Bid Protest Minute: Insufficient Funds are Grounds to Cancel

On April 29, the Government Accountability Office (GAO) denied Davenergy-VCI JV, LLC’s protest of a solicitation’s cancellation, holding that the lack of available funding is sufficient grounds to cancel. In denying the...more

Bid Protest Minute – Protest Underscores Importance of Prejudice, Past Performance Requirements, and Protest Timing

On May 7, the Government Accountability Office (GAO) dismissed a protest challenging the terms of a solicitation for being unduly restrictive. The protest highlights three important considerations that contractors should...more

Small Business Size Protest Minute: The Ostensible Subcontractor Exception that (Almost) Swallowed the Rule

As many of our readers know, the ostensible subcontractor rule is one way in which the Small Business Administration (SBA) can find affiliation between a small business and one of its subcontractors, potentially resulting in...more

Bid Protest Minute: Bidder’s Responsibility to Submit Well-Drafted Proposal

On February 26, GAO denied the protest of Mission Analytics, Inc., challenging the award of a small business set-aside contract to ThunderCat Technology, LLC, explaining that “it is a firm’s responsibility to submit a...more

COFC Decision Significantly Broadens OTA Bid Protest Jurisdiction

On February 24, Judge Armando Bonilla of the Court of Federal Claims (COFC) declined to dismiss a challenge to a $648 million award under a Missile Defense Agency (MDA) development deal, finding that the court had...more

Project Labor Agreements No Longer Mandated for Large Federal Construction Contracts

On January 21, in MVL, Inc., et al. v. United States, the U.S. Court of Federal Claims (COFC) struck down a 2022 Executive Order (EO), as well as the implementing Federal Acquisition Regulation (FAR), signed by then-President...more

Bid Protest Minute: Understanding the Increased DoD/Coast Guard/NASA Task Order Protest Threshold

Generally speaking, the U.S. procurement system allows companies competing for U.S. government contracts broad rights to challenge contract awards, as well as the terms of solicitations. There are, however, restrictions...more

Bid Protest Minute: GAO Decision Clarifies SAM Registration Rule

On January 8, the Government Accountability Office (GAO) sustained a pre-award bid protest filed by Bass, Berry & Sims PLC (Bass Berry), which challenged the Federal Law Enforcement Training Centers’ (FLETC or the Agency)...more

Bid Protest Minute: COs Must Account for Corporate Restructuring When Assessing Qualifications

On November 13, the Government Accountability Office (GAO) sustained a protest by DecisionPoint Corporation concluding that when the Air Force determined EmeSec, a wholly owned subsidiary of DecisionPoint, was ineligible for...more

Welcome Clarity Regarding the Ability to Challenge Other Transaction Follow-On Production Awards  

We have addressed on this blog questions relating to jurisdiction at the GAO, Court of Federal Claims (CFC), and district courts to hear suits relating to awards using the government’s Other Transaction (OT) authority....more

Bid Protest Minute: Avoiding the Timeliness Trap

On February 14, the Government Accountability Office (GAO) dismissed a protest by Marathon Medical Corporation, an unsuccessful bidder, concluding that its protest was untimely. GAO reasoned that its strict timeliness...more

Bid Protest Minute: GAO’s Task Order Jurisdiction

On December 21, the Government Accountability Office (GAO) dismissed a protest by ELS, an unsuccessful bidder on a Department of Defense (DOD) task order opportunity, concluding that it did not have jurisdiction to consider...more

Bid Protest Minute: Proving an Organizational Conflict of Interest Exists

On December 20, 2023, the Government Accountability Office (GAO) denied an unsuccessful bidder’s protest, arguing, among other things, that the procurement was tainted by an appearance of impropriety after the agency...more

Bid Protest Minute: The High Bar to Proving Contract Officer Bias

On November 8, the Government Accountability Office (GAO) denied an unsuccessful bidder’s protest that asserted the Veteran Administration’s (VA) evaluation of Texas Waste Company’s past performance was unreasonable and...more

Bid Protest Minute: Recent Decision Imparts Lessons on Timeliness of Solicitation Challenges and Prejudice

On November 21, the Government Accountability Office (GAO) denied an unsuccessful bidder’s protest, arguing that the terms of a solicitation were biased and that the awardee failed to comply with a mandatory solicitation...more

GAO’s 2023 Bid Protest Report: More Than Meets the Eye

On October 26, the Government Accountability Office (GAO) sent its annual bid protest report to Congress, which reflected a dramatic increase in protests filed following four straight years of decline. The report provides...more

Bid Protest Win for AM General on Multi-Billion Dollar Contract

We represented AM General (AMG), an automotive manufacturer that builds military vehicles for government customers, including the Humvee, in a successful bid protest involving a $9.7 billion contract for the U.S. Army to...more

Records in Bid Protest Become More Complete – COFC Sanctions the Government for AR Omissions

In an opinion first publicly released on November 3, the Court of Federal Claims (COFC) took the somewhat usual, but not unheard of, step of sanctioning the government for mishandling the administrative record (AR) in a bid...more

The Black Hole of Protest Jurisdiction: Can I Challenge the Award of an “Other Transaction Agreement”?

While most federal procurements are conducted using the onerous regulations set forth in the Federal Acquisition Regulation (FAR) and agency supplements, agencies are increasingly relying on the more flexible, but...more

Selling Assets During a Protest?  Careful You Don’t Jump the Shark

In the past, we have cautioned readers about the potential impact of transactions on pending awards, particularly on the ability of a contractor to protest. A recent decision from the Court of Federal Claims (COFC) shows that...more

Bleak House Redux: Another Federal Circuit Win in Protracted Protest Litigation

As we previously discussed in a 2019 blog post, since 2018 Bass, Berry & Sims Government Contracts and Litigation attorneys have successfully defended B&O JV in a host of challenges to an 8(a) small business set-aside award...more

Bass, Berry & Sims Successfully Protests—And Then Defends—Client Award of a Task Order Before the GAO

After a successful challenge last year to the award of a service-disabled veteran-owned small business (SDVOSB) set aside task order for technology service desk operations by the U.S. Customs and Border Protection (CBP or the...more

The Importance of Being Timely: Protester Waives Protest Ground by Unduly Delaying Protest

By failing to object to solicitation terms before the close of bidding, a protester typically waives those objections in a post-award bid before the Court of Federal Claims (COFC). An exception exists, however, where a...more

Tis the Season (for Protests)!

The government fiscal year runs from October 1 to September 30, and at the end of each fiscal year federal agencies rush to award contracts and commit funding before that funding expires. As a result, our Government Contracts...more

How Do Mergers & Acquisitions Impact Pending Bids?

Given the continued high volume of mergers and acquisitions (M&A) transactions in the federal marketplace, buyers and sellers need to be aware of the developing body of case law at Government Accountability Office (GAO) and...more

34 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide