Subcontractors No Damage For Delay

Robinson+Cole Construction Law Zone

Second Circuit Affirms Win for General Contractor on No Damages for Delay Provision

In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more

Cohen Seglias Pallas Greenhall & Furman PC

New York’s Strong Enforcement of No-Damages-for-Delay Provisions

A common clause in many New York construction contracts is a “no-damage-for-delay” exculpatory provision, providing, in sum, that delay damages are not compensable and that if you are delayed, then you are only entitled to a...more

White & Case LLP

Claims For Liquidated Damages Against Subcontractors

White & Case LLP on

Main contractors often make claims against subcontractors for liquidated damages for delay. A question that sometimes arises is whether liquidated damages may be claimed by a main contractor where there is no corresponding...more

Bradley Arant Boult Cummings LLP

New York Courts Continue to Uphold Enforceability of No Damages for Delay Clauses - Construction and Procurement Law News, Q2 2019

A New York trial court recently upheld the enforceability of a no-damages-for-delay clause in a contract between a general contractor and its subcontractor. In Hailey Insulation Corp., v. WDF, Inc., the subcontractor...more

Buckingham, Doolittle & Burroughs, LLC

Dear YouDig? Must be done on time? Don't get burned!

Dear YouDig? We decided to expand our plant to meet the needs of a major international customer. This is a game changer for us. We MUST have the expansion completed within 10 months in order to meet the client’s demands or...more

Bradley Arant Boult Cummings LLP

A Dangerous Myth: That a Great Subcontract Will Prevent Claims on a Poorly-Executed Project - Construction and Procurement Law...

Well-drafted, legally-enforceable agreements are key to any construction company’s risk management strategy. This is especially true for subcontracts, which serve as a contractor’s critical tool to coordinate a successful...more

Troutman Pepper

General Contractor’s Unjustified Threats To Assess Delay Damages Against Subcontractor Are A Material Breach Of Contract

Troutman Pepper on

Randy Kinder Excavating, Inc. v. JA Manning Constr. Co. 2018 U.S. App. LEXIS 21878 (8th Cir. Aug. 7, 2018) - This dispute arose from a contract to build a pumping station in Arkansas (the “Project”). In June of 2010, the...more

Troutman Pepper

Federal Court in California Holds That Subcontractor May Proceed With Claim for Delay Damages, Despite No-Damage-For-Delay Clause,...

Troutman Pepper on

Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018) - Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training...more

Burr & Forman

Subcontractor’s Failure to Strictly Comply With Notice Provision Costs $200,000

Burr & Forman on

Whether you are an owner, contractor, subcontractor or supplier, you will want to read the rest of this post since it illustrates precisely what all those attorneys have been telling you for years: “Please, please, please...more

Robinson+Cole Construction Law Zone

Limitations of Liability – The Elephant in the Room

This is the first post in the four-part series “Limitations of liability—The Elephant in the Room.” One or more of the following scenarios takes place in my office virtually every day...more

Troutman Pepper

Pennsylvania Commonwealth Court Explains and Applies Active Interference Exception to No Damage for Delay Clause

Troutman Pepper on

John Spearly Constr., Inc. v. Penns Valley Area Sch. Dist., 2015 Pa. Commw. LEXIS 337 (Pa. Commw. Ct. July 24, 2015) - This action arose out of the construction of a biomass boiler system for the Penns Valley Area School...more

Robinson+Cole Construction Law Zone

What are the three most important risk-shifting provisions contractors and subcontractors should be concerned about?

“No damages for delay” clauses: “No damages for delay” clauses allocate the risks of project delays and disruptions between the owner and contractor. Oftentimes, these clauses preclude a contractor from recovering...more

Robinson & Cole LLP

Federal Court Determines that General Contractor’s Unreasonable Exercise of its Broad Discretion over Scheduling and Sequencing of...

Robinson & Cole LLP on

In a recent decision, Elec. Contractors, Inc. v. Fid. & Deposit Co. of Maryland, No. 3:13-CV-00514 MPS, 2015 WL 1444481 (D. Conn. Mar. 30, 2015), the United States District Court for the District of Connecticut dismissed on...more

Bradley Arant Boult Cummings LLP

No Damages for Delay Exceptions: Active Interference?

While a contractor generally has a right to a time extension and damages stemming from a delay caused by the owner, the owner (or general contractor if the harmed party is a subcontractor) may be able to assert several...more

Troutman Pepper

Connecticut Supreme Court Construes “Active Interference” Exception to “No-Damage-for-Delay” Clause

Troutman Pepper on

C&H Electric, Inc. v. Town of Bethel, 312 Conn. 843, 2014 Conn. LEXIS 263 (Aug. 5, 2014) - This dispute arose out of a project to renovate and build an addition at a high school in the Town of Bethel, Connecticut. The...more

Holland & Knight LLP

The Legal and Financial Consequences of Moving to a More Contractor Friendly No-Damage-For-Delay Cause

Holland & Knight LLP on

According to the New York City Building Congress, Manhattan is poised to add roughly nine million square feet of new office space to its inventory between 2013 and 2015. If realized, this would be the highest volume of new...more

Snell & Wilmer

Under Construction - March 2013: Tips for Presenting, Analyzing and Resolving Delay and Impact Claims

Snell & Wilmer on

Contractor and subcontractor claims seeking relief—time and often money—for impacts due to delay, acceleration, disruption and loss of productivity and/or efficiency are common, as are disputes arising from such claims that...more

Ogletree, Deakins, Nash, Smoak & Stewart,...

Subcontractor Loses Delay Claim for Delays Occurring Before Execution of Subcontract

Both an Illinois circuit and appellate court had little sympathy for a subcontractor that suffered significant delays before executing a subcontract, which failed to allow for compensation for the prior delays. Asset Recovery...more

18 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide