Contract Terms Construction Contracts Breach of Contract

BCLP

Does “Back to Back” Mean “Pay When Paid” in Construction Contracts?

BCLP on

In Sze Fung Engineering Limited v Trevi Construction Company Limited [2025] HKCA 278, the Hong Kong Court of Appeal (“CA”) ruled that the “back to back” wording in that case was not a “pay when paid” clause, but governed only...more

Kohrman Jackson & Krantz LLP

Avoiding Legal Pitfalls: Understanding Ohio’s Home Solicitation Sales Act

Are you a contractor who sells services directly to customers at their homes or outside your ordinary place of business? If so, do you know about Ohio’s Home Solicitation Sales Act? Understanding this law is crucial, and if...more

PilieroMazza PLLC

Top 10 Killer Construction Contract Clauses, Part 1: No Damages for Delay

PilieroMazza PLLC on

Those familiar with the construction industry know that construction projects are seldom, if ever, completed within the time originally anticipated at the project’s outset. Fortunately, prime contractors and lower-tier...more

BCLP

Shifting Contractual Risks and Managing Electronic Contracts

BCLP on

In this Insight, Shy Jackson takes a look at the decision of John Sisk and Son Limited v Capital & Centric (Rose) Limited [2025] EWHC 594 (TCC) where the court had to grapple with interpreting a contract which was kept on a...more

Gray Reed

Manufacturing Matters: Change Orders

Gray Reed on

Manufacturing construction is booming across Texas in early 2025, with Samsung’s landmark $17 billion semiconductor facility in Taylor, Texas leading the charge as part of a broader trend concentrated along major metro areas...more

Carlton Fields

Eleventh Circuit Holds Course of Construction Exclusion Applies to Water Damage as Project Was Not Fully Complete

Carlton Fields on

In Liberty Surplus Insurance Corp. v. Kaufman Lynn Construction Inc., the Eleventh Circuit Court of Appeals held that a “course of construction exclusion” in a commercial general liability precluded coverage for water damage...more

Bradley Arant Boult Cummings LLP

Don’t Be a Junkyard Dog: Put Your Agreements in Writing!

A federal judge in Louisiana has dished out some harsh criticism of contractors who don’t reduce their contracts to writing. The case involves the decommissioning of 26 orphaned oil and gas wells near Baton Rouge. The...more

BCLP

Battle of the Forms: A Recent Example

BCLP on

In this Insight, first published in the March 2025 edition of the NEC Newsletter, Shy Jackson considers the topic of the “battle of the forms” in the context of a recent Scottish case, Caledonia Water Alliance v Electrosteel...more

Gray Reed

Disrupted Operations – Owners Beware! – Part 2 (DAMAGES)

Gray Reed on

Liquidated damages are intended to provide predictability to the owner and contractor as to the financial consequence of not completing a project in a timely manner. Since liquidated damages are intended to compensate the...more

Snell & Wilmer

Lessons from the Idaho Supreme Court Decision in Moyer v. Doug Lasher Construction and Statute of Limitations Considerations

Snell & Wilmer on

The Idaho Supreme Court recently issued its decision in Moyer v. Doug Lasher Construction, Inc., clarifying several critical issues in construction law and the application of the statute of limitations on summary judgment....more

Snell & Wilmer

Recent Colorado Appeals Court Decision Provides Further Guidance on the Colorado Economic Loss Rule Doctrine

Snell & Wilmer on

In the recent decision of Veolia Water Tech., Inc. v. Antero Treatment LLC, 2024 COA 126 (Colo. App. 2024), the Colorado Court of Appeals addressed the “murky” application of the economic loss rule to the intentional tort of...more

Adams & Reese

“Hidden Ball Trick” – Yankees’ Aaron Judge Case Involving Deception Carries Lessons for Contractors

Adams & Reese on

The hidden ball trick is a baseball play in which the fielder fakes a throw to the pitcher, so that he can trick the runner into stepping off the base. The fielder then tags out the runner. It’s a deceptive move that can...more

Frantz Ward LLP

Oral Contract and Invalid Lien Spell Trouble for Contractor

Frantz Ward LLP on

Speedy Maintenance, LLC v. Windsor Tower, LLC, 2024-Ohio-5841 (2d Dist.) is a recent case concerning a dispute over repairs to a parking garage where Ohio’s Second District Court of Appeals confronted issues....more

Bradley Arant Boult Cummings LLP

General Contractor Defeats Owner’s Notice Argument and Prevails in Seattle Condo Dispute

The Washington Court of Appeals recently affirmed a jury verdict and $30 million judgment for general contractor Skanska. The case involves the construction of the 41-story Nexus condominium tower in downtown Seattle. As is...more

Porter Hedges LLP

How Long Does that “One Year Warranty” Last? Longer than You Might Think

Porter Hedges LLP on

If you ask owners, general contractors, or subcontractors how long the warranty lasts that they received or gave on a construction project, they will often tell you that they have a “one year warranty.” However, if the...more

Gray Reed

Manufacturing Matters: Controlling Construction Costs

Gray Reed on

Manufacturing construction is anticipating an uptick in 2025 with expected domestic economic protections and the continued consumer demand. Texas will remain a hotbed for this activity with continued business relocations,...more

Conn Kavanaugh

The Massachusetts Prompt Payment Act Continues to Have Harsh Consequences for Transgressors, Unwitting or Otherwise

Conn Kavanaugh on

With the exception of those living under rocks, construction professionals are well aware of the recent spate of litigation about the Massachusetts Prompt Pay Act. In 2022, the Massachusetts Appeals Court interpreted the Act...more

Frantz Ward LLP

Offset, Setoff, and State Trends in Withholding Clauses

Frantz Ward LLP on

States have been slowly clawing back at a higher-tier’s ability to withhold payments owed to its lower-tier subcontractors, aiming to protect subcontractors from undue financial hardship and ensure that payment disputes are...more

BCLP

JCT 2024 Contracts - Good Faith in Practice

BCLP on

Not everyone will be familiar with the 1994 Latham Report that advocated the use of good faith, but the government’s Construction Playbook and the equivalent private sector Trust and Productivity report are more recent...more

Saiber LLC

The Saiber Construction Law Column: December 2024

Saiber LLC on

The legal concept of “privity of contract” is a common law principle which provides that only parties directly involved in a contract can enforce its terms or be held liable for its obligations. This means that third parties...more

MG+M The Law Firm

Massachusetts Supreme Judicial Court to Address the Application of the Statute of Repose to Contractual Indemnification Claims

MG+M The Law Firm on

An issue of great importance to all construction project parties, including design professionals and contractors, is pending before the Massachusetts Supreme Judicial Court (SJC). In the matter of Trustees of Boston...more

BCLP

Recovering Adjudicators' Fees and Interest: Recent Guidance

BCLP on

In this Insight, first published in PLC, Yorkie Fong considers the decision in A&V Building Solution Ltd v J&B Hopkins Ltd [2024] EWHC 2295 (TCC), which clarified the binding nature of an adjudicator's decision on their fees...more

Bradley Arant Boult Cummings LLP

Court Separates Facts from Fiction – Lack of Supporting Project Documents Dooms Contractor

A recent decision from the U.S. District Court for the Southern District of Florida demonstrates how facts supported by documents generated during the project can be vital to prime contractor/subcontractor disputes. In...more

BCLP

HK High Court Refuses Leave to Appeal Against Interim Measures

BCLP on

In W v Contractor [2024] HKCFI 1452, the Hong Kong High Court dismissed an application for leave to appeal against the interim measures granted by an arbitrator to restrain an employer from calling on a bond in relation to a...more

Moritt Hock & Hamroff LLP

Contractor Prevails Against Owner In Arbitration Successfully Arguing Modification Of The Contract Based Upon The Parties’ Course...

Often, the performance by parties to a contract varies from the written terms and conditions of the contract in slight, immaterial ways. Occasionally, the parties’ performance, either individually or collectively, may vary...more

110 Results
 / 
View per page
Page: of 5

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide