Northeast Supply Enhancement Project Receives Key Environmental Permits

Akin Gump Strauss Hauer & Feld LLP
Contact

Akin Gump Strauss Hauer & Feld LLP

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

NESE initially received a certificate of public convenience and necessity from FERC for the project in 2019 under the Natural Gas Act (NGA), but its project sponsor ultimately canceled the project without initiating construction due to an inability to secure CWA and flood hazard permits from New York and New Jersey that were required by FERC. In 2025, following the President’s declaration of an Energy Emergency in Executive Order No. 14156 (E.O. 14156), Transco applied to reinstate the 2019 certificate, relying on FERC’s prior environmental analysis. FERC granted the requested relief on August 28, 2025, and reauthorized the project under NGA section 7.

The states’ changed position on the permits after rejecting prior applications made by Transco in 2018, 2019 and 2020, may portend a broader energy and environmental policy shift for several converging reasons. These include a surging demand for energy in the Northeast, forecasted grid reliability concerns in New York and historically high electricity prices in New Jersey. New York’s governor, Kathy Hochul, stated that the NYSDEC’s decision is consistent with her administration’s “all of the above approach” to addressing grid reliability and affordability. State officials also may be concerned about future actions by the federal government to force infrastructure development in the Northeast region in line with statements made in E.O. 14156, and seek to take greater control to maintain a level of state autonomy for federally permitted projects. Additional Northeast pipeline projects are anticipated to materialize. However, project opponents may try to challenge state-issued permits required for FERC-approved natural gas infrastructure, akin to a recent challenge to a Louisiana-issued Coastal Use Permit received by a liquefied natural gas terminal developer with FERC NGA section 3 authorization.

The Akin team will continue to monitor these regulatory developments.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations. Attorney Advertising.

© Akin Gump Strauss Hauer & Feld LLP

Written by:

Akin Gump Strauss Hauer & Feld LLP
Contact
more
less

What do you want from legal thought leadership?

Please take our short survey – your perspective helps to shape how firms create relevant, useful content that addresses your needs:

Akin Gump Strauss Hauer & Feld LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide