Pay Attention to the Fine Print! Court Enforces Broad Release in Change Order to Deny $25M Claim

A Texas court has rejected a pipeline contractor’s $25 million claim for additional costs based on broad release language include in an executed change order (see Wood Group, USA v. Targa NGL Pipeline Company, LLC, No....more

Liquidated Damages Disproportionate to Actual Damages Deemed Unenforceable

Construction contacts often include provisions that provide for pre-determined or “liquidated” damages in the event of a breach. Such provisions can provide certainty to the parties as to the consequences of a breach and can...more

Washington Court Affirms $150M Award for Victims of Seattle Crane Collapse

Earlier this month, the State of Washington Court of Appeals affirmed a $150 million jury verdict against subcontractors involved in the disassembly of a tower crane that collapsed in 2019. The collapse, which was caught on...more

Damages for Buyer’s Breach of Contract for the Sale of Real Property: Court Rejects Contractor’s Creative Damages Theory in...

Who said legal opinions have to be boring? Not Judge Terrence L. Michael of the U.S. Bankruptcy Court for the Northern District of Oklahoma, who last week issued a colorful opinion rejecting a home builder’s creative claim...more

Limitation of Liability in Extra Work Order Trumped by Subcontract

A federal court in Louisiana last week refused to enforce a limitation of liability provision included in an extra work order holding that it was trumped by the parties’ subcontract (see Planet Construction v. Gemini...more

Court Allows Expert Testimony Regarding Measured Mile Analysis Comparing Work on Different Projects

Loss of productivity damages are commonly estimated using a “measured mile” analysis, which compares unimpacted construction work to work which has been disrupted to determine the cost impact of the disruption. Such analyses...more

Preserve Your Claims by Preserving the Evidence

A recent case out of Washington serves as a good reminder to preserve evidence that may be relevant to pending or future litigation. That includes not only evidence in the form of documents and electronic information, but...more

No Written Notice of Delay? Big Problem! Court Sides with Contractor in Termination Dispute

Earlier this week we saw the court in Patriot Construction use the waiver doctrine to excuse a subcontractor’s failure to strictly comply with the documentation requirements of the contract. As a litigant in Illinois federal...more

33 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide