Even if a contract does not have a force majeure clause, a party’s obligation to perform may still be discharged under the doctrine of impossibility. The doctrine of impossibility refers to situations when it is impossible for a party to a contract to perform. Florida courts are reluctant to excuse performance that is not impossible but merely inconvenient, profitless, and expensive. However, even if performance is impossible, a party may not be able to use the doctrine of impossibility as a defense to non-performance if the party:
- knew of the facts, at the time the contract was executed, that made performance impossible;
- assumed the risk of impossibility; or
- could have acted to prevent the event rendering performance impossible.
Ultimately, determining whether a party can successfully use the doctrine of impossibility as a defense is a factually intensive inquiry. The findings of Florida courts are too numerous to catalog due to the multiple of varied factual situations. Moreover, courts have used the doctrine of impossibility as a devise to allocate risk among the parties to a contract.
In allocating risk under the doctrine of impossibility, courts have analyzed the following factors, furthering the depth and scope of the factual inquiry:
- the degree of hardship imposed on a party;
- the foreseeability of the event making performance impossible; and
- the language of the contract in determining the allocation of the relevant risks.
The coronavirus and the indirect effects of the coronavirus – such as government orders and supply chain deficiencies – provide a multitude of factual situations that may give rise to a defense based on the doctrine of impossibility. An important factual inquiry may revolve around when the parties’ executed the contract. For example, China reported a cluster of cases of the coronavirus on January 7, 2020. Thus, if a party entered into a contract after January 7, 2020, a court may find that, at the time the contract was executed, a party assumed the risk or knew of the facts which led to performance being impossible.
The doctrine of impossibility as a defense to non-performance is fact specific and depends on the specific language of the contract, we encourage you to seek out a lawyer to analyze your agreement and the facts specific to your matter.