Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) -
In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation...more
6/6/2019
/ Breach of Contract ,
Compensation Agreements ,
Construction Contracts ,
Construction Project ,
Contract Terms ,
Delay Claims ,
Delayed Compensation ,
Liquidated Damages ,
No Damage For Delay ,
NY Supreme Court ,
Prime Contractor ,
Quantum Meruit ,
Settlement ,
Subcontracts ,
Time-Barred Claims
James Talcott Construction, Inc. v. United States, No. 14-427 C, 2019 BL 72711, at *1 (Fed. Cl. Mar. 4, 2019) -
In May of 2010, the United States, acting through the Department of Defense (the “Government”) awarded a...more
Archon Construction Co. v. U.S. Shelter, LLC, 2017 Ill. App. LEXIS 197 (March 31, 2017) -
U.S. Shelter, LLC, a developer, undertook to develop a new residential subdivision in Elgin, Illinois. As part of that project,...more
Securiforce Int’l America, LLC v. United States, 125 Fed. Cl. 749 (March 21, 2016) -
Plaintiff Securiforce International America, LLC (“Securiforce”) was awarded a contract by the Defense Logistics Agency Energy (“DLA...more
American Towers LLC v. BPI, Inc., 2014 U.S. Dist. LEXIS 106724 (E.D. Ky. Aug. 4, 2014) -
American Towers LLC (“American Towers”), which operates wireless and broadcast communications towers, undertook a project to...more