On November 17, 2023, the U.S. Court of Appeals of the District of Columbia Circuit (“D.C. Circuit”) denied petitions challenging FERC’s approval of recent changes to the PJM Interconnection, L.L.C.’s (“PJM”) Open Access...more
On July 7, 2023, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an opinion rejecting petitioner Hecate Energy Green County 3 LLC’s (“Hecate”) claim that the New York Independent System...more
On May 3, 2023, a divided FERC voted 3-1 to deny a widely-supported complaint by multiple utilities in the Southwest Power Pool (“SPP”) region arguing that the absence of the new 15% generation Planning Reserve Margin...more
On January 19, 2023, FERC established that a facility’s classification as transmission or distribution under criteria established in the Southwest Power Pool, Inc.’s (“SPP”) Open Access Transmission Tariff (“Tariff”) can be...more