On October 5, 2012, Commissioner Mark Ferron of the California Public Utilities Commission (CPUC or Commission) issued a ruling proposing reforms to California's Renewables Portfolio Standard (RPS) procurement process. These proposals would streamline the CPUC's approval process for certain power purchase agreements (PPAs) between utilities and renewable energy developers under California's RPS, change the standard by which such PPAs are reviewed, and create a clear timeline for approvals. The goal of these changes is to promote greater certainty in the California renewable energy market. The ruling requests input from interested parties by November 15. This represents a significant opportunity for project developers and financiers who currently participate or are interested in participating in the California renewable energy markets to address shortcomings in the RPS procurement process and suggest improvements.

This new ruling follows Commissioner Ferron's April 2012 ruling, which also sought to reform California's RPS procurement process. Changes proposed under the April ruling included establishing a two-year procurement authorization process (i.e., annual RPS solicitations would not be required), changes to the "Least-Cost, Best-Fit" (LCBF) methodology for evaluating RPS-eligible PPAs, requiring an Independent Evaluator (IE) report earlier in the procurement process, efforts to minimize transmission upgrade costs, and other actions.

The second ruling summarizes the major changes that have taken place in the California renewable energy markets over the past couple of years, observing a 250 percent increase in the number of bidders and a 150 percent increase in the number of developers in the 2011 RPS solicitation as compared with the 2009 solicitation. According to the ruling, the total amount of renewable energy generation bid into the 2011 RPS solicitation was 4.5 times greater than the total compliance need under the RPS. The ruling notes that in light of this increased supply and the decrease in the cost of many renewable energy technologies over this time period, the average bid price of projects decreased by approximately 30 percent between the 2009 and 2011 solicitations.

In light of these significant changes in the California renewable energy markets and modifications to the RPS program implemented in response to Senate Bill 2 (1X) (Simitian, Stats. 2011, ch.1) (SB 2(1X)), the ruling concludes that the following changes to the procurement process are needed to increase transparency, efficiency, and market certainty:

  • Shortlists to Undergo Tier 3 Advice Letter Review. Of the PPAs submitted in response to an RPS solicitation, the Investor Owned Utilities (IOUs) create a shortlist of bids that meet their CPUC-approved evaluation criteria. Currently, the shortlists are approved by the CPUC Energy Division at the staff level. The proposal would require review and full Commission approval of the IOUs' shortlists by resolution.
  • Defined Timeline for Contract Execution and Approval. Under existing regulations, there are no deadlines that determine when RPS PPAs must be executed and when the IOUs must request CPUC approval of the PPAs they execute. This has led to lengthy delays in the procurement process, Commission review of PPAs long after market conditions have changed, and uncertainty for project developers. The proposal set forth in the ruling would reform the California RPS procurement process by requiring PPAs to be executed within one year of Commission approval of the IOU shortlist and filed with the CPUC for approval within one month of the date such contracts are signed.
  • Tier 1 Advice Letter Approval for PPAs of Less Than Five Years. Currently, all PPAs executed by IOUs must be approved for cost recovery by the full Commission by resolution in order to comply with the RPS. The ruling proposes that PPAs with terms of less than five years be approved by the CPUC's Energy Division at the staff level via an expedited Tier 1 Advice Letter if certain conditions are met (i.e., generation quantity consistent with IOU's net short, contract selected from competitive solicitation or bilateral negotiations and has equivalent or better market value than recently executed similar contracts, use of pro forma contract, and delivery within one year of execution).
  • Tier 2 Advice Letter Approval for PPAs Greater Than Five Years. As proposed in the ruling, PPAs with terms of greater than five years that use commercially proven technologies would be approved by CPUC Energy Division staff via an expedited Tier 2 Advice Letter if certain conditions are met (i.e., generation quantity consistent with IOU's net short, contract selected from competitive solicitation, use of pro forma contract, delivery consistent with procurement need in IOU's RPS procurement plan, and project viability criteria).
  • Changes to RPS Standard of Review for Tier 3 Advice Letter Review. For PPAs that do not meet the new conditions for expedited Tier 1 or Tier 2 review summarized above (which must therefore undergo full Commission review via Tier 3 Advice Letter), the ruling proposes three new standards of review for three types of PPA cost recovery approval: (1) PPAs selected from a competitive solicitation, (2) PPAs negotiated bilaterally with the IOUs, and (3) amendments to PPAs. The detailed standards of review proposed in the ruling are specific to each of these three types of approvals and are organized by the following categories of criteria: portfolio need; price reasonableness; project value; project viability; and consistency with CPUC decisions, rules, and laws.
  • Applications for PPAs Not Meeting the RPS Standards of Review. The ruling proposes that if a PPA does not meet the standards of review for Tier 3 Advice Letters (e.g., unproven technology, project will provide greater than 1 percent of an IOU's total bundled sales in first year of delivery, or contracts with other extenuating circumstances), the PPA must be submitted for approval to the CPUC as an application and subject to a different review criteria.
  • New Standard of Review for Unbundled REC Contracts and IOU Sales of Excess Procurement. The ruling proposes a new standard of review for contracts for the purchase of renewable energy credits (RECs) procured separately from the underlying energy used to satisfy RPS procurement requirements. This standard also would apply to IOU sales of excess RPS-eligible procurement that do not qualify for the expedited Tier 1 or Tier 2 approval processes outlined above.
  • New Independent Evaluator Report Template. The Commission's RPS procurement approval process involves the use of IEs hired by the IOUs to evaluate the solicitation and procurement selection process. The ruling proposes specific evaluation criteria that would be included in the IE report template.
  • Least-Cost, Best-Fit Methodology. SB 2(1X) requires that the criteria for the rank ordering and selection of "least-cost and best-fit" resources eligible for compliance with the RPS take into account estimates of integration costs and costs of procurement, project viability, and workforce recruitment, training, and retention efforts, including the goals of recruiting and training women, minorities, and disabled veterans. The ruling requests input from parties on how to implement the new LCBF criteria required the statute.
  • Potential Revisions to "Green Attributes" Standard Term and Condition. Form PPAs under California's RPS currently contain a standard term and condition (STC) regarding "Green Attributes" (i.e., RECs, offsets, allowances, avoided pollutants, etc.). The STC defines "Green Attributes" and requires the seller to convey all Green Attributes to the buyer. The ruling invites input from parties on whether this STC is still necessary and useful.

The ruling requests comments and input from interested parties and poses specific discussion questions for each of the proposals. We encourage market participants to weigh in on these reforms and suggest ways to improve California's RPS procurement process. Comments are due November 15, 2012, and reply comments must be submitted by December 7, 2012. If your company is interested in filing comments or would like more information on the proposals contained in the ruling, please contact Todd Glass or Sheridan Pauker in the firm's energy and clean technology practice.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Wilson Sonsini Goodrich & Rosati | Attorney Advertising

Written by:

Wilson Sonsini Goodrich & Rosati
Contact
more
less

Wilson Sonsini Goodrich & Rosati on:

Readers' Choice 2017
Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Privacy Policy (Updated: October 8, 2015):
hide

JD Supra provides users with access to its legal industry publishing services (the "Service") through its website (the "Website") as well as through other sources. Our policies with regard to data collection and use of personal information of users of the Service, regardless of the manner in which users access the Service, and visitors to the Website are set forth in this statement ("Policy"). By using the Service, you signify your acceptance of this Policy.

Information Collection and Use by JD Supra

JD Supra collects users' names, companies, titles, e-mail address and industry. JD Supra also tracks the pages that users visit, logs IP addresses and aggregates non-personally identifiable user data and browser type. This data is gathered using cookies and other technologies.

The information and data collected is used to authenticate users and to send notifications relating to the Service, including email alerts to which users have subscribed; to manage the Service and Website, to improve the Service and to customize the user's experience. This information is also provided to the authors of the content to give them insight into their readership and help them to improve their content, so that it is most useful for our users.

JD Supra does not sell, rent or otherwise provide your details to third parties, other than to the authors of the content on JD Supra.

If you prefer not to enable cookies, you may change your browser settings to disable cookies; however, please note that rejecting cookies while visiting the Website may result in certain parts of the Website not operating correctly or as efficiently as if cookies were allowed.

Email Choice/Opt-out

Users who opt in to receive emails may choose to no longer receive e-mail updates and newsletters by selecting the "opt-out of future email" option in the email they receive from JD Supra or in their JD Supra account management screen.

Security

JD Supra takes reasonable precautions to insure that user information is kept private. We restrict access to user information to those individuals who reasonably need access to perform their job functions, such as our third party email service, customer service personnel and technical staff. However, please note that no method of transmitting or storing data is completely secure and we cannot guarantee the security of user information. Unauthorized entry or use, hardware or software failure, and other factors may compromise the security of user information at any time.

If you have reason to believe that your interaction with us is no longer secure, you must immediately notify us of the problem by contacting us at info@jdsupra.com. In the unlikely event that we believe that the security of your user information in our possession or control may have been compromised, we may seek to notify you of that development and, if so, will endeavor to do so as promptly as practicable under the circumstances.

Sharing and Disclosure of Information JD Supra Collects

Except as otherwise described in this privacy statement, JD Supra will not disclose personal information to any third party unless we believe that disclosure is necessary to: (1) comply with applicable laws; (2) respond to governmental inquiries or requests; (3) comply with valid legal process; (4) protect the rights, privacy, safety or property of JD Supra, users of the Service, Website visitors or the public; (5) permit us to pursue available remedies or limit the damages that we may sustain; and (6) enforce our Terms & Conditions of Use.

In the event there is a change in the corporate structure of JD Supra such as, but not limited to, merger, consolidation, sale, liquidation or transfer of substantial assets, JD Supra may, in its sole discretion, transfer, sell or assign information collected on and through the Service to one or more affiliated or unaffiliated third parties.

Links to Other Websites

This Website and the Service may contain links to other websites. The operator of such other websites may collect information about you, including through cookies or other technologies. If you are using the Service through the Website and link to another site, you will leave the Website and this Policy will not apply to your use of and activity on those other sites. We encourage you to read the legal notices posted on those sites, including their privacy policies. We shall have no responsibility or liability for your visitation to, and the data collection and use practices of, such other sites. This Policy applies solely to the information collected in connection with your use of this Website and does not apply to any practices conducted offline or in connection with any other websites.

Changes in Our Privacy Policy

We reserve the right to change this Policy at any time. Please refer to the date at the top of this page to determine when this Policy was last revised. Any changes to our privacy policy will become effective upon posting of the revised policy on the Website. By continuing to use the Service or Website following such changes, you will be deemed to have agreed to such changes. If you do not agree with the terms of this Policy, as it may be amended from time to time, in whole or part, please do not continue using the Service or the Website.

Contacting JD Supra

If you have any questions about this privacy statement, the practices of this site, your dealings with this Web site, or if you would like to change any of the information you have provided to us, please contact us at: info@jdsupra.com.

- hide
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.
Feedback? Tell us what you think of the new jdsupra.com!