News & Analysis as of

General Contractors Breach of Contract

Bradley Arant Boult Cummings LLP

Court Affirms $1 Nominal Damage Award in Wind Farm Construction Dispute

Court Affirms $1 Nominal Damage Award in Wind Farm Construction Dispute The general contractor on the 60-turbine wind farm project in Good Hope, Illinois, is entitled to collect a whopping $1 on its cost-to-complete claim...more

J.S. Held

Lessons Learned from the Recent Ruling on Contractor Responsibilities in Delay and Inefficiency Claims

J.S. Held on

The recent ruling in Berkley Insurance Company v. Suffolk Construction Company, issued by the United States District Court for the Southern District of Florida, has highlighted several significant lessons for subcontractors,...more

Bradley Arant Boult Cummings LLP

Proportional Fault Indemnification Provisions Held Enforceable in Alabama

The Alabama Supreme Court found that an indemnification provision was enforceable that required a subcontractor to indemnify a general contractor on a proportional-fault basis against liability for death or personal injury. ...more

Bradley Arant Boult Cummings LLP

Whiting-Turner Prevails in Wrongful Termination Dispute

A California appeals court has upheld a $5 million award in favor of Whiting-Turner Contracting Company and against the owner of a 12-story, Virgin-brand hotel in San Francisco. Whiting-Turner agreed to construct the hotel...more

Marshall Dennehey

General Contract May Be Entitled to Award of Attorneys’ Fees Against Subcontractor, Despite Jury’s Apportionment of Damages

Marshall Dennehey on

Babin Builders and Development Inc. v. Quinones, Fla. 1st DCA, No. 1D2022-4103, February 12, 2025 - For construction defect litigation, many times we are called into action to defend a subcontractor who has been included as a...more

Bradley Arant Boult Cummings LLP

Yes, Damages for Delay: Court Permits Delay Damage Claim to Proceed

A federal court in upstate New York is permitting a subcontractor’s delay claim to proceed notwithstanding a “no damages for delay” provision in the subcontract. The case, The Pike Company, Inc. v. Tri-Krete, Ltd., involves...more

Spilman Thomas & Battle, PLLC

Subcontracting Lessons on Indemnity Provisions, Consistency of Contract Terms and Estoppel From the SC Court of Appeals

The Retreat at Charleston National Country Club Home Owners Ass’n, Inc. v. Winston Carlyle Charleston National, LLC, S.C. App. Case No. 2021-001050, Opinion No. 6099 (Feb. 12, 2025) Key Takeaways: Case Summary (for those of...more

Bradley Arant Boult Cummings LLP

General Contractor Defeats Owner’s Notice Argument and Prevails in Seattle Condo Dispute

The Washington Court of Appeals recently affirmed a jury verdict and $30 million judgment for general contractor Skanska. The case involves the construction of the 41-story Nexus condominium tower in downtown Seattle. As is...more

Saiber LLC

The Saiber Construction Law Column: December 2024

Saiber LLC on

The legal concept of “privity of contract” is a common law principle which provides that only parties directly involved in a contract can enforce its terms or be held liable for its obligations. This means that third parties...more

Bradley Arant Boult Cummings LLP

Court Separates Facts from Fiction – Lack of Supporting Project Documents Dooms Contractor

A recent decision from the U.S. District Court for the Southern District of Florida demonstrates how facts supported by documents generated during the project can be vital to prime contractor/subcontractor disputes. In...more

Robinson+Cole Construction Law Zone

Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court

Earlier this year, the Associated Subcontractors of Massachusetts hired Robinson+Cole attorney Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before...more

Hinckley Allen

Massachusetts Supreme Judicial Court Releases Much-Anticipated Prompt Pay Act Decision

Hinckley Allen on

On June 17, 2024, the Massachusetts Supreme Judicial Court (“SJC”) issued its decision in Business Interiors Floor Covering Business Trust v. Graycor Construction Company, Inc. (“Graycor”).  The SJC’s decision addresses an...more

Nutter McClennen & Fish LLP

Massachusetts Supreme Judicial Court Interprets Prompt Pay Act for the First Time

On June 17, 2024, the Supreme Judicial Court (SJC) issued its first decision interpreting the Massachusetts Prompt Pay Act (the “PPA”). In Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc.,[1]...more

Stoel Rives -  Ahead of Schedule

The Role of Liquidated Damages Provisions in Construction Contracts

Considering all that can go wrong on a construction site, it can seem like a miracle that anything is ever built. Construction projects can be massive undertakings, often with millions of dollars at stake, requiring the...more

Bradley Arant Boult Cummings LLP

Court Rejects Contractor’s Claim That COVID-19 Rendered Performance Impossible

A fundamental premise of contract law is that promises must be kept. If legally enforceable promises or “contracts” are not kept, courts may step in to enforce them by ordering performance, awarding damages, or granting some...more

Bradley Arant Boult Cummings LLP

Liquidated Damages Disproportionate to Actual Damages Deemed Unenforceable

Construction contacts often include provisions that provide for pre-determined or “liquidated” damages in the event of a breach. Such provisions can provide certainty to the parties as to the consequences of a breach and can...more

BCLP

Can liquidated damages clauses set general cap?

BCLP on

A pair of cases in the past two years have come to opposite conclusions about whether general damages can be capped by contract provisions for liquidated damages. Liquidated damages clauses are a common feature of...more

Bradley Arant Boult Cummings LLP

Damages for Buyer’s Breach of Contract for the Sale of Real Property: Court Rejects Contractor’s Creative Damages Theory in...

Who said legal opinions have to be boring? Not Judge Terrence L. Michael of the U.S. Bankruptcy Court for the Northern District of Oklahoma, who last week issued a colorful opinion rejecting a home builder’s creative claim...more

Bradley Arant Boult Cummings LLP

Limitation of Liability in Extra Work Order Trumped by Subcontract

A federal court in Louisiana last week refused to enforce a limitation of liability provision included in an extra work order holding that it was trumped by the parties’ subcontract (see Planet Construction v. Gemini...more

Stoel Rives -  Ahead of Schedule

Efforts Expected of a Contractor When Efforts Clauses Are in Dispute

Originally published by the Daily Journal of Commerce on May 18, 2023. You will often see in construction contracts terms directing the contractor to use “best efforts” or “reasonable efforts” or “commercially reasonable...more

Stoel Rives -  Ahead of Schedule

What Parties Ought To Consider When Considering Arbitration Provisions

When reviewing a proposed design or construction contract, the responding party will often do a cursory check to see whether the contract proposes arbitration or litigation for dispute resolution. So long as the proposed...more

Davis Wright Tremaine LLP

Do I Need a Contractor License to Enter Into a Development Management Agreement?

Looking at statutes and case law from Washington and California for the answer - Whether a developer is required to obtain a contractor license to enter into a development management agreement ("DMA") must be viewed...more

Bradley Arant Boult Cummings LLP

Willful or Wanton Conduct Not Enough to Overcome Economic Loss Rule Says Colorado Court

n Mid-Century Insurance Co., v. HIVE Construction, Inc., a Colorado court of appeals recently reversed the decision of a lower court that had refused to apply the economic loss rule to a negligence claim alleging wanton or...more

Davis Wright Tremaine LLP

Oregon Ruling Calls Into Question Quantum Meruit Claims in Construction Cases

On February 15, 2023, the Oregon Court of Appeals ruled that an excavation subcontractor, plaintiff Kizer Excavating Co., ("Kizer") could not maintain a quantum meruit claim against a general contractor, defendant Stout...more

Miller Nash LLP

Recession Planning: Prepare Ahead If Contract Terminated for Convenience

Miller Nash LLP on

With a recession casting a dark shadow on the new year and news of various projects being put on hold, it is a good time to revisit the checklists on what to do if your contract is terminated for convenience....more

94 Results
 / 
View per page
Page: of 4

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide