On April 29, 2025, FERC partially granted rehearing in the case of Cometa Energia, S.A. de C.V. (“Saavi”) against the California Independent System Operator Corporation (“CAISO”), finding a provision of CAISO’s Business...more
5/8/2025
/ CAISO ,
California ,
Contract Terms ,
Energy Policy ,
Energy Projects ,
Enforcement Actions ,
FERC ,
Government Agencies ,
Infrastructure ,
Petition For Rehearing ,
Regulatory Authority ,
Rulemaking Process ,
Service Professionals ,
Tariffs ,
Utility Rates
On March 20, 2025, FERC denied Ponderosa Power, LLC’s (“Ponderosa”) complaint alleging that NorthWestern Corporation’s (“NorthWestern”) application of its large generator interconnection procedures (“LGIP”) was unjust and...more
On February 10, 2025, Pluvia LLC (“Pluvia”) filed a petition for a declaratory order, asking FERC to clarify its jurisdiction to issue a preliminary permit for the construction, operation, and maintenance of transmission...more
On January 14, 2025, the U.S. Court of Appeals for the D.C. Circuit (“D.C. Circuit”) held that FERC complied with the National Environmental Policy Act (“NEPA”) in approving the surrender of a hydroelectric project license....more
1/23/2025
/ Appeals ,
Dams ,
Energy Projects ,
Environmental Impact Statements ,
Environmental Litigation ,
Environmental Policies ,
FERC ,
Hydropower ,
Municipalities ,
NEPA ,
Regulatory Requirements ,
Scope of License
On December 16, 2024, the Federal Energy Regulatory Commission (“FERC”) directed American Efficient, LLC, its subsidiaries, and corporate parents (collectively, “American Efficient”) to show cause why American Efficient...more
1/13/2025
/ Capacity Market ,
Civil Monetary Penalty ,
Clean Energy ,
Energy Projects ,
Enforcement Actions ,
FERC ,
Market Manipulation ,
MISO ,
Regulatory Agenda ,
Renewable Energy ,
RTO
On September 10 and 11, 2024, FERC staff held a two-day workshop at its headquarters in Washington, DC on opportunities to further refine the generator interconnection queue process. Panelists and FERC staff discussed...more
On July 16, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) found that FERC failed to adequately consider a liquefied natural gas (“LNG”) project’s greenhouse gas (“GHG”)...more
At the February 15, 2024, FERC open meeting and in four orders issued the same day, FERC established a new policy governing its issuance of preliminary permits under section 4(f) of the Federal Power Act (“FPA”), pursuant to...more
On January 18, 2024, FERC granted a certificate of public convenience and necessity to Transcontinental Gas Pipe Line Company, LLC (“Transco”) to construct and operate the Texas to Louisiana Energy Pathway Project (“Texas to...more
On December 12, 2023, FERC staff offered information and recommendations to help registered entities (i.e., users, owners, and operators of the bulk electric system) improve their compliance with mandatory Critical...more
12/29/2023
/ Audits ,
Critical Infrastructure Sectors ,
Cybersecurity ,
Electricity ,
Energy Market ,
Energy Projects ,
FERC ,
Homeland Security Cybersecurity & Infrastructure Security Agency (CISA) ,
NERC ,
Renewable Energy ,
Risk Management
On November 16, 2023, FERC granted Virginia Electric and Power Company d/b/a Dominion Energy Virginia’s (“Dominion”) petition requesting the Commission declare that Dominion’s planned liquefied natural gas (“LNG”) production,...more
11/27/2023
/ Electricity ,
Energy Market ,
Energy Projects ,
Energy Reform ,
Environmental Policies ,
FERC ,
Infrastructure ,
Liquid Natural Gas ,
Natural Gas ,
Natural Gas Act ,
Oil & Gas ,
Renewable Fuel
On July 28, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023 (Order No. 2023 or Final Rule), which updates the procedures for interconnecting large generating facilities (20MW and above)...more
8/4/2023
/ Electric Generation Suppliers ,
Energy Market ,
Energy Policy ,
Energy Projects ,
Energy Reform ,
Energy Sector ,
Energy Storage ,
FERC ,
Final Rules ,
Infrastructure ,
Interconnections ,
ISO/RTO ,
Notice of Proposed Rulemaking (NOPR) ,
Renewable Energy ,
SGIP
On December 20, 2022, the U.S. Court of Appeals for the D.C. Circuit (“D.C. Circuit”) in Waterkeepers Chesapeake, et al. v. FERC vacated a FERC order approving the relicensing of the Conowingo Dam because FERC did not have...more
On October 21, 2022, the U.S. Department of Energy (“DOE”) announced three new funding opportunities to support research and development projects for hydropower infrastructure in the United States. The funding totals $28...more