Trump’s Infrastructure Plan — Environmental Reviews, They Are a-Changin’

President Trump’s infrastructure plan includes a number of important proposals. My initial reaction is consistent with my view of many of the President’s initiatives – he gives regulatory reform a bad name. We do need to...more

Does NEPA Require Assessment of Downstream GHG Emissions Resulting From Gas Pipelines?

Last week, a divided panel of the D.C. Circuit Court of Appeals ruled that FERC violated NEPA in failing to assess downstream greenhouse gas emissions resulting from construction of the Sabal Trail pipeline, part of the...more

The Social Cost of Carbon: Not Too Speculative for NEPA

Earlier this week, the Judge Donald Malloy of the District Court for the District of Montana granted summary judgment to the Montana Environmental Information Center on several of its claims alleging that the Office of...more

Trump’s “2 for 1” EO: Can You Say “Arbitrary and Capricious”?

On June 5, 2017, on behalf of our client, the Union of Concerned Scientists, Foley Hoag filed an amicus brief in support of the plaintiffs in the case challenging President Trump’s Executive Order 13771, the so-called “2 for...more

Managing Water Releases From Dams to Protect Fish: A Tale of Good Legislation and Bad Engineering

Earlier this week, the 9th Circuit found that the Bureau of Reclamation had authority under 1955 legislation to order additional releases of water to the Trinity River from the Lewiston Dam beyond the amount designated in an...more

Trump’s Impact on Environmental Law? Let the Speculation Begin!

What will a Trump Presidency mean for environmental law? I’m not sure my crystal ball if better than anyone else’s, but here are a few quick thoughts...more

Back to the Fracking Drawing Board for BLM? Fracking’s Risks Are Too Obvious to Ignore

Last week, Judge Michael Fitzgerald granted summary judgment to the plaintiffs in a citizen suit alleging that BLM’s Environmental Impact Statement prepared to address whether to open certain lands in California to mineral...more

NEPA Does Not Require An Agency To Guarantee Project Compliance with Environmental Laws

In an interesting decision last week, the 9th Circuit Court of Appeals rejected challenges to BLM’s decision to issue a right-of-way permit for Tule Wind’s plan for a wind farm southeast of San Diego. It’s not exactly...more

If You Don’t Like Nukes, Petition Congress: The D.C. Circuit Affirms the NRC’s GEIR On Nuclear Waste Storage

On Friday, the D.C. Circuit Court of Appeals rejected challenges by several states and the NRDC to the Nuclear Regulatory Commission’s Generic Environmental Impact Statement analyzing the impacts of continued on-site storage...more

The Writing on the Wall Moves to the Federal Register: No 30-Year Take Permits

As we discussed last summer, the Judge Lucy Koh of the Northern District of California ruled that the Fish and Wildlife Service’s 30-year programmatic permit for incidental takes of bald and golden eagles from wind farms...more

No Short Cuts Allowed: The FWS Must Comply with NEPA Before Extending Programmatic Take Permits to 30 Years

Earlier this month, the Judge Lucy Koh set aside the Fish & Wildlife Service’s decision to extend its programmatic permit for bald and golden eagle takes from five to 30 years. The extension was sought by the wind industry...more

NEPA Review — Still the Land of Deference

Last week, District Judge Ralph Beistline allowed the summary judgment motion filed by the United States Forest Service, and dismissed citizen claims challenging the Forest Service decision to approve an logging project in an...more

Environmental Impact Analysis — The Impact of a Project on the Environment or the Impact of the Environment on a Project?

Traditionally, environmental impact analysis, under NEPA and state analogs, has focused on the impacts that a proposed project may have on the environment. In Massachusetts, the Executive Office of Energy and Environmental...more

The Federal Tail Should Not Wag the Non-Federal Dog: The Sixth Circuit Concludes that the Corps’ Review of Mountaintop Removal...

The Sixth Circuit Court of Appeals has ruled, in Kentuckians for the Commonwealth v. Army Corps of Engineers, that the scope of review by the Army Corps of Engineers of § 404 permit applications for fills related to...more

3/18/2014  /  Environmental Claims , Mining , NEPA

The Ninth Circuit Addresses NEPA’s Goldilocks Problem: How Many Alternatives Are Just Enough?

One of the critical elements of NEPA is that project proponents must assess the feasibility and impacts of not only the preferred alternative, but also a range of alternatives. However, there is a tension in NEPA, because it...more

BOEM Gives a Lesson on How Not To Survive NEPA Review

Last week, the Ninth Circuit Court of Appeals agreed with the plaintiffs that the Environmental Impact Statement issued by the Bureau of Ocean Energy Management to support oil and gas leasing in the Chukchi Sea was flawed. ...more

41 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide