New York Supreme Court Granted Summary Judgment for Subcontractor Where Contractor Attempted to Utilize Contractual...

A.E. Rosen Elec. Co. v. Plank, LLC, No. 07862-7, 2019 BL 113951 (Sup. Ct. Mar. 01, 2019) - On March 1, 2019, the Supreme Court of New York, Albany County, granted a subcontractor’s motion for summary judgment on a payment...more

The Doctrine Of Arbitral Immunity Applied To An Arbitral Organization Absent A Showing Of Clear Lack Of Jurisdiction

Univ. of Iowa Bd. of Regents v. Am. Arbitration Ass’n, No. 17-0949, 2019 BL 7069 (Iowa Ct. App. Jan. 09, 2019) - Modern Piping, Inc. (“Modern Piping”) and the University of Iowa, Board of Regents, and State of Iowa...more

Concurrent Delay: Surety—Standing in the Shoes of Subcontractor—Is Barred From Asserting Defense of Concurrent Delay Because...

Fid. & Deposit Co. of Md. v. Travelers Cas. & Sur. Co. of Am., 2018 U.S. Dist. LEXIS 162265 (D. Nev., September 21, 2018) - Clark County School District (“CCSD”) hired Big Town Mechanical (“Big Town”) as general contractor...more

Claimant Is Not Required To Conduct An Investigation Into The Veracity Of The Representation To Prove Justifiable Reliance When...

Fisk Elec. Co. v. DQSI, L.L.C., 2018 U.S. App. LEXIS 17914 (5th Cir., June 29, 2018) - DQSI, L.L.C., (“DQSI”) a general contractor, was hired by the Army Corps of Engineers (“Corps”) for a pump station construction...more

The Completed and Accepted Doctrine: When the Majority Rule Becomes the Minority

The “Completed and Accepted Rule,” or the “Completed and Accepted Doctrine,” is a judicially created doctrine that is said to have originated in the United States with the 1919 Connecticut case Howard v. Redden, in which a...more

Contractor Who Failed To Challenge Arbitration Award Within Statutory Three Month Period Cannot Resurrect The Challenge As An...

St. George Fire Prot. Dist. No. 2 v. J. Reed Constructors, Inc. 2018, La. App. LEXIS 262 (February 20, 2018) - J. Reed Constructors, Inc. (“J. Reed”) and St. George Fire Protection District No. 2 (“St. George”) entered...more

Michigan Court Of Appeals Holds That Contractor Who Failed To Timely Seek A Time Extension Is Barred From Contesting Liquidated...

Abhe & Svboda, Inc. v. State of Michigan Department of Transportation, 2017 Mich. App. Lexis 1387 (August 29, 2017) - Contractor Abhe & Svboda, Inc. (“A&B”) entered into a contract with the Michigan Department of...more

7 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide