Delay Claims Damages

Burr & Forman

Pre-Bid Documents and Estimates Can’t Be Hidden Behind the Curtain in Disputed Delay Claims

Burr & Forman on

In WDF, Inc. v. City of New York,  No. 652478 (N.Y. Sup.) (Mar. 12, 2021), the contractor filed suit to recover damages from the City on numerous combined waste water treatment projects.  The contractor claimed that the City...more

Burr & Forman

No Longer in the Dark: A Primer on the Distinction between Delay and Disruption Damages in a Construction Dispute

Burr & Forman on

If you are left in the dark about something, you don’t have the information you should have to make an informed decision. Delay claims on a construction can be confusing, especially when you think about the delay to the work...more

Troutman Pepper

Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

Troutman Pepper on

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more

White & Case LLP

Termination & Liquidated Damages: Less Clear than Ever

White & Case LLP on

The Court of Appeal of England & Wales considered, in respect of a delayed software project, whether a liquidated damages provision survived termination of the contract....more

Nossaman LLP

Regulatory Taking May Result From Improper CEQA Determination? Stay Tuned

Nossaman LLP on

A few months ago, we reported on a Court of Appeal decision, Bottini v. City of San Diego, where the Court held that delays resulting from a governmental agency’s improper denial of a permit application for a new development...more

Troutman Pepper

Federal Court Clarifies When Idle Equipment Costs Are Recoverable Under the Miller Act

Troutman Pepper on

United States ex rel. Am. Civ. Constr., LLC v. Hirani Eng’g & Land Surveying, P.C., 2018 U.S. Dist. LEXIS 200829 (D.D.C. Nov 28, 2018). The case involved the construction of a levee wall on the National Mall in Washington,...more

Troutman Pepper

Ohio Appeals Court Holds That Contractor Who Seeks Application of HOOP Formula to Calculate Home Office Overhead Need Not Prove...

Troutman Pepper on

Wood Elec., Inc. v. Ohio Facilities Constr. Comm’n, 10th Dist. Franklin No. 16AP-643, 2017-Ohio-2743, 2017 Ohio App. Lexis 1745 (May 9, 2017) - The Ohio Facilities Construction Commission (“OFCC”), together with a school...more

Troutman Pepper

Court of Appeals of Michigan Holds Contractor Cannot Recover Eichleay Damages from Supplier Absent Contractual Right and Proof...

Troutman Pepper on

ITT Water & Wastewater USA, Inc. v. L. D’Agostini & Sons, Inc., 2016 Mich. App. LEXIS 579 (March 17, 2016) - This action arises out of a contract dispute between plaintiff, ITT Water & Wastewater USA, Inc. (“ITT”), and...more

Snell & Wilmer

Delay and Disruption Claims: Big Impacts on Your Bottom Line

Snell & Wilmer on

“Time is money” in construction. Owners, design professionals and contractors use time to calculate the impact of lost performance. Yet delay and disruption can be commonplace in construction projects. The reasons for the...more

Snell & Wilmer

Under Construction - March 2015

Snell & Wilmer on

Welcome to the spring edition of our Under Construction newsletter. There have been some interesting legal changes that have taken place recently with the potential to significantly impact the construction industry. ...more

Snell & Wilmer

Effective Use of CPM Scheduling

Snell & Wilmer on

In a relatively recent case, Metcalf Construction Co. v. U.S., 107 Fed. Cl. 786 (2012), the U.S. Court of Federal Claims once again looked to the critical path method (CPM) in determining the allocation of damages in a...more

Pillsbury Winthrop Shaw Pittman LLP

NY State Appellate Court Sides with Airlines, Dismisses Tarmac Delay-Related Claims

The Second Department in Biscone v. JetBlue Airways Corporation recently dismissed airline passengers’ tort claims against an airline based on the failure to provide food, water and facilities during an 11-hour tarmac delay,...more

12 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide