Termination for Default Construction Project

Burr & Forman

Contracting Offficer’s Belief That Contractor Could Not Meet Schedule Requirements Insufficient to Support Default Termination

Burr & Forman on

There is objection evidence.  There is subjective evidence.  And sometimes, it is a combination of both  A case cannot go much worse when a court’s opinion starts with the following: “This case concerns a contract in which a...more

Bradley Arant Boult Cummings LLP

Casting the First Stone: Contractors Considering Default Termination Should Examine Which Party Committed First Material Breach -...

During a construction project, circumstances may arise that lead a general contractor to consider termination of a subcontractor’s right to proceed under the subcontract. The Randy Kinder Excavating v. J.A. Manning...more

Cohen Seglias Pallas Greenhall & Furman PC

Termination for Default Held Improper

A contractor performed a project involving the construction of stone dike extensions and other work at four sites on the Mississippi River. Nelson, Inc. ASBCA No. 57201 (December 15, 2015). One of the issues was whether the...more

3 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide