FERC's Co-Location Conundrum: Balancing Grid Reliability with Data Center Development as PJM's Tariff Faces Scrutiny

Womble Bond Dickinson on

FERC's Order Signals Transformative Change While Navigating Jurisdictional Limits: While FERC recognizes the urgent need to address co-location arrangements (particularly given the AI/data center boom), the intricate...more

Troutman Pepper Locke

FERC Institutes Show Cause Proceeding on Co-Location Issues in PJM

Troutman Pepper Locke on

On February 20, 2025, FERC found that the PJM Interconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“OATT”) appears to be unjust and unreasonable because it does not address with clarity or consistency the rates,...more

Dorsey & Whitney LLP

Energy Law: Month in Review - June 2024

Dorsey & Whitney LLP on

Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. ...more

Troutman Pepper Locke

PJM Files Capacity Market Overhaul for Resource Adequacy and Grid Reliability

Troutman Pepper Locke on

On October 13, 2023, PJM Interconnection, L.L.C. (“PJM”) submitted two filings with FERC proposing revisions to its Open Access Transmission Tariff (“Tariff”) and its “Reliability Assurance Agreement” (“RAA”) designed to...more

A&O Shearman

PJM Makes MOPR Compliance Filing and Proposes Timing for Delayed RPM Auction

A&O Shearman on

Ohio Commission Requests Comment Delay for COVID-19 Emergency On March 18, PJM Interconnection, L.L.C (PJM) filed with the Federal Energy Regulatory Commission (FERC) proposed changes to its Tariff in compliance with FERC’s...more

5 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide