Randy Kinder Excavating, Inc. v. JA Manning Constr. Co. 2018 U.S. App. LEXIS 21878 (8th Cir. Aug. 7, 2018) -
This dispute arose from a contract to build a pumping station in Arkansas (the “Project”). In June of 2010, the...more
Woodrow Wilson Constr. LLC v. Orleans Par. Sch. Bd., 2018 La. App. LEXIS 762 (April 18, 2018) -
The Orleans Parish School Board (“OPSB”) awarded a prime contract to Woodrow Wilson Construction (“WWC”) for the construction...more
6/28/2018
/ Appeals ,
Construction Contracts ,
Construction Disputes ,
Construction Litigation ,
Construction Project ,
Delay Claims ,
Liquidated Damages ,
Mandamus Petitions ,
Ministerial Decisions ,
Prompt Payment ,
Public Entities
United States ex rel. Metro Mech., Inc. v. Triangle Constr. Co., 2018 U.S. Dist. LEXIS 1487 (S.D. Miss. Jan. 4, 2018) -
Triangle Construction Company, Inc. (“Triangle”) contracted with Mississippi Portfolio Partners III,...more
United States v. Int’l Fid. Ins. Co., No. 16-0472-WS-C, 2017 U.S. Dist. LEXIS 16791 (S.D. Ala. Feb. 7, 2017) -
This action arose out of a payment dispute between Bay South Limited, Inc. (“Bay South”) and Stephens...more