On March 30, 2025, FERC approved revisions to Southwest Power Pool, Inc.’s (“SPP”) Open Access Transmission Tariff (“Tariff”) and Governing Documents to allow nine entities (“Expansion Members”) in the Western Interconnection...more
On February 28, 2025, FERC granted a request by Holtec Palisades, LLC (“Holtec”) for waiver of certain provisions of the Midcontinent Independent System Operator, Inc. (“MISO”) Open Access Transmission, Energy and Operating...more
On February 20, 2025, FERC found that the PJM Interconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“OATT”) appears to be unjust and unreasonable because it does not address with clarity or consistency the rates,...more
On January 21, the Connecticut Public Utilities Regulatory Authority (“PURA” or the “Authority”) opened Docket 25-01-27 to investigate interconnection process modifications. On February 3, 2025, in its Notice of Proceeding,...more
On October 17, 2024, the Federal Energy Regulatory Commission (FERC) issued Order No. 904, Compensation for Reactive Power Within the Standard Power Factor Range (the “Final Rule”), determining it unjust and unreasonable for...more
On July 19, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an Order denying Tenaska Clear Creek Wind, LLC’s (“Clear Creek”) challenges to FERC’s orders allowing the...more
On September 29, 2023, FERC accepted part of Arizona Public Service Company’s (“APS”) proposed interconnection queue reforms to transition from a first come, first served cluster study process to a first ready, first served...more