Summary of FERC Meeting Agenda for July 19, 2018

by White & Case LLP
Contact

White & Case LLP

Below are brief summaries of the agenda items for the Federal Energy Regulatory Commission,s July 19, 2018 meeting, pursuant to the agenda as issued on July 12, 2018. Item H-1 has not been summarized due to omission from the agenda.

  • Electric Items 
  • Gas Items 
  • Hydro Items 
  • Certificate Items

Electric

E-1 – Cyber Security Incident Reporting Reliability Standards (Docket No. RM18-2-000). On December 21, 2017, the Commission issued a notice of proposed rulemaking (NOPR) proposing to direct the North American Electric Reliability Corporation (NERC) to create and provide revisions to the Critical Infrastructure Protection (CIP) Reliability Standards to improve mandatory reporting of Cyber Security Incidents, including incidents that may facilitate subsequent efforts to damage the reliable operation of the bulk electric system. Numerous entities submitted comments on the NOPR. Agenda item E-1 may be an order on the Commission's NOPR.

E-2 – Revisions to Parts 45 and 46 of the Commission' Regulations (Docket No. RM18-15-000). Agenda item E-2 may be an order establishing a proposed rulemaking regarding the Commission's regulations for applications for authority to hold interlocking positions and filing requirements for persons holding interlocking positions.

E-3 – North American Electric Reliability Corporation (Docket No. RR17-6-000). On June 26, 2017, NERC filed a petition for approval of proposed revisions to Sections 600 and 900 of the NERC Rules of Procedure (ROP). NERC states in its petition that the purpose of the proposed revisions is to (i) clarify the scope of the Personnel Certification Program, the Training and Education Program and the Continuing Education Program; and (ii) streamline and align the language of the ROP with current practices of those programs. Agenda item E-3 may be an order on NERC's petition.

E-4 – Linden VFT, LLC v. PJM Interconnection, L.L.C., PJM Interconnection, L.L.C., PJM Interconnection, L.L.C. Linden VFT, LLC v. PJM Interconnection, L.L.C., PJM Interconnection, L.L.C., Linden VFT, LLC v. Public Service Electric and Gas Company and PJM Interconnection, L.L.C., New York Power Authority v. PJM Interconnection, L.L.C. and PJM Transmission Owners in their Collective Capacity, PJM Interconnection, L.L.C. PJM Interconnection, L.L.C. (Docket Nos. EL15-67-003, ER15-2562-002, ER17-950- 003, EL17-68-000, EL17-84-001, EL17-90-001, EL17-94-000, ER18-579-002, ER18-680-000 (Not Consolidated)). The above proceedings concern cost responsibility assignments for transmission projects selected by PJM Interconnection L.L.C., (PJM) for inclusion in its Regional Transmission Expansion Plan (RTEP) in accordance with the PJM Open Access Transmission Tariff (PJM Tariff). Specifically, on July 10, 2015, under Docket No. EL15-67, Linden VFT, LLC (Linden) filed a complaint pursuant to section 206 of the FPA challenging PJM's solution-based distribution factor cost allocation methodology as applied to certain projects included in PJM's 2013 RTEP. In an order dated April 22, 2016, the Commission denied the complaint, finding that Linden failed to satisfy its burden under FPA section 206 to demonstrate that PJM's solution-based distribution factor cost allocation methodology was unjust, unreasonable, or unduly discriminatory or preferential. Numerous parties filed requests for rehearing of the Commission's April 22 order.

On April 28, 2017, under Docket No. EL17-68, Linden filed a complaint pursuant to Section 206 of the FPA with respect to PJM's revised cost allocations for RTEP projects b s b2436 and b2437 resulting from Consolidated Edison Company of New York (Con Edison) terminating 1,000 MW of long-term firm transmission service, effective April 30, 2017. The complaint asserts PJM's cost reallocations are unjust and unreasonable and unduly discriminatory and preferential. Numerous parties filed interventions, comments, and protests with respect to the complaint.

On September 18, 2017, under Docket No. EL17-90, Linden filed a complaint pursuant to Section 206 of the FPA. In this complaint, Linden contended that Public Service Electric and Gas Company (PSEG) is unreasonably withholding its consent to an amendment to the existing Linden interconnection service agreement between Linden, PSEG, and PJM to allow Linden to reduce all of its Firm Transmission Withdrawal Rights to Non-Firm Transmission Withdrawal Rights, or, in the alternative, the PJM Tariff is unjust and unreasonable to the extent it does not permit a merchant transmission facility owner to reduce all of its Firm Transmission Withdrawal Rights to Non-Firm Transmission Withdrawal Rights without amending its interconnection service agreement or the consent of transmission owner party to that agreement. On December 15, 2017, the Commission issued an order granting in part Linden's complaint, finding the interconnection service agreement with PSEG to be unjust and unreasonable insofar as it did not permit Linden to convert its transmission rights as discussed above. The Commission rejected arguments that by converting its transmission withdrawal rights Linden was avoiding cost allocation assignment under the PJM RTEP or that the complaint was a collateral attack on the PJM cost allocation method. Numerous parties filed requests for rehearing of the Commission's December 15 order.

Relatedly, on September 8, 2017, under Docket No. EL17-84, the Commission issued an order instituting an proceeding pursuant to Section 206 of the FPA directing PJM and PSEG to show cause (1) why its existing interconnection service agreement between Hudson Transmission Partners, LLC (HTP), PSEG, and PJM was not unjust and unreasonable and unduly discriminatory to the extent it failed to allow HTP to convert its firm transmission withdrawal rights to non-firm transmission withdrawal rights; and (2) why PSEG’s failure to consent to an amendment reflecting the same was not unjust, unreasonable, and unduly discriminatory. On September 29, 2017, PJM and PSEG filed responses to the Commission's September 8 show cause order. On December 15, 2017, the Commission issued an order finding the interconnection service agreement with HTP unjust and unreasonable insofar as it does not permit HTP to convert its firm transmission withdrawal rights to non-firm transmission withdrawal rights, and directing PJM to submit a compliance filing amending the agreement accordingly. Numerous parties filed requests for rehearing of the Commission's December 15 order.

On August 25, 2015, under Docket No. ER15-2562, pursuant to section 205 of the FPA, PJM filed amendments to Schedule 12-Appendix A of the PJM Tariff to incorporate cost responsibility assignments for 19 of the 31 transmission projects included in its 2015 update to the RTEP. On April 22, 2016, the Commission issued an order approving PJM's amendments, finding that PJM complied with its Tariff obligations in applying the solutionbased distribution factor cost allocation methodology. Numerous parties filed requests for rehearing of the April 22 order.

On February 8, 2017, under Docket No. ER17-950, PJM filed proposed amendments to Schedule 12-Appendix and Schedule 12-Appendix A of the PJM Tariff regarding cost reallocations for certain projects included in the PJM RTEP. On April 25, 2017, the Commission issued a letter order accepting and suspending PJM proposed revisions for a nominal period, subject to refund, stating the proposed changes may be unjust, unreasonable, and unduly discriminatory or preferential, or otherwise unlawful. Linden and the New York Power Authority filed requests for rehearing, or, in the alternative, clarification of the Commission's April 25 letter order.

On December 29, 2017, as amended on January 3, 2018, under Docket No. ER18-579, PJM, pursuant to section 205 of the Federal Power Act, filed revisions in Docket ER18-579 to Schedule 12-Appendix and Schedule 12- Appendix A of the PJM Tariff to provide updated annual cost responsibility assignments for Regional Facilities and Necessary Lower Voltage Facilities, and Lower Voltage Facilities included in the PJM RTEP. On March 5, 2018, the Commission issued an order accepting PJM’s proposed tariff changes, approving PJM's proposal to reduce the load-ratio share cost responsibility assignments and solution-based distribution factor cost allocation methodology for certain merchant transmission facility owners to zero, effective January 1, 2018. Numerous parties have filed requests for rehearing of the Commission's March 5 order.

On January 19, 2018, under Docket No. ER18-680, PJM submitted for filing proposed revisions to Schedule 12- Appendix and Schedule 12-Appendix A of the PJM Tariff to implement the changes directed by the Commission in its two December 15, 2017, orders. Numerous parties filed interventions, comments, and protests with respect to PJM's proposed revisions.

Agenda item E-4 may be an order related to the above proceedings.

E-5 – KCP&L Greater Missouri Operations Company (Docket No. EL18-146-00). On May 11, 2018, KCP&L Greater Missouri Operations Company (GMO) filed a Petition for Declaratory Order finding that the proposed payment of dividends furnished in the filing is in compliance with section 305(a) of the Federal Power Act (FPA). GMO states that the Tax Cuts and Jobs Act passed into law in December 2017 resulted in a one-time, non-cash charge to income tax expense of $111.6 million due to the re-evaluation of its non-regulated deferred income tax assets. As such, this one-time charge has constrained the ability of GMO to pay dividends to Great Plains Energy, its parent company and sole shareholder. In the Petition, GMO requests authorization pay current dividends from Account 211 until it has retained sufficient earnings to pay dividends. Agenda item E-5 may be an order on the Petition for Declaratory Order.

E-6 – Delaware Public Service Commission and Maryland Public Service Commission v. PJM Interconnection, L.L.C. and Certain Transmission Owners Designated under CTOA RS FERC No. 42 (Docket No. EL15-95-003). On August 28, 2015, PJM Interconnection, L.L.C. (PJM) filed proposed amendments to its Tariff to reflect cost allocations for the Artificial Island Project, pursuant to section 205 of the FPA. Contemporaneously, the Delaware Public Service Commission and the Maryland Public Service Commission (collectively, the Complainants) filed a Complaint alleging that methodology used in determining the proposed cost allocations was unjust and unreasonable. On November 24, 2015, the Commission issued an order suspending the proposed Tariff amendments for a period of five months, while withholding a final determination on the reasonableness of the cost allocations. To evaluate the methodology fully, the Commission held a technical conference on January 12, 2016. Ultimately, on April 22, 2016, the Commission issued an order denying the Complaint and accepting the proposed cost responsibility assignments as set forth in the PJM filing. On May 23, 2016, the Complainants filed a Request for Rehearing of the April 22 order, asserting that the order failed to establish why PJM would be allowed to apply a different cost allocation methodology and that the Commission had acted in an arbitrary and capricious manner. Referencing changed circumstances in the project, the Complainants filed a Motion to Defer Ruling on August 23, 2016. The Complainants stated that PJM had suspended all elements of the Artificial Island Project due to further analysis — scheduled to be complete by February 2017 — contemplating new financial requirements and obligations. Agenda item E-6 may be an order on the Request for Rehearing or the Motion to Defer Ruling.

Gas

G-1 – Guttman Energy, Inc. and PBF Holding Company LLC v. Buckeye Pipe Line Company, L.P. and Laurel Pipe Line Company, L.P. (Docket No. OR14-4-002). On October 15, 2013, Guttman Energy, Inc. and PBF Holding Company (the Complainants) filed a complaint, pursuant to the Interstate Commerce Act (ICA), alleging that Buckeye Pipeline Company, L.P. and Laurel Pipe Line Company, L.P. (collectively, the Carriers) were: 1) charging Guttman interstate rates for intrastate transportation service, 2) were discriminating by charging higher rates for interstate service than for identical intrastate service, and 3) that Buckeye has significant market power in markets in which it has market-based rate authority. On May 2, 2014, the Commission issued an order dismissing the Complaint against Laurel and the discrimination claims against Buckeye, and establishing a hearing to examine whether Buckeye possesses market power in the Pittsburg and Harrisburg markets. On June 2, 2014, the Complainants filed a request for rehearing and clarification of the May 2 Order requesting rehearing of the Commission's determination that Buckeye properly charged Guttman its interstate rate and clarification that the scope of the hearing included both market power and cost-of-service issues. On November 6, 2014, the Commission issued an Order on Rehearing and Establishing Hearing that established a hearing as to whether the Complainants shipments should be considered interstate or intrastate transportation. The Commission subsequently consolidated the hearing into the ongoing hearing proceeding regarding Buckeye's market-based rate. The hearing was held from September 29, 2015 through October 19, 2015. On November 16, 2017, the Commission issued an Order on Initial Decision that addressed the Initial Decision and Briefs On and Opposing Exceptions. The Order on Initial Decision affirmed the Presiding Judge's that the shipments at issue were interstate in character, reversed the Presiding Judge in finding that Buckeye's market-based rate authority in the Pittsburgh destination should be revoked, and affirmed the Presiding Judge's recommendation that Buckeye's market-based rate authority for the Harrisburg destination market be revoked. On December 18, 2017, Buckeye requested rehearing of the Commission's Order on Initial Decision. Agenda item G-1 may be an order responding to the request for rehearing.

Hydro

H-1 – Omitted

H-2 – Public Utility District No. 2 of Grant County, Washington (Docket No. P-2114-296). On April 7, 2017, Public Utility District No. 2 of Grant County, Washington (Grant PUD), licensee for the Priest Rapids Hydroelectric Project No. 2114 (Priest Rapids Project), filed an application for non-project use authorization to permit Stockdale, Inc. (Stockdale) to increase the watercraft capacity at the existing Vantage Riverstone Marina (Vantage Marina) on the Columbia River in the Wanapum Dam Reservoir near Vantage, Kittitas County, Washington. On March 15, 2018, the Commission conditionally approved Grant PUD's request. On April 15, 2018, a request for rehearing was submitted by Pat Kelleher. Agenda item H-2 may be an order responding to the request for rehearing.

H-3 – Verdant Power, LLC (Docket No. P-12611-011). On December 29, 2017, Verdant Power, LLC (Verdant) submitted a request for a five-year extension of the term of its pilot license for the Roosevelt Island Tidal Energy Project No. 12611, and a Notice of Intent to relicense the project, pursuant to section 5.5(d) of the Commission's regulations. On May 3, 2018, the Commission issued an order rejecting Verdant's request for an extension, and denying Verdant's request of a waiver of the Commission's filing requirements so that it may file a pre-application document and Notice of Intent two years before expiration of the pilot license. On June 1, 2018, Verdant submitted, pursuant to section 313(a) of the FPA, a request for rehearing of the Commission May 3 Order. Agenda item H-3 may be an order responding to the request for rehearing.

Certificates

C-1 – Columbia Gas Transmission, LLC (Docket No. CP17-80-000). On March 15, 2017, Columbia Gas Transmission submitted an application for a certificate of public convenience and necessity for the Eastern Panhandle Expansion Project (Project), which, as proposed, will consist of approximately 3.4 miles of newly constructed pipeline running from Fulton County, Pennsylvania to Morgan County, West Virginia. On January 27, 2018, FERC staff issued the Environmental Assessment for the Project, and comments on the Environmental Assessment were due on February 26, 2018. Agenda item C-1 may be an order granting a certificate for the Project.

C-2 – Texas Eastern Transmission, LP (Docket No. CP18-10-000). On October 19, 2017, Enbridge – Texas Eastern Transmission LP (Texas Eastern) submitted an application for a certificate of public convenience and necessity for the TX-LA Markets Project (Project), which, as proposed, will modify Texas Eastern's existing Gillis Compressor Station in Beauregard Parish, Louisiana to provide additional firm capacity. On May 31, 2018, FERC staff issued the Environmental Assessment for the Project. Agenda item C-2 may be an order in the proceeding.

C-3 – Northwest Pipeline LLC (Docket Nos. CP17-441-000, CP17-441-001). On May 11, 2017, Northwest Pipeline LLC (Northwest) submitted an application requesting abandonment and certificate approvals necessary for its North Seattle Lateral Upgrade Project (Project), which, as proposed, will replace approximately 5.9 miles of 8-inch diameter pipeline with 20-inch diameter pipeline in Snohomish County, Washington to increase service reliability and provide additional firm capacity. On February 12, 2018, FERC staff issued the Environmental Assessment for the Project, and comments on the Environmental Assessment were due on March 13, 2018. On May 22, 2018, Northwest requested issuance of a certificate order for the Project. Agenda item C-3 may be an order granting a certificate for the Project.

C-4 – Gulf South Pipeline Company, LP (Docket No. CP18-66-000), Tristate NLA, LLC (Docket No. CP18-69- 000). On January 26, 2018, Gulf South Pipeline Company, LP (Gulf South) filed an Abbreviated Application for Authorization to Abandon Certain Pipeline Facilities pursuant to section 7(b) of the Natural Gas Act (NGA). Gulf South intends to abandon by sale gathering and transmission pipelines located in Texas and Louisiana to Tristate NLA, LLC (Tristate), which filed a contemporaneous Petition for Declaratory Order pertaining to the jurisdictional status of the aforementioned facilities. Tristate asserts that the facilities would operate as a combination of intrastate pipelines and gathering facilities outside of Commission jurisdiction, and the only existing 'no-notice' firm customer would not be affected. CenterPoint Energy Resources Corporation, the lone customer, filed comments on February 28, 2018, expressing concerns that certain prerequisites and procedural steps may not be finished by the proposed date for authorization. On March 7, 2018, the Commission issued the Environmental Assessment, finding the application is designated as a categorical exclusion, as no facilities are proposed to be constructed or physically abandoned. Agenda item C-4 may be an order on the contemporaneous Abbreviated Application and Petition submitted by Gulf South and Tristate, respectively.

C-5 – Constitution Pipeline Company, LLC (Docket No. CP18-5-001). On June 13, 2013, Constitution Pipeline Company (Constitution) filed an Application for Certificate of Public Convenience and Necessity (CPCN) pursuant to section 7 of the NGA to construct and operate its proposed Constitution Pipeline Project. Located in Pennsylvania and New York, the proposed pipeline would comprise 124 miles. On April 22, 2016, the New York Department of Environmental Conservation (NY DEC) denied the application for water quality certification, citing insufficient information to evaluate compliance with New York water quality standards. Subsequently, Constitution sought relief before the US Court of Appeals for the Second Circuit, arguing that NY DEC had acted to delay the review process and that it had furnished sufficient information. On August 18, 2017, the court issued an opinion upholding the denial by NY DEC. Constitution filed a Petition for Declaratory Order on October 11, 2017, asserting that NY DEC had waived its authority under the Clean Water Act by failing to act within a reasonable time period. On January 11, 2018, the Commission issued an order denying the Petition for Declaratory Order. Following the denial, Constitution filed a Request for Rehearing on February 12, 2018. Agenda item C-5 may be an order on the request for rehearing.

C-6 – NEXUS Gas Transmission, LLC (Docket No. CP16-22-001), Texas Eastern Transmission, LP (Docket No. CP23-001), DTE Gas Company (Docket No. CP16-24-001), Vector Pipeline L.P. (Docket No. CP16-102- 001). On August 25, 2017, the Commission issued an order granting authorization pursuant to section 7(c) of the NGA to NEXUS Gas Transmission, LLC (NEXUS) to construct and operate a new pipeline system located in Ohio, Michigan, and Canada. In addition, the Commission authorized Texas Eastern Transmission, LP (Texas Eastern) to construct and operate natural gas pipeline facilities to a proposed interconnection with the NEXUS project in Ohio. The order issued on August 25, 2017 also granted authorization to DTE Gas Company (DTE) and Vector Pipeline, L.P. (Vector) to lease certain capacity to NEXUS in connection with the project. On September 22, 2017, the Sierra Club filed a Request for Rehearing and a Stay, joined in the following days by a number of other parties. The Commission issued an order denying the stay on January 10, 2018, finding that the parties did not demonstrate irreparable harm (as supported by the Environmental Impact Statement issued in the original docket). Agenda item C-6 may be an order on the requests for rehearing relating to the NEXUS, Texas Eastern, DTE, and Vector authorizations.

C-7 – Millennium Pipeline Company, L.L.C. (Docket No. CP16-486-001). On July 29, 2016, Millennium Pipeline Company, L.L.C. (Millennium) filed an Application for Certificate of Public Convenience and Necessity pursuant to section 7(c) of the NGA for authorization to construct and operate the Easter System Upgrade Project located in New York. The Commission granted the CPCN to Millennium on November 28, 2017. On December 1, 2017, Delaware Riverkeeper Network (DRN) filed a Request for Rehearing, stating that the Commission had performed the environmental review without meeting the requirements set forth by the National Environmental Policy Act. The Commission issued an Environmental Assessment (EA) finding the project would not pose a significant risk to the human environment; DRN alleges that an Environmental Impact Statement would be necessary rather than the EA. DRN contemporaneously submitted a Motion for Stay pending the rehearing decision. On December 19, 2017, Protect Orange County filed a Request for Rehearing. Agenda item C-7 may be an order on the requests for rehearing and the motion for stay.

Click here to download PDF.

[View source.]

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© White & Case LLP | Attorney Advertising

Written by:

White & Case LLP
Contact
more
less

White & Case LLP on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide

JD Supra Privacy Policy

Updated: May 25, 2018:

JD Supra is a legal publishing service that connects experts and their content with broader audiences of professionals, journalists and associations.

This Privacy Policy describes how JD Supra, LLC ("JD Supra" or "we," "us," or "our") collects, uses and shares personal data collected from visitors to our website (located at www.jdsupra.com) (our "Website") who view only publicly-available content as well as subscribers to our services (such as our email digests or author tools)(our "Services"). By using our Website and registering for one of our Services, you are agreeing to the terms of this Privacy Policy.

Please note that if you subscribe to one of our Services, you can make choices about how we collect, use and share your information through our Privacy Center under the "My Account" dashboard (available if you are logged into your JD Supra account).

Collection of Information

Registration Information. When you register with JD Supra for our Website and Services, either as an author or as a subscriber, you will be asked to provide identifying information to create your JD Supra account ("Registration Data"), such as your:

  • Email
  • First Name
  • Last Name
  • Company Name
  • Company Industry
  • Title
  • Country

Other Information: We also collect other information you may voluntarily provide. This may include content you provide for publication. We may also receive your communications with others through our Website and Services (such as contacting an author through our Website) or communications directly with us (such as through email, feedback or other forms or social media). If you are a subscribed user, we will also collect your user preferences, such as the types of articles you would like to read.

Information from third parties (such as, from your employer or LinkedIn): We may also receive information about you from third party sources. For example, your employer may provide your information to us, such as in connection with an article submitted by your employer for publication. If you choose to use LinkedIn to subscribe to our Website and Services, we also collect information related to your LinkedIn account and profile.

Your interactions with our Website and Services: As is true of most websites, we gather certain information automatically. This information includes IP addresses, browser type, Internet service provider (ISP), referring/exit pages, operating system, date/time stamp and clickstream data. We use this information to analyze trends, to administer the Website and our Services, to improve the content and performance of our Website and Services, and to track users' movements around the site. We may also link this automatically-collected data to personal information, for example, to inform authors about who has read their articles. Some of this data is collected through information sent by your web browser. We also use cookies and other tracking technologies to collect this information. To learn more about cookies and other tracking technologies that JD Supra may use on our Website and Services please see our "Cookies Guide" page.

How do we use this information?

We use the information and data we collect principally in order to provide our Website and Services. More specifically, we may use your personal information to:

  • Operate our Website and Services and publish content;
  • Distribute content to you in accordance with your preferences as well as to provide other notifications to you (for example, updates about our policies and terms);
  • Measure readership and usage of the Website and Services;
  • Communicate with you regarding your questions and requests;
  • Authenticate users and to provide for the safety and security of our Website and Services;
  • Conduct research and similar activities to improve our Website and Services; and
  • Comply with our legal and regulatory responsibilities and to enforce our rights.

How is your information shared?

  • Content and other public information (such as an author profile) is shared on our Website and Services, including via email digests and social media feeds, and is accessible to the general public.
  • If you choose to use our Website and Services to communicate directly with a company or individual, such communication may be shared accordingly.
  • Readership information is provided to publishing law firms and authors of content to give them insight into their readership and to help them to improve their content.
  • Our Website may offer you the opportunity to share information through our Website, such as through Facebook's "Like" or Twitter's "Tweet" button. We offer this functionality to help generate interest in our Website and content and to permit you to recommend content to your contacts. You should be aware that sharing through such functionality may result in information being collected by the applicable social media network and possibly being made publicly available (for example, through a search engine). Any such information collection would be subject to such third party social media network's privacy policy.
  • Your information may also be shared to parties who support our business, such as professional advisors as well as web-hosting providers, analytics providers and other information technology providers.
  • Any court, governmental authority, law enforcement agency or other third party where we believe disclosure is necessary to comply with a legal or regulatory obligation, or otherwise to protect our rights, the rights of any third party or individuals' personal safety, or to detect, prevent, or otherwise address fraud, security or safety issues.
  • To our affiliated entities and in connection with the sale, assignment or other transfer of our company or our business.

How We Protect Your Information

JD Supra takes reasonable and appropriate precautions to insure that user information is protected from loss, misuse and unauthorized access, disclosure, alteration and destruction. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. You should keep in mind that no Internet transmission is ever 100% secure or error-free. Where you use log-in credentials (usernames, passwords) on our Website, please remember that it is your responsibility to safeguard them. If you believe that your log-in credentials have been compromised, please contact us at privacy@jdsupra.com.

Children's Information

Our Website and Services are not directed at children under the age of 16 and we do not knowingly collect personal information from children under the age of 16 through our Website and/or Services. If you have reason to believe that a child under the age of 16 has provided personal information to us, please contact us, and we will endeavor to delete that information from our databases.

Links to Other Websites

Our Website and Services may contain links to other websites. The operators of such other websites may collect information about you, including through cookies or other technologies. If you are using our Website or Services and click a link to another site, you will leave our Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We are not responsible for the data collection and use practices of such other sites. This Policy applies solely to the information collected in connection with your use of our Website and Services and does not apply to any practices conducted offline or in connection with any other websites.

Information for EU and Swiss Residents

JD Supra's principal place of business is in the United States. By subscribing to our website, you expressly consent to your information being processed in the United States.

  • Our Legal Basis for Processing: Generally, we rely on our legitimate interests in order to process your personal information. For example, we rely on this legal ground if we use your personal information to manage your Registration Data and administer our relationship with you; to deliver our Website and Services; understand and improve our Website and Services; report reader analytics to our authors; to personalize your experience on our Website and Services; and where necessary to protect or defend our or another's rights or property, or to detect, prevent, or otherwise address fraud, security, safety or privacy issues. Please see Article 6(1)(f) of the E.U. General Data Protection Regulation ("GDPR") In addition, there may be other situations where other grounds for processing may exist, such as where processing is a result of legal requirements (GDPR Article 6(1)(c)) or for reasons of public interest (GDPR Article 6(1)(e)). Please see the "Your Rights" section of this Privacy Policy immediately below for more information about how you may request that we limit or refrain from processing your personal information.
  • Your Rights
    • Right of Access/Portability: You can ask to review details about the information we hold about you and how that information has been used and disclosed. Note that we may request to verify your identification before fulfilling your request. You can also request that your personal information is provided to you in a commonly used electronic format so that you can share it with other organizations.
    • Right to Correct Information: You may ask that we make corrections to any information we hold, if you believe such correction to be necessary.
    • Right to Restrict Our Processing or Erasure of Information: You also have the right in certain circumstances to ask us to restrict processing of your personal information or to erase your personal information. Where you have consented to our use of your personal information, you can withdraw your consent at any time.

You can make a request to exercise any of these rights by emailing us at privacy@jdsupra.com or by writing to us at:

Privacy Officer
JD Supra, LLC
10 Liberty Ship Way, Suite 300
Sausalito, California 94965

You can also manage your profile and subscriptions through our Privacy Center under the "My Account" dashboard.

We will make all practical efforts to respect your wishes. There may be times, however, where we are not able to fulfill your request, for example, if applicable law prohibits our compliance. Please note that JD Supra does not use "automatic decision making" or "profiling" as those terms are defined in the GDPR.

  • Timeframe for retaining your personal information: We will retain your personal information in a form that identifies you only for as long as it serves the purpose(s) for which it was initially collected as stated in this Privacy Policy, or subsequently authorized. We may continue processing your personal information for longer periods, but only for the time and to the extent such processing reasonably serves the purposes of archiving in the public interest, journalism, literature and art, scientific or historical research and statistical analysis, and subject to the protection of this Privacy Policy. For example, if you are an author, your personal information may continue to be published in connection with your article indefinitely. When we have no ongoing legitimate business need to process your personal information, we will either delete or anonymize it, or, if this is not possible (for example, because your personal information has been stored in backup archives), then we will securely store your personal information and isolate it from any further processing until deletion is possible.
  • Onward Transfer to Third Parties: As noted in the "How We Share Your Data" Section above, JD Supra may share your information with third parties. When JD Supra discloses your personal information to third parties, we have ensured that such third parties have either certified under the EU-U.S. or Swiss Privacy Shield Framework and will process all personal data received from EU member states/Switzerland in reliance on the applicable Privacy Shield Framework or that they have been subjected to strict contractual provisions in their contract with us to guarantee an adequate level of data protection for your data.

California Privacy Rights

Pursuant to Section 1798.83 of the California Civil Code, our customers who are California residents have the right to request certain information regarding our disclosure of personal information to third parties for their direct marketing purposes.

You can make a request for this information by emailing us at privacy@jdsupra.com or by writing to us at:

Privacy Officer
JD Supra, LLC
10 Liberty Ship Way, Suite 300
Sausalito, California 94965

Some browsers have incorporated a Do Not Track (DNT) feature. These features, when turned on, send a signal that you prefer that the website you are visiting not collect and use data regarding your online searching and browsing activities. As there is not yet a common understanding on how to interpret the DNT signal, we currently do not respond to DNT signals on our site.

Access/Correct/Update/Delete Personal Information

For non-EU/Swiss residents, if you would like to know what personal information we have about you, you can send an e-mail to privacy@jdsupra.com. We will be in contact with you (by mail or otherwise) to verify your identity and provide you the information you request. We will respond within 30 days to your request for access to your personal information. In some cases, we may not be able to remove your personal information, in which case we will let you know if we are unable to do so and why. If you would like to correct or update your personal information, you can manage your profile and subscriptions through our Privacy Center under the "My Account" dashboard. If you would like to delete your account or remove your information from our Website and Services, send an e-mail to privacy@jdsupra.com.

Changes in Our Privacy Policy

We reserve the right to change this Privacy Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our Privacy Policy will become effective upon posting of the revised policy on the Website. By continuing to use our Website and Services following such changes, you will be deemed to have agreed to such changes.

Contacting JD Supra

If you have any questions about this Privacy Policy, the practices of this site, your dealings with our Website or Services, or if you would like to change any of the information you have provided to us, please contact us at: privacy@jdsupra.com.

JD Supra Cookie Guide

As with many websites, JD Supra's website (located at www.jdsupra.com) (our "Website") and our services (such as our email article digests)(our "Services") use a standard technology called a "cookie" and other similar technologies (such as, pixels and web beacons), which are small data files that are transferred to your computer when you use our Website and Services. These technologies automatically identify your browser whenever you interact with our Website and Services.

How We Use Cookies and Other Tracking Technologies

We use cookies and other tracking technologies to:

  1. Improve the user experience on our Website and Services;
  2. Store the authorization token that users receive when they login to the private areas of our Website. This token is specific to a user's login session and requires a valid username and password to obtain. It is required to access the user's profile information, subscriptions, and analytics;
  3. Track anonymous site usage; and
  4. Permit connectivity with social media networks to permit content sharing.

There are different types of cookies and other technologies used our Website, notably:

  • "Session cookies" - These cookies only last as long as your online session, and disappear from your computer or device when you close your browser (like Internet Explorer, Google Chrome or Safari).
  • "Persistent cookies" - These cookies stay on your computer or device after your browser has been closed and last for a time specified in the cookie. We use persistent cookies when we need to know who you are for more than one browsing session. For example, we use them to remember your preferences for the next time you visit.
  • "Web Beacons/Pixels" - Some of our web pages and emails may also contain small electronic images known as web beacons, clear GIFs or single-pixel GIFs. These images are placed on a web page or email and typically work in conjunction with cookies to collect data. We use these images to identify our users and user behavior, such as counting the number of users who have visited a web page or acted upon one of our email digests.

JD Supra Cookies. We place our own cookies on your computer to track certain information about you while you are using our Website and Services. For example, we place a session cookie on your computer each time you visit our Website. We use these cookies to allow you to log-in to your subscriber account. In addition, through these cookies we are able to collect information about how you use the Website, including what browser you may be using, your IP address, and the URL address you came from upon visiting our Website and the URL you next visit (even if those URLs are not on our Website). We also utilize email web beacons to monitor whether our emails are being delivered and read. We also use these tools to help deliver reader analytics to our authors to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

Analytics/Performance Cookies. JD Supra also uses the following analytic tools to help us analyze the performance of our Website and Services as well as how visitors use our Website and Services:

  • HubSpot - For more information about HubSpot cookies, please visit legal.hubspot.com/privacy-policy.
  • New Relic - For more information on New Relic cookies, please visit www.newrelic.com/privacy.
  • Google Analytics - For more information on Google Analytics cookies, visit www.google.com/policies. To opt-out of being tracked by Google Analytics across all websites visit http://tools.google.com/dlpage/gaoptout. This will allow you to download and install a Google Analytics cookie-free web browser.

Facebook, Twitter and other Social Network Cookies. Our content pages allow you to share content appearing on our Website and Services to your social media accounts through the "Like," "Tweet," or similar buttons displayed on such pages. To accomplish this Service, we embed code that such third party social networks provide and that we do not control. These buttons know that you are logged in to your social network account and therefore such social networks could also know that you are viewing the JD Supra Website.

Controlling and Deleting Cookies

If you would like to change how a browser uses cookies, including blocking or deleting cookies from the JD Supra Website and Services you can do so by changing the settings in your web browser. To control cookies, most browsers allow you to either accept or reject all cookies, only accept certain types of cookies, or prompt you every time a site wishes to save a cookie. It's also easy to delete cookies that are already saved on your device by a browser.

The processes for controlling and deleting cookies vary depending on which browser you use. To find out how to do so with a particular browser, you can use your browser's "Help" function or alternatively, you can visit http://www.aboutcookies.org which explains, step-by-step, how to control and delete cookies in most browsers.

Updates to This Policy

We may update this cookie policy and our Privacy Policy from time-to-time, particularly as technology changes. You can always check this page for the latest version. We may also notify you of changes to our privacy policy by email.

Contacting JD Supra

If you have any questions about how we use cookies and other tracking technologies, please contact us at: privacy@jdsupra.com.

- hide

This website uses cookies to improve user experience, track anonymous site usage, store authorization tokens and permit sharing on social media networks. By continuing to browse this website you accept the use of cookies. Click here to read more about how we use cookies.