In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more
A common clause in many New York construction contracts is a “no-damage-for-delay” exculpatory provision, providing, in sum, that delay damages are not compensable and that if you are delayed, then you are only entitled to a...more
Main contractors often make claims against subcontractors for liquidated damages for delay. A question that sometimes arises is whether liquidated damages may be claimed by a main contractor where there is no corresponding...more
A New York trial court recently upheld the enforceability of a no-damages-for-delay clause in a contract between a general contractor and its subcontractor. In Hailey Insulation Corp., v. WDF, Inc., the subcontractor...more
Dear YouDig? We decided to expand our plant to meet the needs of a major international customer. This is a game changer for us. We MUST have the expansion completed within 10 months in order to meet the client’s demands or...more
Well-drafted, legally-enforceable agreements are key to any construction company’s risk management strategy. This is especially true for subcontracts, which serve as a contractor’s critical tool to coordinate a successful...more
Randy Kinder Excavating, Inc. v. JA Manning Constr. Co. 2018 U.S. App. LEXIS 21878 (8th Cir. Aug. 7, 2018) - This dispute arose from a contract to build a pumping station in Arkansas (the “Project”). In June of 2010, the...more
Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018) - Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training...more
Whether you are an owner, contractor, subcontractor or supplier, you will want to read the rest of this post since it illustrates precisely what all those attorneys have been telling you for years: “Please, please, please...more
This is the first post in the four-part series “Limitations of liability—The Elephant in the Room.” One or more of the following scenarios takes place in my office virtually every day...more
John Spearly Constr., Inc. v. Penns Valley Area Sch. Dist., 2015 Pa. Commw. LEXIS 337 (Pa. Commw. Ct. July 24, 2015) - This action arose out of the construction of a biomass boiler system for the Penns Valley Area School...more
“No damages for delay” clauses: “No damages for delay” clauses allocate the risks of project delays and disruptions between the owner and contractor. Oftentimes, these clauses preclude a contractor from recovering...more
In a recent decision, Elec. Contractors, Inc. v. Fid. & Deposit Co. of Maryland, No. 3:13-CV-00514 MPS, 2015 WL 1444481 (D. Conn. Mar. 30, 2015), the United States District Court for the District of Connecticut dismissed on...more
While a contractor generally has a right to a time extension and damages stemming from a delay caused by the owner, the owner (or general contractor if the harmed party is a subcontractor) may be able to assert several...more
C&H Electric, Inc. v. Town of Bethel, 312 Conn. 843, 2014 Conn. LEXIS 263 (Aug. 5, 2014) - This dispute arose out of a project to renovate and build an addition at a high school in the Town of Bethel, Connecticut. The...more
According to the New York City Building Congress, Manhattan is poised to add roughly nine million square feet of new office space to its inventory between 2013 and 2015. If realized, this would be the highest volume of new...more
Contractor and subcontractor claims seeking relief—time and often money—for impacts due to delay, acceleration, disruption and loss of productivity and/or efficiency are common, as are disputes arising from such claims that...more
Both an Illinois circuit and appellate court had little sympathy for a subcontractor that suffered significant delays before executing a subcontract, which failed to allow for compensation for the prior delays. Asset Recovery...more