US Army Corps of Engineers Delays Construction Litigation

Bradley Arant Boult Cummings LLP

Put Up or Shut Up: Court Grants Summary Judgment for Steel Sub in Price Escalation Clause Dispute

An Illinois federal court ruled in favor of steel subcontractor Nucor in its contract dispute with Direct Steel. The project involved the construction of pre-engineering metal buildings for the Army Corps of Engineers. The...more

Troutman Pepper Locke

General Contractor’s Unjustified Threats To Assess Delay Damages Against Subcontractor Are A Material Breach Of Contract

Troutman Pepper Locke on

Randy Kinder Excavating, Inc. v. JA Manning Constr. Co. 2018 U.S. App. LEXIS 21878 (8th Cir. Aug. 7, 2018) - This dispute arose from a contract to build a pumping station in Arkansas (the “Project”). In June of 2010, the...more

2 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide