News & Analysis as of

PJM Transmission Grid Federal Power Act

Womble Bond Dickinson

FERC's Co-Location Conundrum: Balancing Grid Reliability with Data Center Development as PJM's Tariff Faces Scrutiny

Womble Bond Dickinson on

FERC's Order Signals Transformative Change While Navigating Jurisdictional Limits: While FERC recognizes the urgent need to address co-location arrangements (particularly given the AI/data center boom), the intricate...more

Troutman Pepper Locke

FERC Institutes Show Cause Proceeding on Co-Location Issues in PJM

Troutman Pepper Locke on

On February 20, 2025, FERC found that the PJM Interconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“OATT”) appears to be unjust and unreasonable because it does not address with clarity or consistency the rates,...more

Bracewell LLP

Federal Register Notice on November 26, 2024, Establishes Date for Compliance Filings for FERC Elimination of Generator...

Bracewell LLP on

On October 17, 2024, the Federal Energy Regulatory Commission (“FERC”) issued Order No. 904, finding on a generic basis that allowing transmission providers to charge customers for a generating facility’s provision of...more

Troutman Pepper Locke

FERC Directs PJM to Use a Historical Simulation Model with a 99% Confidence Level for its FTR Credit Requirement

Troutman Pepper Locke on

On September 21, 2023, the Commission approved, in part, PJM Interconnection L.L.C.’s (“PJM”) proposed tariff revisions regarding the calculation of the Financial Transmission Right (“FTR”) credit requirement (“September...more

4 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"