Practical Training for Project Managers & Supervisors Two-Part Webinar Series: Part Two
Construction Delays in the Time of Coronavirus: A Legal Perspective
In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more
The Second Circuit Court of Appeals recently applied a no-damages-for-delay provision to affirm the dismissal of a demolition contractor’s breach of contract claims. The project involved reconstructing and raising the Bayonne...more
My commute home last night took longer than usual. It was not excessive traffic, an accident, or a stalled car. Rather, the cause of my delayed commute was a turtle: one single turtle crossing the road, holding up about 30...more
A common clause in many New York construction contracts is a “no-damage-for-delay” exculpatory provision, providing, in sum, that delay damages are not compensable and that if you are delayed, then you are only entitled to a...more
In this webinar series, George Pallas and Kathleen Morley present practical tips and training to project managers and supervisors regarding best practices in project management. Using real-life examples, George and Kathleen...more
In this webinar series, George Pallas and Kathleen Morley will present practical tips and training to project managers and supervisors regarding best practices in project management. Using real-life examples, George and...more
It happens all the time! The owner-contractor agreement contains a “no damages for delay” clause; a clause requiring that all changes be in writing before work is performed; and a clause requiring partial lien waivers and...more
Main contractors often make claims against subcontractors for liquidated damages for delay. A question that sometimes arises is whether liquidated damages may be claimed by a main contractor where there is no corresponding...more
“Time is money.” There are few places where that phrase is truer than in construction, and unfortunately, that truth has been highlighted by the coronavirus pandemic shutting down construction throughout Pennsylvania....more
Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more
In a recent case, the Federal Court of Australia confirmed that it will enforce a "no damage for delay" clause, including when delay occurs as a result of a variation under a contract....more
Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) - In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation...more
Dear YouDig? We decided to expand our plant to meet the needs of a major international customer. This is a game changer for us. We MUST have the expansion completed within 10 months in order to meet the client’s demands or...more
Hagen Constr. Inc. v. Whiting-Turner Contracting Co., No. JKB-18-1201, 2019 BL 36862 (D. Md. Feb. 04, 2019) - This case arises out of the construction of a pediatric outpatient center in southern New Jersey. Plaintiff...more
Well-drafted, legally-enforceable agreements are key to any construction company’s risk management strategy. This is especially true for subcontracts, which serve as a contractor’s critical tool to coordinate a successful...more
• The Court of Appeal has held that a clause denying an extension of time to a Contractor if there is concurrent delay is enforceable and is not contrary to the so-called “prevention principle.” • The Court of Appeal...more
When we think of delays on a construction project, the first inquiry is to identify the turtle—the one party holding up progress or causing the delay. Many times, the parties’ contract will dictate whether the contractor can...more
Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018) - Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training...more
For years, general contractors and trade contractors have faced very strict “no damages for delay” clauses on New York State construction projects. The tides are changing. If signed into law, S. R. 06686, Reg. Sess....more
In construction contracts, “active interference” is a recognized exception to the enforcement of what is known as a “no damages for delay” clause. This type of provision seeks to preclude any increased costs associated with...more
Letter from the Editor - Welcome to the final 2017 edition of our Under Construction newsletter. It is hard to believe that 2018 is right around the corner! In this issue, we highlight several topics affecting the...more
No-damages-for-delay clauses are commonly found in construction contracts and, with certain exceptions, are generally recognized as valid and enforceable. The exact language can vary, but the typical clause provides that the...more
Central Ceilings, Inc. v. Suffolk Constr. Co., Inc., 2017 Mass App. Lexis 36 (March 29, 2017). The Massachusetts State College Building Authority contracted with Suffolk Construction Company (“Suffolk”) to serve as the...more
Port of Houston Auth. of Harris Cnty. v. Zachry Constr. Corp., 2016 Tex. App. LEXIS 13306 (Tex. App. Houston 14th Dist. Dec. 15, 2016) - This contract dispute dates back to 2004, when the Port of Houston Authority...more
Most commercial construction contracts contain a “No Damage For Delay” Clause and most contractors mistakenly believe they are Kings X for any potential claims related to delay caused by an owner or original contractor. ...more