Latest Posts › Federal Contractors

Share:

What Constitutes a Reasonable Period of Time Under the Suspension-of-Work Clause?

In Granite Construction Company, ASBCA No. 62281 (November 1, 2023), the Armed Services Board of Contract Appeals ("Board") addressed the issue of what constitutes a reasonable period of time to suspend work under the...more

Armed Services Board of Contract Appeals Addresses Sovereign Immunity in Context of COVID-Related Cost Claims

In JE Dunn Construction Company (ASBCA No. 62936 April 25, 2022) the Armed Services Board of Contract Appeals took up the issue of whether the sovereign acts doctrine barred a contractor's claim for additional costs arising...more

Court of Federal Claims Addresses Fraudulent Claim Pricing

"Men must turn square corners when they deal with the Government." So began the Court of Claims decision entitled Lodge Construction, Inc. v. United States, Nos. 13-499 and 13-800 (January 1, 2022), which the court described...more

Armed Services Board of Contract Appeals Addresses Sum Certain Requirement for Claims Submission

The Armed Services Board of Contract Appeals in ECC International Constructors, LLC (ASBCA No. 59643 November 9, 2021) issued a partial summary judgment order dismissing several of the contractor's claims for lack of a sum...more

Contractor Summary Judgment on Gov. Response to Pre-Bid Question

The Civilian Board of Contract Appeals in Wu & Associates granted the contractor's motion for partial summary judgment on entitlement to recover additional funds to strengthen flooring to move heavy equipment for an elevator...more

Contractor Obtains Summary Judgment on Entitlement Based on Government Response to Pre-Bid Question

The Civilian Board of Contract Appeals in Wu & Associates granted the contractor's motion for partial summary judgment on entitlement to recover additional funds to strengthen flooring to move heavy equipment for an elevator...more

ASBCA - Constructive Acceleration & Structural Steel Submittals

The Armed Services Board of Contract Appeals in September 2021 issued a partial summary judgment order dismissing a contractor's constructive acceleration claim asserting that the Government had not timely reviewed its steel...more

ASBCA Addresses Claim for Additional Costs Relating to Removal of Non-Specified Pipe

In Sauer, Inc. (September 29, 2021), the Armed Services Board of Contract Appeals discussed the limits of authority that a Government representative had to utilize substitute materials in lieu of materials specified in a task...more

ASBCA Exercises Jurisdiction Over Contractor Claim Despite Government's Allegations of Fraud

In Nauset Construction Corporation,1 the Armed Service Board of Contract Appeals once again addressed how Government allegations of fraud impact the Board's ability to hear a claim....more

ASBCA Addresses Contractor's Burden in Submitting "or Equal" Product

In Carothers Construction, Inc., the Armed Services Board of Contract Appeals discussed the contractor's burden in submitting an "or equal" product. The contract incorporated FAR 52.336-5, Material and Workmanship, which...more

Armed Services Board of Contract Appeals Addresses Notice Defense and Its Exceptions

In Harry Pepper and Associates, Inc., the Armed Services Board of Contract Appeals addressed three exceptions to the strict enforcement of claim notice requirements in the context of a Government motion for summary judgment...more

ASBCA Provides Limits on Application of Severin Doctrine

In JAAAT Technical Services, LLC, the Armed Services Board of Contract Appeals (ASBCA) addressed the breadth of application of the Severin doctrine, which restricts a prime contractor's ability to file claims on behalf of a...more

Civilian Board of Contract Appeals Addresses the Interplay Between ID/IQ Contracts and the Implied Duty of Good Faith

In Future Forest, LLC, CBCA 5863 (March 9, 2020), the Civilian Board of Contract Appeals discussed the relationship between a minimum delivery order, comments on what volume of deliveries the contractor could anticipate under...more

Court of Federal Claims Provides Guidance on Implied-in-Fact Contracts

In Panther Brands, LLC v. The United States, No. 16-1157C (December 17, 2019), the Court of Federal Claims addressed the elements of an implied-in-fact contract in the context of a motion for summary judgment dismissal of the...more

Civilian Board of Contract Appeals Decision Highlights Importance of Consistent Project Records

In AMEC Foster Wheeler Environmental & Infrastructure, Inc., CBCA 5168, 6298 (November 13, 2019), the Civilian Board of Contract Appeals rejected in large part a federal contractor’s claims due to inconsistencies between the...more

Court of Federal Claims Provides Guidance on Recovery of Unabsorbed Overhead and the Christian Doctrine

In Kudsk Construction Inc. v. The United States, No. 18-1032C (August 30, 2019), the Court of Federal Claims addressed damages in the context of a delayed notice to proceed and addressed the Christian doctrine in the context...more

ASBCA Provides Guidance on CENTCOM Default Termination Decision

In Watts Constructors, LLC, (June 24, 2019), the Armed Services Board of Contract Appeals (ASBCA) provided further guidance on its earlier decision ECC CENTCOM, 18-1 BCA 37,133. ...more

The Court of Federal Claims Provides Guidance on Factors for the Government to Consider in a Default Termination

A recent case from the Court of Federal Claims provides us instruction on the factors that the government should consider in determining whether to terminate a construction contract for default. This case provides a detailed...more

The Court of Federal Claims Provides Guidance on Differing Site Conditions and Superior Knowledge Claims

A recent case from the Court of Federal Claims provides us instruction on differing site conditions and superior knowledge claims. The case arose out of a maintenance dredging contract issued by the United States Army Corps...more

Buyer Beware—The Risks of Settling a Subcontractor Claim

A recent case from the Armed Services Board of Contract Appeals provides us with a reminder of what can happen to a prime contractor when it settles a subcontractor claim and then seeks to pass through the settlement amount...more

The Court of Federal Claims Provides Guidance on Cardinal and Constructive Change Law

A recent case from the Court of Federal Claims provides us with a useful summary of several legal principles applicable to constructive changes and cardinal changes. The case arose out of a contract to supply mail processing...more

The ASBCA Imposes Conditions on Raising Excusable Delay as an Affirmative Defense to Default Termination

A recent decision by the Armed Services Board of Contract Appeals underscores the importance of timely filing a certified claim for excusable delay, and the risks of failing to do so. In ECC CENTCOM Constructors, Inc....more

Lock ‘Em Up or Lose ‘Em — The Importance of Early Execution of Key Subcontracts

A recent decision by the Armed Services Board of Contract Appeals reminds us of the importance of obtaining commitments from your key subcontractors after award....more

The Importance of Modifications and Schedule Updates When Faced with a Termination for Default

A recent decision by the Armed Services Board of Contract Appeals reminds us of the significance of release language in a modification, this time in the context of a contractor seeking to overturn a termination for default of...more

Overturning a Termination for Cause

A recent decision by the Armed Services Board of Contract Appeals provides guidance on overturning a termination for cause of a supply contract. In AEY, Inc. (June 22, 2018), the ASBCA in large part overturned the...more

31 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide