rejects the application with written notice to the applicant.
  3. The Director will provide a copy to the governing body of each city or town in which the facility is proposed to be located.
  4. Not later than 15 business days after any substantive change to the information provided in an application, the applicant must submit an amended application.

Unless otherwise indicated by the applicant, all information submitted to the Director is a public record. Thus, if confidentiality is sought for an application, the applicant must: (1) submit with the original application a redacted copy of the application which clearly identifies each item that is claimed to be confidential and (2) provide legal authority citation for why each particular item is claimed as confidential.

For each identified item, the Director determines if the item is confidential and provides written notice of that determination. Within 3 business days, the applicant must, in writing, concur or object to each item, including the legal basis for an objection. If the Director again rejects the request that the item not be made public, the applicant must either withdraw the application or seek a court order protecting the item from publication. For items determined to be confidential (ether by Director or court), the Director prepares a redacted copy of the application and provides it statutorily defined governmental entities. Thereafter, the Director sets a date for a hearing, providing statutorily defined notice.

At the hearing, the applicant has the burden, by reasonable evidence, to demonstrate eligibility for the partial abatement of taxes. The Director will issue findings of facts, conclusions of law and a final decision within 10 business days of the hearing’s conclusion. The Director may condition the approval of an application upon terms determined necessary. If eligible for a partial abatement of taxes, the Director executes an abatement agreement with the applicant.

 


1 Biomass is defined as any organic matter that is available on a renewable basis, including, without limitation, agricultural crops and agricultural wastes and residues; wood and wood wastes and residues; animal wastes; municipal wastes; and aquatic plants. Owner cannot be receiving another abatement of property tax and/or sales as use tax at the time the abatement is granted

ANOTHER STATE ATTACKS COAL! VIRGINIA PROPOSES TO JOIN RGGI STATES

The Virginia State Air Pollution Control Board approved draft regulations intended to cut Greenhouse Gas Emissions, and that would make Virginia the tenth state to join the Regional Greenhouse Gas Initiative. Presently, those states include Connecticut, Delaware, Maine, Maryland, Massachusetts, New Hampshire, New York, Rhode Island and Vermont. The draft regulations set a cap on carbon emissions, and draw down that cap by thirty percent (30%) by 2030. The stated reason for the cap is that Virginia plants have had increased carbon emissions since 2011, and the State wants to both curb and redirect that trend. Like the other RGGI states, Virginia’s proposal uses a carbon cap and trade system to reduce carbon emissions, starting with a cap of 33 to 34 million in 2020, and declining by 3% per year until 2030. Virginia Republican Legislators have suggested the need for legislation to preclude the rule’s adoption, or that the rule itself lacks authority (meaning possible litigation should the rule be adopted). Clearly, there is more to come on this proposal.

NY AND FERC REDEFINING STATE AND FEDERAL RELATIONS?

Under the National Gas Act (“NGA”), the Federal Energy Regulatory Energy Commission (“FERC”) has jurisdiction over development of interstate natural gas pipelines, except that a state may grant or deny a water quality certification application; provided the State acts timely. Millennium seeks to build a 9-mile pipeline from its main pipeline to the CPV combined cycle natural gas fired electric plant in Orange County, NY (called the Valley Lateral Project). Millennium Pipeline Company sued the New York State Department of Environmental Conservation (DEC), arguing it dragged its feet in ultimately denying its application. At issue was a delay by the DEC to issue a Section 401 Water Quality Certification or denial for the pipeline project. By section 401 of the Clean Water Act, a State must grant or deny the certification application “within a reasonable period of time (which shall not exceed one year) after receipt of [a] request.” Id. Alcoa Power Generating Inc. v. FERC, 643 F.3d 963, 972 (D.C. Cir. 2011) (quoting 33 U.S.C. § 1341(a)(1)). If the State fails to act within that time period, the Act’s “certification requirements” are deemed “waived.” The U.S. Court of Appeals for the District of Columbia Circuit dismissed the lawsuit by Millennium, reasoning FERC had the power to override the DEC and issue the permits. Thereafter, finding the DEC had waived its authority under Section 401, the FERC ordered the pipeline construction by Millennium to go forward. The FERC found the DEC acted untimely. The FERC also denied New York’s request for rehearing and stay, assuring that a federal court would determine the issue. It appears that FERC is taking a more proactive approach to State review. If it prevails, FERC may issue a similar order for the Constitution pipeline, possibly finding the DEC again acted untimely and their waived its authority to review its application. The DEC claims the FERC has misinterpreted when the time period for its review commences, contending the one year period did not commence until it deemed the application to be “complete”. The pipeline companies have asserted that the DEC review of water certification applications has become politicized to preclude pipeline development in NYS that might involve the transport of hdyrofracked natural gas. The Millennium matter presently resides with the United States Court of Appeals for the Second Circuit, which recently denied New York’s motion to stay construction.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Dickinson Wright | Attorney Advertising

Written by:

Dickinson Wright
Contact
more
less

Dickinson Wright on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.