No Damage For Delay General Contractors

Cohen Seglias Pallas Greenhall & Furman PC

New York’s Strong Enforcement of No-Damages-for-Delay Provisions

A common clause in many New York construction contracts is a “no-damage-for-delay” exculpatory provision, providing, in sum, that delay damages are not compensable and that if you are delayed, then you are only entitled to a...more

Cohen Seglias Pallas Greenhall & Furman PC

Practical Training for Project Managers & Supervisors Two-Part Webinar Series: Part Two

In this webinar series, George Pallas and Kathleen Morley present practical tips and training to project managers and supervisors regarding best practices in project management. Using real-life examples, George and Kathleen...more

Cohen Seglias Pallas Greenhall & Furman PC

[Webinar] Practical Training for Project Managers & Supervisors: Part Two: Important Contract Provisions, Claims Preservation, and...

In this webinar series, George Pallas and Kathleen Morley will present practical tips and training to project managers and supervisors regarding best practices in project management. Using real-life examples, George and...more

White & Case LLP

Claims For Liquidated Damages Against Subcontractors

White & Case LLP on

Main contractors often make claims against subcontractors for liquidated damages for delay. A question that sometimes arises is whether liquidated damages may be claimed by a main contractor where there is no corresponding...more

Cohen Seglias Pallas Greenhall & Furman PC

Construction Delays in the Time of Coronavirus: A Legal Perspective

“Time is money.” There are few places where that phrase is truer than in construction, and unfortunately, that truth has been highlighted by the coronavirus pandemic shutting down construction throughout Pennsylvania....more

White & Case LLP

Construction contracts: "No damage for delay" clause enforced

White & Case LLP on

In a recent case, the Federal Court of Australia confirmed that it will enforce a "no damage for delay" clause, including when delay occurs as a result of a variation under a contract....more

Bradley Arant Boult Cummings LLP

New York Courts Continue to Uphold Enforceability of No Damages for Delay Clauses - Construction and Procurement Law News, Q2 2019

A New York trial court recently upheld the enforceability of a no-damages-for-delay clause in a contract between a general contractor and its subcontractor. In Hailey Insulation Corp., v. WDF, Inc., the subcontractor...more

Bradley Arant Boult Cummings LLP

A Dangerous Myth: That a Great Subcontract Will Prevent Claims on a Poorly-Executed Project - Construction and Procurement Law...

Well-drafted, legally-enforceable agreements are key to any construction company’s risk management strategy. This is especially true for subcontracts, which serve as a contractor’s critical tool to coordinate a successful...more

Troutman Pepper

General Contractor’s Unjustified Threats To Assess Delay Damages Against Subcontractor Are A Material Breach Of Contract

Troutman Pepper on

Randy Kinder Excavating, Inc. v. JA Manning Constr. Co. 2018 U.S. App. LEXIS 21878 (8th Cir. Aug. 7, 2018) - This dispute arose from a contract to build a pumping station in Arkansas (the “Project”). In June of 2010, the...more

Burr & Forman

Slow as a Turtle? “No Damages For Delay” Clause Inapplicable to Contractor’s Claim Against Architect

Burr & Forman on

When we think of delays on a construction project, the first inquiry is to identify the turtle—the one party holding up progress or causing the delay. Many times, the parties’ contract will dictate whether the contractor can...more

Troutman Pepper

Federal Court in California Holds That Subcontractor May Proceed With Claim for Delay Damages, Despite No-Damage-For-Delay Clause,...

Troutman Pepper on

Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018) - Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training...more

Troutman Pepper

Massachusetts Appellate Court Holds That No-Damages-for-Delay Clause Does Not Bar Claim for Schedule Compression and Affirms Award...

Troutman Pepper on

Central Ceilings, Inc. v. Suffolk Constr. Co., Inc., 2017 Mass App. Lexis 36 (March 29, 2017). The Massachusetts State College Building Authority contracted with Suffolk Construction Company (“Suffolk”) to serve as the...more

Gray Reed

How to Circumvent “No Damages for Delay” Clauses

Gray Reed on

Most commercial construction contracts contain a “No Damage For Delay” Clause and most contractors mistakenly believe they are Kings X for any potential claims related to delay caused by an owner or original contractor. ...more

Burr & Forman

Subcontractor’s Failure to Strictly Comply With Notice Provision Costs $200,000

Burr & Forman on

Whether you are an owner, contractor, subcontractor or supplier, you will want to read the rest of this post since it illustrates precisely what all those attorneys have been telling you for years: “Please, please, please...more

Burr & Forman

Can Active Interference by Owner Invalidate A No Damages for Delay Clause? Sometimes.

Burr & Forman on

In C and H Electric, Inc. v. Town of Bethel, 312 Conn. 843 (2014), the Connecticut Supreme Court held that a Contractor’s claims against a Town for delay damages could not overcome the “no damages for delay” clause because...more

Robinson & Cole LLP

Federal Court Determines that General Contractor’s Unreasonable Exercise of its Broad Discretion over Scheduling and Sequencing of...

Robinson & Cole LLP on

In a recent decision, Elec. Contractors, Inc. v. Fid. & Deposit Co. of Maryland, No. 3:13-CV-00514 MPS, 2015 WL 1444481 (D. Conn. Mar. 30, 2015), the United States District Court for the District of Connecticut dismissed on...more

Bradley Arant Boult Cummings LLP

No Damages for Delay Exceptions: Active Interference?

While a contractor generally has a right to a time extension and damages stemming from a delay caused by the owner, the owner (or general contractor if the harmed party is a subcontractor) may be able to assert several...more

Dorsey & Whitney LLP

North Dakota Supreme Court Establishes Defense to “No Damage for Delay” Clause

Dorsey & Whitney LLP on

In June 2014, the North Dakota Supreme Court issued its decision in C&C Plumbing & Heating, LLP v. Williams County et al, No. 20130297. The Court articulated a new defense to the application of a “no damage for delay” clause....more

Ogletree, Deakins, Nash, Smoak & Stewart,...

Subcontractor Loses Delay Claim for Delays Occurring Before Execution of Subcontract

Both an Illinois circuit and appellate court had little sympathy for a subcontractor that suffered significant delays before executing a subcontract, which failed to allow for compensation for the prior delays. Asset Recovery...more

19 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide