The U.S. Court of Appeals for the District of Columbia last week vacated and remanded a 2016 Order by the Federal Energy Regulatory Commission that had authorized construction and operation of the Southeast Market Pipelines...more
8/30/2017
/ Administrative Procedure Act ,
Agency Deference ,
Appeals ,
Certificate of Public Convenience and Necessity ,
Environmental Impact Report (EIR) ,
FERC ,
Greenhouse Gas Emissions ,
Natural Gas ,
NEPA ,
Oil & Gas ,
Permits ,
Pipelines ,
Power Plants ,
Remand ,
Reversal ,
Sierra Club ,
Standard of Review