Le 21 février 2024, la Cour d’appel de l’Alberta (la « CAA ») a rendu sa décision dans l’affaire Paramount Resources Ltd. v. Grey Owl Engineering Ltd., laquelle constitue la plus récente décision sur l’application possible de...more
The Alberta Court of Appeal issued its decision in Paramount Resources Ltd. v. Grey Owl Engineering Ltd. on February 21, 2024. This decision represents the latest pronouncement on the potential application of section 218 of...more
Section 218 of Alberta's Environmental Protection and Enhancement Act, RSA 2000, c E-12 (EPEA) is not available to extend the limitation period for a party liable for remediation costs to make claims against other alleged...more
Movants must clear high hurdle once parties reach settlement in principle. On March 9, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order in Maritimes & Northeast Pipeline, LLC (Maritimes...more